Adur District Council / Worthing Borough Council
Joint Strategic Committee, Thursday 5 February 2026 at 6.30pm

Worthing Pier: Virement of Capital Budget for the Reinstatement of Permanent Supports Project

Approved Committee 1 paper

AI summaryJoint committee approves £668,700 budget transfer to permanently repair damaged Worthing Pier piles, pausing the pier sprinkler scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBudget moved, sprinkler scheme paused
Money£668,700 virementPlus £275,000 already approved, total £943,700
What happens nextInvestigatory works in February 2026Tender process to follow for repair contract
Who it affectsWorthing Pier users and tenantsPier businesses, anglers, visitors, residents

What was decided

Members approved the virement of £668,700 from the Pier Sprinkler System project in the 2025/26 capital programme to fund the Reinstatement of Permanent Pier Supports. Report P11

Members authorised the resulting pause of the Sprinkler System project, with fire suppression upgrades to be reviewed once the pier's structure is reinstated. Report P4, P14

Why

A pile was found broken and hanging from the main framework during an inspection on 4th October 2024, with the base sheared and shifted north. Report P5

Independent engineers certified the temporary support framework for an initial two-year lifespan, so permanent reinstatement is needed to secure the structure long term and protect its heritage character. Report P6, P7, P10

Officers advise the sprinkler upgrade is not essential at this time, as manual firefighting capabilities and management procedures are sufficient for statutory compliance. Report P13

What happens next

Intrusive investigatory works will be carried out in February 2026 to assess whether existing below-ground piles can be reused or new piles are needed. Report P8, P16

A tender process for the repair will be run once the investigatory works establish the project specification, with the resulting contract handled under standard project governance. Report P17, P21

A communications plan will be enacted to engage tenants and stakeholders once the timeline and nature of repair works are confirmed. Report P16

The money

  • £668,700 Virement from Pier Sprinkler System project (2025/26 capital programme) Report P11, P19
  • £275,000 New capital allocation for 2026/27, approved by JSC in December 2025 Report P8, P18
  • £943,700 Total project budget for Reinstatement of Permanent Pier Supports Report P17, P20

Options considered

  • Chosen: Vire £668,700 from Sprinkler Scheme to Reinstatement of Permanent Pier Supports. Bridges the gap to the £943,700 total project requirement and prioritises long-term structural security before further upgrades. Report P11, P12
  • Rejected: Continue with the Sprinkler System scheme. Fire risk assessments confirm existing manual capabilities are sufficient for statutory compliance, so the upgrade is not essential at this time. Report P13, P14

Implications

  • Financial: The Pier Booster Pump and Sprinkler System Scheme loses its £668,700 capital allocation, removing the funding allocated to that project. Report P11, P12
  • Financial: A single capital cost centre of £943,700 will be held for the reinstatement works, enabling a tender process. Report P17
  • Legal: Officers rely on Section 111 of the Local Government Act 1972, the best value duty under Section 3(1) of the Local Government Act 1999, contract-making powers under Section 1 of the Local Government (Contracts) Act 1997, and the Procurement Act 2023. Report P22, 7.2, 7.3, 7.4
  • Risk: Previous pier closures have raised concerns about unauthorised access; safety around any worksite will be managed by the contractor in line with appropriate legislation, with security patrols and CCTV as mitigations. Report P37
  • Other: The report acknowledges that the sequencing of budget decisions was suboptimal and notes opportunities for improvement in future virements. Report P8

Who and where

  • Tenants and businesses on Worthing Pier Report P16, P31
  • Pier visitors, anglers and town centre users affected by the current closure Report P34
  • Local residents of Adur and Worthing Report P16, P31

Timeline

  • Following October 2024 inspection: Temporary support framework installed, certified for an initial two-year lifespan. Report P6, P7
  • 4th October 2024: Inspection found a broken pile hanging from the pier framework; independent engineers HOP Consulting engaged. Report P5
  • December 2025: JSC approved a new £275,000 capital bid for pier structure reinstatement in the 2026/27 capital budget. Report P8, P18
  • February 2026: Intrusive investigatory works planned to assess below-ground piling. Report P8, P16
  • 5 February 2026: Joint Strategic Committee considered the virement report.
  • 5.00pm on 17 February 2026: Call-in deadline for the decision.

Plain English for the jargon

  • Virement: Transfer of budget from one spending heading to another within a council's approved budget.
  • Capital programme: The council's planned spending on long-term assets and projects, as opposed to day-to-day revenue spending.
  • JSC: Joint Strategic Committee of Adur District Council and Worthing Borough Council.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/102/25-26

Resolved

That the virement of £668,700 from the Pier Sprinkler System project in the 2025/26 capital programme to create an in-year budget for the Reinstatement of Permanent Pier Supports as detailed in Section 4 of this report be approved. 2. That the resulting pause of the Sprinkler System project as highlighted in 4.1.3 be authorised Call In: The call-in deadline for decisions will be 5.00pm on 17 February 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose 1.1.​ This report seeks approval for a virement of £668,700 of the capital budget originally allocated to the Pier Sprinkler scheme in order to fund the planned project to reinstate the damaged structure at Worthing Pier. 1.2.​ The Virement is requested to secure the long term stability of the section of deck which was subject to temporary repair in 2024. 1.3.​ This report addresses the context of the need for and the impact anticipated of approving this virement.

2.​ Recommendations 2.1.​ Members are asked to:

2.1.1.​ Approve the virement of £625,000 from the Pier Sprinkler System project in the 2025/26 capital programme to create an in-year budget for the Reinstatement of Permanent Pier Supports as detailed in Section 4 of this report.

2.1.2.​ Authorise the resulting pause of the Sprinkler System project as highlighted in 4.1.3. 3.​ Context

3.1​ The Initial Incident ​ 3.1.1​ Following a report of damage to the Pier, the Borough’s Engineering Services Team undertook an inspection on 4th October 2024. A pile was found to be broken and hanging from the main framework; the base of the pile had sheared and shifted north. Independent structural engineers, HOP Consulting (HOP), were requested to inspect the defect. HOP was selected due to their working knowledge of the Pier from previous inspections and a 2018 condition report.

3.1.2​ The actioned response was a temporary support framework designed to carry the loads of the failed piles. Supported by its own independent piling, this framework braces the deck section, diverting weight away from the damaged area.

3.1.3​ HOP advised that, given its exposure to tidal forces and the elements, the temporary works could be certified for an initial two-year lifespan. Since the completion of these emergency works, the Council’s Engineering Team has been investigating options for the full reinstatement of the original structure. This aims to restore the character of the Pier as a heritage asset and secure the long-term future of the damaged section beyond the lifespan of the temporary structure.

3.1.4​ Intrusive investigatory works will be undertaken in February 2026 to understand the suitability of reusing the existing below ground piles or the need to repile. ​ 3.1.5​ The 2026/27 Capital Budget approved by the Joint Strategic Committee (JSC) in December 2025 included a new capital bid of £275k allocated to the reinstatement of the Pier Structure. This report seeks to consolidate the remaining funding required to deliver the full scheme. 3.1.6​ This report is required as part of the budget was not assembled at the time the 2026/27 budget was requested. A review of the movements has confirmed that this was compliant. However, it is recognised that the specific sequencing of these decisions was suboptimal and, in retrospect, unhelpful to the wider context. We acknowledge that a different chronological approach would have been preferable, and these opportunities for improvement have been noted for future virements of this nature. ​ 4.​ Issues for consideration

4.1​ Budget Consolidation

4.1.1​ The Council’s Engineering Team in consultation with the Pier Maintenance Specialists has developed estimates for the full, permanent reinstatement of the structure. This scheme aims to restore the character of the Pier as a heritage asset and secure the long-term future of the damaged section.

4.1.2​ Members are asked to approve the virement of £668,700 from the capital budget originally allocated to the Pier Booster Pump and Sprinkler System Scheme. This transfer is critical to bridge the gap between the newly approved £275k and the total project requirement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Worthing Pier: Virement of Capital Budget for the Reinstatement of Permanent Supports ProjectAgenda 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
SC
Councillor Sophie CoxWorthing Member, present
RG
Councillor Rita GarnerWorthing Member, present
ÖB
Councillor Ödül BozkurtWorthing Member, present
DF
Councillor Dom FordWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
VW
Councillor Vicki WellsWorthing Member, absent
RW
Councillor Rosey WhorlowWorthing Member, present
JG
Councillor Jeremy GardnerChair, present
LC
Councillor Lee CowenAdur Member, absent
BA
Councillor Becky AllinsonVice-Chair, present
SJ
Councillor Saffa JanAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present

All 13 on the meeting page

On this subject at Adur & Worthing

Search all
  1. Worthing Pier: Virement of Capital Budget for the Reinstatement of Permanent Supports ProjectThis decision
  2. Items Raised under Urgency Provisions - Worthing Pier UpdateNoted
  3. Worthing Pier - Emergency WorksNoted

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies