Adur District Council / Worthing Borough Council
Joint Strategic Committee, Tuesday 14 July 2026 at 6.30pm

Refurbishment of Eskan Court, Milton Keynes, to support income generation and to comply with MEES regulations as part of Adur District Council’s SPIF Portfolio

Approved Committee 1 paper

AI summaryAdur and Worthing Joint Strategic Committee approves £630,000 capital budget to refurbish vacant office suite at Eskan Court, Milton Keynes, to meet energy rules and attract a new tenant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEskan Court, Milton Keynes, SPIF asset
Money£630,000 capital budgetIncludes £180,000 from Property Risk Reserve
What happens nextSavills to run procurementService Director authorised to award contract
Who it affectsAdur SPIF portfolioGround floor vacant suite, 6,976 sq ft

What was decided

The Joint Strategic Committee approved increasing the existing SPIF capital budget to £630,000 for the Eskan Court refurbishment. Report P7, P43

Members approved using £180,000 from the Adur Property Risk Reserve as part funding for the increased capital budget. Report P8, P45

Authority was delegated to the Service Director for Place and Economy to award the works contract, provided costs stay within the approved budget, after Savills runs a compliant procurement exercise under its existing managing agent contract. Report P10

Why

The 6,976 sq ft ground floor suite has been vacant since 2022, and the council is meeting holding costs including its share of service charges, business rates, repairs and lost rent. Report P12, P24, P46

The suite is rated EPC D, below the legal minimum required for letting from 2027 under Minimum Energy Efficiency Regulations, so mechanical and electrical upgrades are needed to reach EPC B. Report P20, P29, P62

Market feedback and agent benchmarking indicate the space and common parts do not present well enough to attract quality tenants without refurbishment, and the council received a £157,000 dilapidation payment from the outgoing tenant in 2023 to contribute to costs. Report P4, P16, P19, P25

What happens next

Savills will carry out a compliant procurement exercise for a contractor to deliver the refurbishment works, with the contract awarded by the Service Director for Place and Economy within the approved budget. Report P10

A building control application will be made for aspects of the work, and no planning consent is needed. Report P39

The call-in deadline for the decision is 5.00pm on 23 July 2026.

The money

  • £630,000 Total capital budget for the refurbishment, including a ~5% contingency Report P7, P43
  • £250,000 From the existing Adur SPIF capital budget approved in the 2025/26 programme Report P44
  • £200,000 From the property's sinking fund accrued via tenant service charges, subject to RICS Code permissions Report P44
  • £180,000 Contribution from the Adur Property Risk Reserve to the capital budget Report P8, P45
  • £157,000 Dilapidation payment received from the outgoing tenant in 2023, contributing to refurbishment costs Report P4
  • £1,996,951 Current balance of the Property Void Risk Reserve before the transfer Report P45
  • £1,816,951 Projected balance of the Property Void Risk Reserve after the £180,000 transfer Report P45

Options considered

  • Rejected: Do nothing: keep the suite on the market as it is. Agent advice is the space and common parts do not present well enough; holding costs continue. Report P28, P32
  • Rejected: Do less: refurbish only the letting space. Impending 2030 EPC B requirement means mechanical and electrical work is needed regardless; would be cosmetic only and not aligned to environmental or commercial reality. Report P29
  • Rejected: Strip out the suite to avoid business rates. Requires capital expenditure, does not avoid service charge costs, and would make quick reletting impossible. Report P29
  • Rejected: Freehold disposal of part or all of the property. Vacant possession value is less than the 2019 purchase price for the fully let investment; the primary tenant wishes to stay, and SPIF assets are held to generate income. Report P30
  • Chosen: Refurbish the suite to meet market expectations and MEES compliance. Stops holding cost outflow, enables letting at better rents, and meets legal EPC requirements. Report P23, P24, P33, P62

Implications

  • Financial: Capital budget rises from £250,000 to £630,000, funded by existing SPIF budget, the property's sinking fund, and a £180,000 draw from the Property Risk Reserve, which would reduce from £1,996,951 to £1,816,951. Report P43, P44, P45
  • Legal: The refurbishment is needed to comply with Minimum Energy Efficiency Regulations requiring an EPC B standard for letting, and the suite is currently rated EPC D. Report P20, P62
  • Legal: Expenditure of public funds must comply with the Council's Contract Standing Orders and the Subsidy Control Act 2023; procurement will be run by Savills under an existing managing agent contract. Report 7.3, P10
  • Risk: Primary risk is the suite failing to let after refurbishment, considered unlikely by agents given scarce new office supply. Secondary risk is contractor failure, to be mitigated by credit and trading checks. Report P35, P36
  • Climate: Refurbishment will upgrade an outdated heating and ventilation system and raise the energy performance rating from EPC D to EPC B, achieving compliance with MEES legislation. Report P62
  • Staffing: The Service Director for Place and Economy is given delegated authority to authorise and enter into the works contract within the approved budget. Report P10

Who and where

  • Adur District Council as owner of the SPIF asset and recipient of rental income Report P11, P46
  • Alliance Automotive, the main tenant of the upper floor, whose lease ends in January 2027 and who have indicated they wish to stay Report P12, P30
  • Future tenants of the refurbished ground floor suite at Eskan Court, Campbell Park, Milton Keynes, MK9 4AN Report P12, P14
  • Adur SPIF programme, reviewed regularly with the Cabinet Member for Resources and scrutinised at the Economy and Regeneration Mission Board Report P40, P41

Timeline

  • April 2018: Eskan Court purchased as part of the Adur SPIF portfolio Report P11
  • 2022: Former tenant vacated the 6,976 sq ft ground floor suite Report P12
  • 2023: Council received a £157,000 dilapidation payment from the outgoing tenant; Savills carried out a tender process and provisionally selected a contractor Report P4, P26
  • 2026: Cost plan updated for 2026 by the provisionally selected contractor, whose price is subject to revision after three months Report P26
  • From 2027: Legal minimum EPC for letting applies under MEES regulations Report P20
  • 5.00pm on 23 July 2026: Call-in deadline for this decision
  • January 2027: Alliance Automotive's lease ends Report P30
  • 2030: Requirement to let with an EPC B or better takes effect Report P29

Plain English for the jargon

  • SPIF: Strategic Property Investment Fund, the Adur District Council vehicle for investing in income-producing commercial property to support council services.
  • MEES: Minimum Energy Efficiency Regulations, which set the legal minimum Energy Performance Certificate rating for letting commercial property.
  • EPC: Energy Performance Certificate, rating the energy efficiency of a building on a scale from A (most efficient) to G (least efficient).
  • RICS Code: The Royal Institution of Chartered Surveyors' professional and ethical standards, referenced here in relation to drawing on the service charge sinking fund.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/26/26-27

Resolved

That the increase of the existing Capital Budget for the Strategic Property Investment Fund be (intended for this project) be approved to £630,000 as detailed in Section 7 of this report 2. That the use of £180,000 from the Adur Property Risk Reserve be approved as part funding for the increase in capital budget for the proposed work, detailed in section 7. 3. That it be noted that the current costs associated with holding the vacant space amount to our share of Landlord’s service charge, business rates and repairs, plus lost rent, in the Exempt Appendix, as part of the decision to refurbish the asset. 4. That it be noted that under an existing Managing Agent Contract with Savills as detailed in the Exempt Appendix; Savills will carry out a compliant procurement exercise for the contractor to deliver the works and to delegate authority to the Service Director for Place & Economy to authorise and enter into a contract for the Works providing they are within the authorised budget. Call In: The call-in deadline for decisions will be 5.00pm on 23 July 2026.
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose

1.1.​ The purpose of this report is to outline to Members that Eskan Court, Milton Keynes, forms part of the Adur Strategic Property Investment Fund (SPIF) portfolio and to outline its current position as an asset for the Council.

1.2.​ The report also outlines the need for Eskan Court to be refurbished in order to attract a new tenant for the asset to continue to generate income for the Council. It should be noted that this asset was purchased in 2019 and therefore investment is required due to wear and tear since the acquisition. In addition, in order to re-let any refurbishment also needs to cater for MEES (Minimum Energy Efficiency Regulations) compliance.

JAW/0xx/22-23 1.3.​ The report and the exempt appendix, provide Members with the financial appraisal of the current situation, while vacant, and also provides the financial case for the refurbishment itself. As part of that assessment, Members will note as set out in the report, that the Council received a dilapidation payment from the outgoing tenant of £157,000 in 2023, which will contribute to the costs of the refurbishment works to enable this project to go forward.

2.​ Recommendations

2.1.​ The Joint Strategic Committee is recommended:-

2.1.1.​ To approve the increase of the existing Capital Budget for the Strategic Property Investment Fund (intended for this project) to £630,000 as detailed in Section 7 of this report.

2.1.2.​ To approve the use of £180,000 from the Adur Property Risk Reserve as part funding for the increase in capital budget for the proposed work, detailed in section 7.

2.1.3.​ To note the current costs associated with holding the vacant space amount to our share of Landlord’s service charge, business rates and repairs, plus lost rent, in the Exempt Appendix, as part of the decision to refurbish the asset.

2.1.4.​ To note that under an existing Managing Agent Contract with Savills as detailed in the Exempt Appendix; Savills will carry out a compliant procurement exercise for the contractor to deliver the works and to delegate authority to the Service Director for Place & Economy to authorise and enter into a contract for the Works providing they are within the authorised budget. 3.​ Context

3.1.​ The property is a detached two storey office building situated in parkland between the centre of the City of Milton Keynes and the M1 motorway. It was purchased in April 2018 as part of the Adur District Council Strategic Property Investment Fund (SPIF). The Fund exists to make investments in income producing commercial property to support council services.

3.2.​ The property is income producing at present as it is majority let, the main tenant is Alliance Automotive. However, the 6,976 (gross area) sq ft ground floor suite is vacant since the former tenant vacated in 2022. The associated financials of this asset can be found in the exempt appendix.

3.3.​ The vacant space is being actively marketed for lease by a national commercial agent with a local office. The following brochure comprises our ground floor suite plus areas put up for sublet by Alliance Automotive who are our primary tenant in the remainder of the building.

Office Commercial Property For Rent in Eskan Court, Campbell Park, Milton Keynes, MK9 4AN | LSH

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Refurbishment of Eskan Court, Milton Keynes, to support income generation and to comply with MEES regulations as part of Adur District Council’s SPIF PortfolioReport 2.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JG
Councillor Jeremy GardnerChair, present
BA
Councillor Becky AllinsonVice-Chair, present
LC
Councillor Lee CowenAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AL
Councillor Adrienne LoweAdur Member, present
CB
Councillor Caroline BaxterWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
SC
Councillor Sophie CoxWorthing Member, absent
DF
Councillor Dom FordWorthing Member, present
MM
Councillor Martin McCabeWorthing Member, present

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies