Joint Strategic Committee, Tuesday 14 July 2026 at 6.30pm

Albion Street Housing Scheme Update Report

Approved Committee 1 paper

AI summaryAdur and Worthing Joint Strategic Committee approves £3.2 million budget increase for remedial works on the 49-home Albion Street housing scheme, funded partly by virements from existing 2026/27 capital budgets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor remedial works on 49-home Albion Street scheme
Money£3.2 millionTotal estimated cost: £2.1m works, £0.4m fees, £0.7m interest
What happens nextProcurement and works beginOfficers authorised to proceed as a matter of urgency
Who it affectsFuture tenants on housing register49 affordable homes in Adur affected by defects

What was decided

Approved a £2 million virement in the 2026/27 capital programme to the Albion Street project budget, funded by £450,000 from Electrical Works, £400,000 from Reactive Works, £900,000 from Kitchens and Bathrooms, and £250,000 from Structural Work budgets. Report P9

Approved a £1.2 million budget for the remaining estimated remedial works cost from the overall 2027/28 capital budget as a priority project. Report P10

Delegated authority to the Corporate Director for Housing and Communities to procure, enter into or extend contracts, and seek and accept grant funding to deliver the works within the approved budget. Report P12

Why

Intrusive surveys revealed significant construction defects, including porous brickwork, defective cavity trays, and inadequate drainage, causing water ingress in 25 of the 49 units and making the building unsafe for occupation. Report P2, P17, P33

The original contractor, Westridge Construction Ltd, became insolvent in October 2023, leaving the Council unable to enforce remediation of poor workmanship through normal contractual means. Report P15, P23, P27

The Council must meet statutory obligations under the Building Safety Act 2022 and assemble the required 'golden thread' of safety documentation before tenants can occupy. Report P4, P31, P74

What happens next

Officers to proceed with procurement and execution of essential remedial works as a matter of urgency, prioritising external brickwork sealing during the drier summer months. Report P11, P52

A new Planning Application is required for the proposed works, with determination expected to take around 16 weeks at Committee. Report P37, P41

A further report covering final remediation outcomes and lessons learned will be presented to the Joint Strategic Committee in September; a business case will be developed for Homes England to seek additional grant funding. Report P18, P36, P69

The money

  • £2 million Virement to Albion Street capital project budget in 2026/27 Report P9
  • £1.3 million For construction works and professional fees within the £2m virement Report P9
  • £700,000 Capitalised interest within the £2m virement Report P9
  • £450,000 Funded from Electrical Works budget Report P9
  • £400,000 Funded from Reactive Works budget Report P9
  • £900,000 Funded from Kitchens and Bathrooms budget Report P9
  • £250,000 Funded from Structural Work budget Report P9
  • £1.2m Budget for remaining estimated cost from 2027/28 capital programme Report P10
  • £3.2 million Total estimated cost of remedial works (£2.1m construction, £0.4m professional, £0.7m capitalised interest) Report P5, P35, P64
  • £1.3m Capital expenditure in last financial year, including £698K capitalised interest Report P61
  • £1.776m Budget virement approved by JSC on 1 February 2024 Report P24
  • £998k Anticipated insurance claim recovery against insolvency bond Report P24

Options considered

  • Chosen: Carry out comprehensive rectification programme immediately to address root causes. Units cannot be safely occupied; works are weather-dependent and must be completed in summer; failing to act breaches statutory Building Safety Act 2022 obligations and increases void losses Report P37, P51, P52
  • Rejected: Do nothing or delay decisions. Would result in ongoing void loss, continued breach of statutory building safety obligations, and failure to address critical demand for affordable housing Report P51

Implications

  • Financial: Estimated £3.2m additional cost, but figure may be higher if intrusive works reveal further unforeseen defects; costs subject to subcontractor pricing and product availability. Report P45, P65
  • Financial: Capital programme reprioritised: fire remedial works, kitchen and bathroom replacements, mechanical extraction installations, and other health and safety work to be delivered first, with remaining programme phased over 20 months. Report P7, P54
  • Financial: A business case is being developed for Homes England to seek additional grant funding and mitigate the financial impact on the Housing Revenue Account (HRA). Report P36, P47, P69
  • Legal: Council must meet statutory obligations under the Building Safety Act 2022 and assemble the required 'golden thread' of safety documentation; powers under Localism Act 2011 and Local Government Act 1999 cited. Report P70, P71, P74
  • Risk: Risks identified across planning (new application required, 16-week determination), building control, financial (cost overruns), operational/technical (weather dependency), funding (Homes England bid may be unsuccessful), and regulatory compliance. Report P40, P41, P44, P45, P46, P47, P48
  • Climate: Remediation approach improves the existing building rather than rebuilding, reducing waste and carbon impact; replacement insulation and brickwork specification to address damp issues long-term. Report P84
  • Equalities: Project helps address housing inequality by providing 49 affordable homes for people on the housing register, including households with protected characteristics most affected by lack of affordable housing. Report 2.2, P81
  • Other: A lessons-learned report will be presented to the Joint Strategic Committee in September, covering the final remediation outcomes and comprehensive analysis of identified lessons. Report P18

Who and where

  • Future residents of 49 affordable homes at Albion Street Report P1, P14
  • Current tenants on the housing register waiting to occupy the development, who have been offered the option to return to the Choice Based Lettings system or continue waiting Report P8, P38
  • Households on the Adur housing register requiring affordable homes in Sompting, Lancing, Shoreham and Fishersgate areas Report P14, 2.2
  • Existing Adur Homes tenants whose planned improvement programmes (kitchens, bathrooms, electrical, structural works) may be rescheduled to fund the virements Report P7, P54
  • Local construction sector, which will benefit from the remedial works activity Report P76

Timeline

  • April 2019: Adur District Council resolved to terminate agreement with private developer and assume direct control of Albion Street site Report P20
  • March 2021: Construction of the 49 apartment scheme commenced Report P22
  • December 2022: Council formally granted the contractor an extension of time due to Covid-19, material/labour shortages, adverse weather, and drainage issues Report P22
  • October 2023: Contract with Westridge Construction Ltd terminated following the company's insolvency Report P23
  • 1st February 2024: Joint Strategic Committee approved a £1.776m budget virement for the recovery strategy Report P24
  • July 2025: Non-material amendment to Planning Permission approved for top floor leak remediation Report P28
  • Late 2025: Cladding works completed; it became apparent water ingress was far more extensive than initially identified Report P29
  • Early 2026: Pre-occupation inspections identified new damp issues and persistent water ingress; building deemed unsafe for occupation Report P29, P30
  • 2026/27: Phased capital expenditure: £2m within current capital programme Report P7, 7.6
  • 2027/28: Remaining £1.2m to be accommodated within capital budget as a priority project Report P7, P10, 7.7
  • Summer months: Critical external works (e.g. masonry sealing) prioritised to be completed during drier weather Report P46, P52
  • Approximately 16 weeks: Expected determination time for the new Planning Application at Committee Report P37
  • September: Further report on final remediation outcomes and lessons learned to be presented to Joint Strategic Committee Report P18

Plain English for the jargon

  • Albion Street development: A 49-home affordable housing scheme in Adur, arranged in two blocks with lift access, originally contracted to Westridge Construction Ltd
  • Virement: The transfer of budget from one capital scheme to another within the same financial year
  • Building Safety Act 2022: Legislation setting stringent safety standards for residential buildings, including the requirement to maintain a 'golden thread' of safety documentation
  • Golden thread: The complete record of safety documentation required by the Building Safety Act 2022, which the original contractor's insolvency hindered assembling
  • HRA (Housing Revenue Account): A local authority account ring-fenced for spending on income from rents and service charges on council housing
  • JSC (Joint Strategic Committee): The Joint Strategic Committee of Adur District Council and Worthing Borough Council
  • CHoSS (Council Housebuilding Support Service): A service providing free consultancy advice to councils, used here to develop a business case for Homes England funding
  • RIBA Stages 4-5: Royal Institute of British Architects design stages covering technical design and construction
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemJSC/22/26-27

Resolved

That the following virements be approved in the 2026/27 capital programme of: a. £2 million to Albion Street capital project budget. (£1.3 million for construction works and professional Fees and £700,000 capitalised interest). Funded by: b. £450,000 from Electrical Works budget, c. £400,000 from the Reactive Works budget, d. £900,000 from the Kitchens and Bathrooms budget, and e. £250,000 from the Structural Work budget. 2. That a budget for £1.2m be approved for the remaining estimated cost to complete the remedial works for the Albion Street scheme from the overall 2027/28 capital budget allowance as a priority project within the programme. 3. That it be noted that this will enable officers to proceed with the procurement and execution of essential remedial works as a matter of urgency as we continue to progress the building toward a habitable condition. 4. That authority be delegated to the Corporate Director for Housing and Communities to procure and enter into or extend all necessary contracts and associated legal documentation and to seek and to accept any relevant grant funding in order to deliver these works and enable ... view the full minutes text for item JSC/22/26-27
Word for word from the decision Adur & Worthing published for this meeting. Source: democracy.adur-worthing.gov.uk

Follow this further

Built from Adur & Worthing's papers

What the report saysPro

Report to Joint Strategic Committee

Executive summary

1.​ Purpose 1.1.​ The Albion Street development will provide 49 energy-efficient, desirable homes. It forms part of what has been, up until this point, a largely successful development programme for Adur Homes, which has resulted in the provision of 26 homes in Sompting, Lancing, Shoreham and Fishersgate for local residents since 2024.

1.2.​ However, a number of issues and challenges have come to light with this development, following the insolvency of the contractor. Due to issues with water penetration in several locations within the last several months, extensive intrusive investigations were commissioned to confirm the building's integrity, which have revealed significant and complex construction defects that must be resolved before the homes can be safely occupied.

1.3.​ This report sets out these issues, which include design features that inadvertently funnel rainwater into the structure, alongside faulty damp course installations and the use of materials not fully suited to the highly exposed coastal environment. During periods of adverse weather, these issues have allowed excessive moisture to penetrate the building envelope, which presents unacceptable risks regarding damp and mould.

1.4.​ Taken together, these issues require significant remedial work. These must be addressed systematically rather than applying superficial repairs to ensure that fully address these issues before this building is occupied. This Council remains committed to its strategic goal of providing these secure, high-quality, safe homes for residents and to fulfill our statutory obligations under the Building Safety Act 2022

1.5.​ The overall increased costs for the Albion Street project are estimated to total £3.2 million. The estimated figure is subject to ongoing overview by the project's cost consultants and includes £2.1m to address extensive remedial works, £400,000 for professional costs and £700,000 allowance for capitalised interest associated with the borrowing required for the project.

1.6.​ An increase to the Albion Street budget is required to immediately commence these time-sensitive remedial works, address safety compliance requirements under the Building Safety Act 2022, and progress the development toward safe occupation, thereby reducing significant ongoing void losses.

1.7.​ It is expected that the cost of the capital works will be phased over the current 2026/27 financial year £2m and £1.2m in 2027/28. The increase in the project budget will need to be accommodated within the overall capital programme, with members asked to approve budget virements in recommendation 2.1 from the 2026/27 capital programme and approval in recommendation 2.2 to allocate as a priority scheme the remaining budget required from the 27/28 capital programme. This capital programme will continue to deliver critical planned investment in Adur Homes including fire remedial works, kitchen and bathroom replacements, mechanical extraction installations and other essential health and safety related work, ensuring the remainder of the programme is phased accordingly over the next 20 months to meet the budget headroom.

1.8.​ The report also sets out our approach with tenants who are currently waiting to occupy this development to keep them informed and support them throughout this process. A further report with lessons-learned will be brought back to Members in September.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Albion Street Housing Scheme Update ReportReport 268 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 11 attended
JG
Councillor Jeremy GardnerChair, present
BA
Councillor Becky AllinsonVice-Chair, present
LC
Councillor Lee CowenAdur Member, present
AH
Councillor Andrew HarveyAdur Member, present
SJ
Councillor Saffa JanAdur Member, present
AL
Councillor Adrienne LoweAdur Member, present
CB
Councillor Caroline BaxterWorthing Member, present
JT
Councillor John TurleyWorthing Member, present
SC
Councillor Sophie CoxWorthing Member, absent
DF
Councillor Dom FordWorthing Member, present
MM
Councillor Martin McCabeWorthing Member, present

On this subject at Adur & Worthing

Search all
  1. Albion Street Housing Scheme Update ReportThis decision
  2. Adur Homes - Albion Street UpdateNoted
  3. Albion Street UpdateNoted
  4. Approval of budget to complete Albion Street housing developmentApproved
  5. Adur Homes Development Programme - Albion Street and Cecil Norris HouseAgreed

More from Adur & Worthing Joint Strategic Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 MinutesResolved : that the minutes from the Joint Strategic Committee meeting held on 14 July 2026 be approved as the correc... Approved Open
8 Sep 2026 1st Quarter Revenue Monitoring Report 2026/27That it be noted that the report and projected outturn position for the Joint Committee, Adur District Council and Wo... Noted Open
8 Sep 2026 Joint 1st Quarter Capital Investment Programme & Projects Monitoring 2026/27That requested approvals as detailed within the project specific paragraphs in section 7.1 be agreed in relation to A... Approved Open
8 Sep 2026 Refreshing the economic strategy for Adur and Worthing (and Arun), 2026-31That the Arun, Adur and Worthing Economic Draft Strategy 2026 - 2031 be approved and the five economic themes and dis... Approved Open
8 Sep 2026 Fair, Green & Local Plan update: Introducing the Pride in Place missionThat the revision of the Thriving Together mission to Pride in Place be approved 2. That the proposed actions and re-... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies