Decision 1. To approve construction of the breakwater at Dunoon Pier and the proposed works programme subject to revision once the seabed strengthening requirements have been determined. 2. To approve capital expenditure of £75,000 in 2001/2002 to be contained within the existing Transportation Capital Programme. 3. To approve appointment of Halcrow as the consultant for the ground investigation based on the rates accepted for the engineering assessment completed for the funding bid. 4. That the funding allocation for 2002/03 be amended to £1,500,000 (Ref: Report by Director of Transportation and Property Services dated 20 December 2001, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
This report outlines the proposed programme for the construction of the new breakwater at Dunoon Pier following the successful Public Transport Fund Bid. It also seeks approval for capital expenditure in 20001/02 for essential ground investigation works.
Recommendations
2.1The Committee approve the construction of the breakwater at Dunoon Pier and the proposed programme for the works. (Subject to revision once the seabed strengthening requirements have been determined)
2.2The Committee approve the capital expenditure of E75,000 in 2001/02 to be contained within the existing Transportation Capital programme
2.3The Committee approve the appointment of Halcrow as the consultant for the Ground e Investigation based on the rates accepted for the engineering assessment completed for the funding bid,
Background
3.1The Council submitted a bid for Public Transport Funds for the construction of a new breakwater and linkspan at Dunoon Pier.
3.2The Council have been awarded &2,500,000towards the cost of the new breakwater with the decision on the new linkspan deferred until a decision has been made on the future trpe of ferry vessel.
3.3The funding allocation is for f1,5000,000 in 2002/03 and &1,000,000in 2003/04
C:\Documents and Settings\jonesm\Lwal Settings\Temporary lntemet Files\OLK8\ral637.doc 1O f 2 12 December 2001 56
4. PROPOSAL
4.1The Public Transport Funding allocation requires a site start in January 2003
4.2This requires a tender issue in Mid October 2002
4.3The final breakwater design will take at least 10 weeks so must start by July 2002 at the latest.
4.4Before the final design can start it is necessary to know the seabed strength. The seabed strengthening requirements are also required in order to estimate the final cost of the proposed breakwater.
4.5It will take 16 weeks to appoint a contractor and cany out the necessary ground investigation. The estimated cost of the ground investigation is f100,OOO and this work should start in January 2002 if the proposed design programme is to be achieved.
4.6There is no approved capital funding for this project in 2001/02. Approval of the committee is therefore sought for E75,OOO of capital expenditure in 2001/02 and &25,000in 2002/03. The 2001/02 expenditure can be funded from the slippage of E122,OOO identified in the October Capital monitoring of the Transportation capital budget for 200 1/02
4.7Funding to complete the design and construction of the breakwater has been submitted in the 3 year capital programme bid for 2002 - 2005. (This may require revision when the seabed strengthening requirements are known)
4.8An external consultant will be required to cany out the ground investigation as there are no staff resources available within Design Services. In order to avoid a months delay in appointing a consultant by tender the approval of the committee is sought to extend the existing rates from Halcrow, who carried out the engineering assessment for the Public Transport Fund bid.
5. IMPLICATIONS
5.1Policy - None
5.2Financial - &75,000 in 2001/02 to be funded from adjustment to the capital programme
53 Personnel - None
5.4Equal Opportunities - None
5.5Legal -None
For further information please contact Peter Ward (01546 604651)
A Gow Director of Transportation & Property
C:\Documents and Settings\jonesm\LocaI Settings\Temporary Internet Files\OLKS\~a1637,doc 20f2 12 December 2001
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.