The purpose of this report is to advise the Area Committee on the progress of various matters regarding Bunessan Pier.
Recommendation
That the Committee note the contents of the report.
3. DETAIL
3.1Improvement Works
Previous improvement works have included repairs to the end of the pier and the steps plus resurfacing of the access road.
There is at present a scheme in the Capital Programme to be completed in this financial year for further works. The scope of works includes:
• upgrading the access; • formalising the marshalling area; • altering the geometry of the pier to create a double level landing (thus accommodating loading/unloading at high tides); • alterations to the fendering system; • provision of power and water supply
The anticipated costs of these works is approximately £100,000. Due to the high usage of the pier during the summer this work is programmed to commence in October 2002.
3.2Ongoing Remedial Works
The report of a ladder which has been dislodged from the pier is noted. An inspection has taken place and appropriate remedial actions have taken place to make the ladder safe.
F:\moderngov\data\published\Intranet\C00000245\M00000774\AI00003962\BunessanPier0.doc 1 of 2 01 July 2002 3.3 Pier Dues
Pier dues are set annually and apply equally to all facilities owned by the Council. These are based on applying both berthing and landing charges as appropriate. While the Council employs full-time staff at its larger piers and harbours to manage and collect dues, this is not economic on the smaller entities. In these circumstances it is left to the honesty of the users to make the payments due to the Council. While random checks are made of our smaller piers, harbours, and slips much of the landing activities take place at unsociable and variable hours, so enforcement without full time cover is difficult.
In order to overcome this difficulty consideration is being given to introducing a revised charging regime including the option of a composite annual charge for use of our smaller harbours, piers and slips. Such schemes are used in Highland and Comhairle nan Eilean Siar, and informal discussions with the fishermen’s associations have indicated their general acceptance of this charging system in appropriate circumstances. It is intended to bring a proposal to Council on this basis as part of the budget consideration process for 2003/2004. . 4. IMPLICATIONS
4.1Policy – None.
4.2Financial – None.
4.3Personnel – None.
4.4Equal Opportunities – None.
4.5Legal – None.
For further information please contact Stewart Turner, Principal Engineer (01546 604686).
F:\moderngov\data\published\Intranet\C00000245\M00000774\AI00003962\BunessanPier0.doc 2 of 2 01 July 2002
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.