Agreed:- (a) to approve the expenditure as follows: Item 2002/03 Major improvements to the street sweeping in the Oban area £15,000 Community collections for bulk waste on Mull and Iona £ 6,000 Total £21,000 And (b) that a further report be presented to the next meeting in regard to (i) proposed allocation of the remaining £8,610 in 2002/03, £29,610 in 2003/04 and £29,610 in 2004/05; and (ii) costings of the proposed projects, implementation dates and any proposed scale of charges to be imposed. (Ref: Report by the Head of Amenity Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Council at its meeting on 30 May 2002 agreed to make available to each Area Committee the sum of £29,610 over each of the next three years as a result of funding released through success in attracting European Transitional Funding to support the Council's Waste Management Public Private Partnership.
1.2This Report suggests particular projects, which could be implemented locally to the benefit of members of the public in the area served by this local committee.
1.3It is for Members to approve the list of projects or suggest otherwise as they see fit.
Recommendations
2.1Members approve the suggested projects listed in the Appendix to this report, or decide on further consideration of other Waste Management Projects as they see fit.
3. DETAIL
3.1The Council is likely to receive a total of £2,108,007 as the result of a successful European Funding bid last year.
3.2Decisions on the allocation of the majority of this funding have already been taken by the SPC and Council over the past 9 months. However, the residual non-allocated funds are now available as discretionary spend to each Area Committee on the basis of £29,610 annually over the next three financial years, possibly extended slightly further than this dependent on draw down of funds taking place beyond that period. 3.3 While it is for local Members to decide how the improved waste management services should operate in their area, an Appendix of tasks which are felt most pressing from the viewpoint of officials is attached.
4. POLICY
Policy: Improved local services in line with the Council's wish for local decision making.
Financial: The resources for these improved services will be provided from funding additional to the Council's base budget. This funding is available over this and the next two financial years, subject to satisfactory performance of the Waste Management Public Private Partnership. Delay in implementing the various objectives of the PPP could result in a slower release of funds. If this seems likely Members will be given prior warning of such an occurrence.
Personnel: Some of the projects being funded as part of the process of European Funding will result in additional work for current employees, or in some cases additional staffing.
Equal Opportunity: None
For further information contact: Andrew R Law, Head of Amenity Services
Telephone (01546) 604245
LIST OF BACKGROUND PAPERS:
1 Reports on this subject to SPC in 27 September 2001, 7 March 2002, 18 April 2002 and to Council on 30 May 2002 APPENDIX OBAN, LORN AND THE ISLES Annual Spend Available - £29,610 Total Spend Available - £88,830
No Item Rationale for Spending 2002/03 2003/04 2004/05 Total 1 Major Improvements to the Street As a major tourist destination for much of the year, £15,000 £18,000 £18,500 £51,500 Sweeping in the Oban area. Oban suffers from gaps in its street sweeping provision. Employment of an extra member of staff on a shift pattern to cover weekend litter bin emptying and attention to litter hot spots. Also the potential for the funding to contribute to the hire and purchase of mechanical sweeping equipment to deal with littering on the blockwork areas.
Would also deal with foreshore cleaning in Oban.
2 Community Collections for bulk To subsidise the cost of periodic bulk waste £6,000 £6,500 £7,000 £19,500 waste on Mull & Iona. collections in remote parts of Mull and Iona, using the refuse collection vehicle at weekends during autumn and spring. 3 Recycling Collection and handling Using current depot site, with small baler procured £0 £9,110 £8,720 £17,830 on Tiree (and Coll). for cardboard and newspaper handling, which would then be sent back to Oban on return loads. Coll refuse could be partially kept separate by use of “survival bags” which would then be dealt with on Tiree. Cost of small baler + 0.5 employee to do extra work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
6dReport by Director of Development & Environment Services in regard to Local Spending on Improved Waste Management Services - European FundingThis decision
Report by Director of Development & Environment Services in regard to Local Spending on Improved Waste Management Services - European FundingThis decision
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.