Decision To welcome the contribution of £20,000 from the Argyll and Islands Enterprise and to request the Oban, Lorn and the Isles Area Committee identify the match funding from within their area budget to allow a European funding and planning application to proceed. (Ref: Joint report by Directors of Transportation & Property Services and Development & Environment Services dated 12 September 2002, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1A report was placed before Members at the last meeting of the Strategic Policy Committee on the 15 August 2002 detailing the development of the Argyll Air Services and advising on the estimated capital and revenue costs of the development. The purpose of this current report is three fold. Firstly it seeks Members commitment to progress the project given the potential capital and revenue costs for supporting air services from Oban to the Argyll Islands.
1.2Secondly the report updates Members on recent discussions between the Director of Transportation and Property, The Scottish Executive and Highland & Islands Airport Limited (HIAL) and the resulting implications for revenue costs were HIAL to agree to take over responsibility of Oban Airport. Finally the report details as far as possible the outstanding work which requires to be carried out prior to the submission of the European funding application on the 1st November 2002 and the need for additional finance to allow this work to be carried out.
Recommendations
2.1Members are asked to confirm their commitment to progress with the project given the anticipated potential capital and net annual revenue cost of supporting air services from Oban to the Argyll Islands.
2.2That Members agree to the allocation of funding from the existing revenue budgets of the Directors of Transportation and Property (Piers and Harbours) and Development and Environment Services (Fees and Consultancy Revenue Budget) to allow the continued development of the project with the aim of submitting the European funding application on the 1st November 2002. This additional funding allocation would match a 50% contribution by Argyll and the Islands Enterprise (£20,000.00) which represents a total estimated sum of £40,000.00 as detailed in paragraph 3.11.
3. DETAILS
Public Service Obligation (PSO) and Highlands & Islands Airport Limited (HIAL)
3.1Further information has now come to light as a consequence of the discussions between the Director of Transportation & Property, The Scottish Executive and HIAL with regard to the development of the project, the involvement of HIAL, and the implications as regards the capital and revenue costs. It is felt that this information should be brought to Members attention in order to allow Members to give the matter due consideration.
3.2Further to the report submitted to Members on 15th August 2002, informal contact has been made with officials within the Scottish Executive in regard to a future application for a PSO for air services to the Argyll Islands and to HIAL in regard to the operation of Oban Airport.
3.3While no commitment could be given in either regard, as this will ultimately depend on the economic and social case presented by the Council in support of its application, the Director of Transportation and Property has stated that the indications were:
• A PSO is likely to be restricted to internal air services and any links between Oban and Glasgow would require to operate on a commercial basis albeit at marginal cost although HIE feel that this position may be open to change subject to the submission of a case to the Scottish Executive for a PSO between Oban and Glasgow, Edinburgh, or Prestwick.
• While HIAL had previously indicated an unwillingness to consider taking over responsibility for Oban Airport, there is now a recognition that the criteria to be taken into account may have altered owing to the Government's commitment to social inclusion and the proposal to operate scheduled services to the Argyll islands from Oban. In consequence HIAL were prepared to reconsider their position and to discuss the matter further with the Scottish Executive. 3.4 COSTS Appendix 1 details the financial tables updated from the previous SPC report of 15 August 2002.
3.5Capital Costs The Council will require applying to the DTLR for additional Section 94 Borrowing Consent of £494,140.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.