Decision To note the overall budgetary position and various matters identified in the report. To approve the proposed increase of £104,000 to the lighting maintenance budget. A sum was deducted from this budget at a late stage in the budget process in order to free money to fund the enhanced concessionary fares scheme, operational from 1 October 2002. This represented a gap between what the SPT estimated the additional cost of the enhanced scheme would be and what the Scottish Executive were originally prepared to finance by increased grant. The reduction in the lighting budget should it have been necessary would have forced a major restriction on this service. The Scottish Executive however have accepted the case made by the SPT member councils and have provided additional grant funding which will allow the lighting budget to be restored. To note the changes to forecast outturn and action already taken or proposed. (Ref: Report by Director of Transportation and property Services dated 12 September 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1To note the overall budgetary position and various matters identified in this report
2.2To approve the proposed increase of £104,000 to the lighting maintenance budget. A sum was deducted from this budget at a late stage in the budget process in order to free money to fund the enhanced concessionary fares scheme, operational from 1 October 2002. This represented the gap between what the SPT estimated the additional cost of the enhanced scheme would be and what the Scottish Executive were originally prepared to finance by increased grant. The reduction in the lighting budget should it have been necessary would have forced a major restriction on this service. The Scottish Executive however have accepted the case made by the SPT member councils and have provided additional grant funding which will allow the lighting budget to be restored.
2.3To note the changes to forecast outturn and action already taken or proposed.
3 DETAIL
3.1General Overview 3.1.1 The main challenge facing the department at the moment is the programming of the additional work funded by increased grant on a one year only basis. However early budget pressures have appeared under Ferries with abnormal levels of expenditure being incurred. This situation will be monitored closely over the next quarter.
3.2Forecast Outturn
3.2.2 The forecast outturn position is showing projected expenditure of £20.565m. This is in line with the approved budget.
3.3Year To Date Position
3.3.1 Year to date expenditure is £4.036m. This compares to a year to date budget of £4.723m. Actual expenditure is under budget by £0.687m for the year to date. This represents (3.2%) of the full year budget. Actual expenditure compares to an amount of £4,645m for the same period in 2001/2002.
3.3.2 There are three main areas of variance within Transportation and Property Services. The most significant is the underspend on road maintenance which relates to the additional grant income where no spend has occurred to 30 June. There is an adverse variance on Public Transport but this has occurred due to the non processing of recharge accounts and will not have any long term impact.
3.4Year To Date Underspend Or Additional Income
3.4.1 Year to date underspends and additional income have been identified in relation to the undernoted areas. The section below highlights the areas of underspend or additional income and outlines the anticipated forecast outturn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.