INTERNAL AUDIT RESOURCES 2002/03 - UPDATE REPORT

Agreed Finance 2 papers

Audit Committee agreed this item on Friday 8 November 2002. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision Agreed to note the contents of the report. (Ref: Report by Internal Audit Manager dated 8 November 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

Summary

At the conclusion of September 2002 a review has been carried out in order to ascertain the true position of Internal Audit in relation to resources and time available against the objectives set out in the annual audit plan for 2002 - 03. The DETAIL section below gives the findings of this review and outlines current projections. The position review will be the subject of ongoing review and reporting to the Audit Committee.

Recommendations

2.1The contents of this report are to be noted.

3. DETAILS

3.1As reported to the Audit Committee in July 2002 the recruitment process has proceeded well in that as at the 15th of July the section became fully staffed. Following completion of recruitment a process has been carried out where audits have been allocated to individual staff members. Each auditor has planned the audits allocated to him or her over the period to the 31st March 2003.

3.2The annual plan as agreed in May 2002 was based on 970 days of full staff complement for the financial year. A re-evaluation of actual staff days available following completion of the recruitment process indicates that the days available for audits will be 805 days. This is a reduction of 165 days.

3.3Using risk ranking, date last audited and in co-operation with Audit Scotland audits have been prioritised. This prioritisation has been used to allocate audits from the available 805 audit days. As a consequence audits totalling 165 days with lower priority cannot be accommodated within the existing audit resources.

3.4The fact that the staff complement was not complete until the middle of July 2002 has identified some savings, which could be used for the buying in of additional services. At this time there is a projected saving of £15,220. Appendix 1 details the difference in audit days and lists the audits to be carried out within the available days.

4. CONCLUSIONS

Following the successful recruitment of staff and the allocation of audits a review of available audit resources against the audit plan was carried out. This has identified a shortfall in the number of audit workdays available. As a result and in conjunction with Audit Scotland an achievable audit plan for the remainder of the financial year has been agreed. The review has also identified a savings amount that would enable the employment of additional resources to concentrate on progressing the lower priority audits. 5. IMPLICATIONS

5.1Policy: None

5.2Financial: None

5.3Personnel: None

5.4Legal: None

5.5Equal Opportunities: None

For further information please contact Ian Nisbet, Internal Audit Manager (01546 604216)

Ian Nisbet Internal Audit Manager November2002. NovemberprogreportNovember08/2002

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT RESOURCES 2002/03: UPDATE REPORTReport 58 KB DownloadRead as text
PDF
Nov02Progress ReportBruceNovReport 8 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
AM
Archie MortonOfficer, expected
AM
Councillor Alistair MacDougallMember, expected
GM
Councillor Gordon McKinvenMember, expected
JS
Councillor John StirlingChair, expected
SM
Stewart McGregorOfficer, expected
VB
Vincent BradburyVice-Chair, expected
JM
James McLellanOfficer, expected
JM
Councillor James McQueenMember, expected
GM
Graham MichieMember, expected
IN
Ian NisbetOfficer, expected
CR
Charles ReppkeSecretary, expected
LS
Councillor Len ScoullarMember, expected

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. INTERNAL AUDIT RESOURCES 2002/03 - UPDATE REPORTThis decision
  2. Internal audit updateNoted
  3. Internal audit report stakeholder engagementDecided
  4. Internal audit report risk managementDecided
  5. Internal audit contractNoted
  6. Internal audit report direct paymentsDecided

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open