EXTERNAL AUDIT REPORTS TO COUNCIL FROM 1999/00 TO PRESENT - PROGRESS REPORT

Noted Finance 5 papers

Audit Committee noted this item on Friday 8 November 2002. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

Decision To note the contents of the Internal Audit Manager’s report and that it be followed up by Internal Audit. (Ref: Report by Internal Audit Manager dated 8 November 2002, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

Appendix 4

ARGYLL & BUTE COUNCIL

AUDIT MANAGEMENT LETTER 2000/01

7 JANUARY 2002 (Updated 11 October 2002)

7 January 2002 1 Findings Recommendation Management Responsible Agreed Update as at Update as at 11/10/02 Comment Officer completion 20/06/02 date 8.0.1 Performance Indicators – supporting information

As part of our audit we undertake The supporting Management is aware All Directors Partially Partially The Corporate Policy section of work on the Statutory information for the of this issue. Completed Completed the Chief Executives Performance Indicators (“PIs”) PIs should be Procedures currently Department took steps to produced by the Council. From recorded and under review. improve the collection of data this work we noted that there reported throughout for the 2001/02 PI’s. This has were a number of problems the financial year. resulted in the number of the within the systems used for Council’s “X” rated PI’s being recording the information from reduced from 11 in 2000/01 to 7 which the PIs are produced. PI’s in 2001/02 with 5 repeats from 2000/01. There is clearly We could not place reliance on still a need for improvement the information provided and had and the appropriate departments to grade 11 out of 65 PIs as an are currently addressing this. “X” where the reliability of the data was questionable.

7 January 2002 2 Findings Recommendation Management Responsible Agreed Update as at Update as at 11/10/02 Comment Officer completion 20/06/02 date 8.01 Cont

Best practice would Management is aware Alasdair Ongoing Has started. A 6 monthly report will be suggest that of this issue. A report Bovaird First round of presented to the Management performance on remedies for some quarterly Team on the 28 October 2002. measures should be of the underlying reports to go reported to the difficulties is before to It is then proposed to submit Council on a the Management Team Management quarterly reports to the quarterly basis as for consideration. Team on 26 Management Team with 6 these provide useful August 2002. monthly reports going to the information as to SPC. how Council departments are performing. This would enable the Council to take corrective action if required.

7 January 2002 3 Findings Recommendation Management Responsible Agreed Update as at Update as at 11/10/02 Comment Officer completion 20/06/02 date 9.01 Partial Exemption

The Council has a VAT partial The Council should The Council is going T Armour / Ongoing Ongoing Contact has been made with exemption de-minimus level of review the current to review the contract B West KPMG, the Council’s VAT 5%. At the time of our visit, we procedure for for external advisers with a view to them noted that the Council had not calculation of its consultancy for both undertaking this exercise. undertaken a partial exemption partial exemption partial exemption and KPMG are now working on calculation for either the position such that advice support. It is this. 1999/2000 or 2000/2001 financial this is undertaken on the intention to carry years, although we were advised a timely basis. out a tendering that their VAT advisers were exercise early in 2002. currently working on the 1999/2000 calculation. It is still the intention to retender for this In the absence of any partial service in 2002 exemption calculations for either 1999/2000 or 2000/2001 we are unable to comment as to whether the Council has remained within its 5% de minimus limit. It should be noted that if the Council were to exceed its 5% limit, the VAT cost to it would be in excess of £340,000 per year (based on 5% of the input tax declared on the VAT returns submitted for 2000/2001.

7 January 2002 4 Findings Recommendation Management Responsible Agreed Update as at Update as at 11/10/02 Comment Officer completion 20/06/02 date 9.02 Detailed Review of March 2001 VAT return

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Management Letter 2001 Update 11th October 2002Report 143 KB DownloadRead as text
PDF
EXTERNAL AUDIT REPORTS TO COUNCIL FROM 1999/00 TO PRESENT: PROGRESS REPORTReport 63 KB Download
PDF
IML 2000-2001 september 01 2 updated 11th October 2002 1Report 179 KB Download
PDF
NovExternal Audit ReportsPwC1: new oneReport 16 KB Download
PDF
Second Interim Management Letter July 2001_updated 11th October(2) 2002Report 92 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
AM
Archie MortonOfficer, expected
AM
Councillor Alistair MacDougallMember, expected
GM
Councillor Gordon McKinvenMember, expected
JS
Councillor John StirlingChair, expected
SM
Stewart McGregorOfficer, expected
VB
Vincent BradburyVice-Chair, expected
JM
James McLellanOfficer, expected
JM
Councillor James McQueenMember, expected
GM
Graham MichieMember, expected
IN
Ian NisbetOfficer, expected
CR
Charles ReppkeSecretary, expected
LS
Councillor Len ScoullarMember, expected

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. EXTERNAL AUDIT REPORTS TO COUNCIL FROM 1999/00 TO PRESENT - PROGRESS REPORTThis decision
  2. Annual external audit reportNoted
  3. External audit correspondence and assuranceNoted
  4. External audit contract extensionNoted
  5. Internal and External Audit Report Follow Up 2026-27Decided
  6. External Audit Progress UpdateAgreed

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open