CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Mid Argyll, Kintyre & the Islands Area Committee, Wednesday 2 April 2003 at 10.00am

CHILDREN'S PLAY AREAS

Agreed Committee 1 paper

Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 2 April 2003. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Decision Members agreed to review the proposals for their area and advise if amendments to the proposals prior to a full report being presented to the Strategic Policy Committee in April 2003. Members noted the requirement for additional funding in future years in order to complete the improvement programme. (Reference – Report by Horticultural Services Technical Officer dated 2 April 2003)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Mid Argyll, Kintyre & the Islands Area Committee

Summary

1.1Argyll & Bute Council has committed capital expenditure over the next three years to renovate children’s play areas. (see 3.11)

1.2The provision of children’s play areas enables the Council to offer accessible and creative play opportunities for children.

1.3This report details the improvement programme required to ensure these sites meet the requirements of BS EN 1176-7:1998.

Recommendations

2.1Members review the proposals for their area and advise of amendments to the proposals prior to a full report being presented to the Strategic Policy Committee in April 2003.

2.2Members note the requirement for additional funding in future years in order to complete the improvement programme.

Background

3.1The Council are responsible for 51 children’s play areas, which include 161 pieces of individual play equipment. There are 14 sites in Mid Argyll and Kintyre to be improved. There are 46 pieces of equipment on these sites. The 4 sites on Islay were considered to be very high priority and are being renovated during March 2003.

3.2A full condition survey was carried out during 2002, and the results of the survey are summarised in Appendix A. Account was taken of the twice yearly reports from inspections carried out by Zurich Municipal Insurance and local knowledge from routine inspections. 3.3 The main assessment criteria were: - • Condition of safety surfacing • Condition of existing equipment • Requirement for new play equipment • Suitability of existing location • Provision of fencing and signs

3.3The survey was limited to Council owned sites. There is no provision at present to construct children’s play areas at new locations or to adopt play areas built by local community groups. To do so would require a substantial commitment of additional funds. However, the Council will provide assistance to community groups by providing training in safety inspections.

3.4The exception to this approach would be where it was agreed that two existing sites would be closed in order to construct one new site as a replacement at a preferred location.

3.5The provision of related play facilities including playing fields and changing facilities form part of the Council’s existing Playing Fields Strategy approved in November 1999.

3.6All new play areas will be constructed in accordance with the new European Standard BS EN 1176-7:1998. The new regulations came into effect on 1st January 1999, harmonising a number of different standards with new research into safe use of play equipment. The new regulations are not retrospective, i.e. where existing equipment is in good condition and installed according to BS 5696:1986, it can continue to be used, provided it is maintained in a safe condition.

3.7When the applying the new European Standards, to the 164 individual pieces of existing play equipment many pieces of equipment have faults which require routine maintenance but would not result in a failure under the standard. Those, which have been noted as failures, have been immobilised pending repairs or removed from service.

•

3.8A Risk Assessment of the 161 individual pieces of existing play equipment resulted in most equipment considered to be of a reasonable standard at the time of survey in August and September 2002

• 3.9 The priority listing and scheduled programme for renovation and repair of children’s play areas is detailed in Appendix B. The plan is divided into three phases based on the finances available. Projects will be accelerated as additional funds become available.

3.10The current estimated cost for the full renovation programme is £500,000.

3.11The current budget projection for expenditure is: -

2003-04 2004-05 2005-06

Council capital budget £35,000 £59,000 £59,000 Council revenue budget £24,961 £26,209 £27,519 Quality of Life Fund £30,000 £31,500 £33,000

Current projection £89,961 £116,709 £119,519

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CHILDREN'S PLAY AREASReport 95 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 23 attended
AB
Councillor Alasdair BlairMember, expected
AM
Councillor Alastair McKinlayMember, expected
BR
Councillor Bruce RobertsonMember, expected
DM
Councillor Dugie MacKinnonMember, expected
DF
Deirdre ForsythSecretary, expected
JG
Jolan GergelyOfficer, expected
RM
Roddy McDowellOfficer, expected
HB
Hugh BlakeOfficer, expected
SB
Shona BrechinSecretary, expected
RC
Councillor Robin CurrieMember, expected
ID
Ian DownieOfficer, expected
IF
Ian FawcettOfficer, expected

All 23 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CHILDREN'S PLAY AREASThis decision
  2. Housing stock transfer and children's play areasAgreed
  3. Housing stock transfer - children's play areasNoted
  4. Childrens play areasAgreed
  5. Childrens Play AreasApproved
  6. Children's Play AreasAgreed

More from Argyll and Bute Mid Argyll, Kintyre & the Islands Area Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Charts (argyll and the isles)Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the information provided. (Reference: Presentat... Noted Open
2 Sep 2026 Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an... Agreed Open
2 Sep 2026 Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ... Noted Open
2 Sep 2026 Lochgilphead conservation area regeneration scheme (cars) - final project reportDecision The Mid Argyll, Kintyre and the Islands Area Committee noted: 1. the content of the report and noted that Lo... Noted Open
2 Sep 2026 Area committee quarterly performance reports – fq1 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee noted the performance and supporting commentary as pr... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies