Decision The Area Committee agreed:- (i) To note the report and acknowledged that all possible measures are being undertaken; and (ii) Agreed that funding should be sought from alternative sources towards the repair costs. (iii) That a programme of repairs of Dunoon Pier be initiated to address the overall deterioration of the structure with funding being provided from the piers & harbours budget and or monies to be identified within the Capital Programme. (Reference; Report by Director of Transportation & Property dated 1 st May 2003 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The linkspan at Dunoon Pier has been closed to vehicular traffic since Friday 28 March. It was hoped that the facility would only be closed for weeks rather than months. However it has become evident that the extent of remedial work required is substantially greater than first anticipated. Current indications are that works will require to continue into June at a cost of at least £150,000 during which period a passenger only service will be possible.
Recommendations
The Committee is asked to note the contents of this report, acknowledge that all possible measures are being undertaken to allow the linkspan to be opened as soon as possible and due to cost of the repair work, funding should be sought from an alternative source in preference to the overstretched Piers and Harbours Revenue Budget.
3. DETAIL
3.1The Strategic Policy Committee of 24 April received an initial report on progress. This report to the Bute and Cowal Area Committee provides details on progress up to Friday 2 May. An updated verbal report will be presented to the Committee on 13 May.
3.2As part of ongoing inspection works at Dunoon Pier, Arch Henderson & Partners were appointed in mid March to undertake an inspection of the linkspan and dolphins. The inspection was carried out on 25 and 26 March and the result of the inspection was reported to Transportation and Property on 28 March.
3.3The report indicated that 42 piles were inspected and in general terms they were in poor condition. These piles consist of steel casings with a reinforced concrete core. The majority of the steel casings had corroded exposing the core. These casings are considered to be sacrificial on a long term basis provided the internal reinforced concrete core was properly constructed.
F:\moderngov\data\published\Intranet\C00000242\M00001140\AI00009228\ra17250.doc 1 of 3 09 May 2003 3.4 The inspection identified two piles which were of particular concern where the reinforcement had been exposed over significant lengths.
3.5As a result of this information it was considered imperative that steps were put in place to prevent the linkspan being used until repairs could be completed due to the major risk to public safety. It was decided that the linkspan would be closed to vehicular traffic from the last sailing on Friday 28 March until further notice. All appropriate bodies were advised as soon as possible of this decision to allow the customers of the service to make alternative travel arrangements.
3.6The Consultants for the Dunoon Pier Breakwater – Arch Henderson & Partners were appointed to design and supervise the emergency repair work. In addition Shearwater Marine Services of Dunoon who are specialist contractors in underwater engineering work, have been employed to undertake this work.
3.7Work commenced on site on Monday 31 March. Following the initial inspection it was considered that 6 or 7 piles would require repair prior to re- opening. However, after the detailed inspection and subsequent cleaning it has become evident that the extent of repair work required has substantially increased and 21 piles require repair.
3.8The speed of progress is hampered by the overall poor condition of the dolphins and the concrete accessway and it is impracticable to tackle more than one or two piles at a time without affecting the integrity and safety of the structure. By Friday 2 May, repair work had been completed on six piles.
3.9At the end of March it was anticipated that repair work would be completed in a matter of weeks, rather than months. Due to the increase in repair work required it is anticipated that work will continue into June.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.