Decision Agreed the following budget proposals:- 1. Virement of £100,000 from the Bridge Maintenance Revenue Budget to the Piers and Harbours Revenue Budget. 2. Slippage of £100,000 of Capital expenditure on the A846 Duich Bridge from 2003/2004 to 2004/2005 with subsequent adjustments in later years. 3. That £75,000 of expenditure planned for Piers and Harbours Revenue Budget be deferred until 2004/2005. (Ref: Report by Director of Development Services dated 31 July 2003, submitted). The Committee resolved in terms of Section 50A(4) of the Local Government (Scotland) Act 1973, to exclude the press and public for the following 3 items of business on the grounds that it was likely to involve the disclosure of exempt information as defined in Paragraphs 13, 1 & 9, and 6 respectively of Part 1 of Schedule 7A to the Local Government (Scotland) Act 1973. E1
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The Dunoon Pier linkspan was closed to vehicular traffic from 28 May until 16 June. The cost of the works to re-open the facility is in the region of £175,000. As a result it is necessary to amend various budgets to allow this work to be appropriately financed.
Recommendations
The Committee is asked to approve the following budget proposals.
2.1Virement of £100,000 from the Bridge Maintenance Revenue Budget to the Piers and Harbours Revenue Budget.
2.2Approve slippage of £100,000 of capital expenditure on the A846 Duich Bridge from 2003-04 to 2004-05 with subsequent adjustments in later years.
2.3To note that £75,000 of expenditure planned for Piers and Harbours Revenue Budget shall now be deferred until 2004/05.
3. DETAIL
3.1On Friday 28 March following an engineering diving inspection, the linkspan at Dunoon Pier was closed to vehicular traffic on health and safety grounds.
3.2Arch Henderson & Partners were appointed in mid March to undertake a routine inspection of the linkspan, vehicle accessway and the berthing dolphins at the north end of the pier. Their inspection report indicated that all 42 piles were found to be in poor condition. The piles consist of steel casings with a reinforced concrete core and in the majority of cases the steel had corroded exposing the core. Immediate action was taken to close the linkspan and instigate remedial action.
3.3A passenger only service continued to operate between Gourock and Dunoon whilst berthing at the southern end of the pier.
3.4Arch Henderson were immediately appointed to design and implement the emergency repair work and Shearwater Marine Services of Dunoon were appointed as the Contractor for the works. This Company are specialist in underwater engineering works and they were able to mobilise immediately to undertake the works.
F:\moderngov\data\published\Intranet\C00000188\M00001212\AI00010502\DunoonPierLinkspan0.doc 1 of 3 04 August 2003 3.5 Initially it was anticipated about eight piles would have to be repaired to allow the linkspan to be reopened to vehicular traffic. The timescale for completing the works at that stage was put at “weeks rather than months”.
3.6Site work commenced on Monday 31 March with cleaning and subsequent detailed inspection of all 42 piles. It was only after this work had been completed that the necessary extent of repair work was established. A total of 21 piles required repair.
3.7Speed of progress was hampered by the overall poor condition of the linkspan, vehicle accessway and berthing dolphin and it transpired to be impracticable to undertake repairs to more than one or two piles at a time without affecting the integrity and safety of the structure. Indeed by early May work on only six piles had been completed, based on this rate of progress the linkspan would have reopened in late July.
3.8Meetings with the Consultant and Contractors with the objective of establishing improved working methods were held, and as a result it was initially programmed to reopen the linkspan on Saturday 21 June. Subsequent discussions increased the rate of progress and the concrete works required to open the linkspan were completed on Wednesday 11 June.
3.9The linkspan was reopened to vehicular traffic on Monday 16 June with the 1720 sailing from Gourock.
3.10Repair work to several other piles was undertaken following the linkspan being opened to vehicular traffic, but this did not affect the ferry operating.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.