Oban Lorn & The Isles Area Committee agreed this item on Wednesday 14 January 2004. Below is the council's own wording, with the papers it was decided on.
It was agreed to:- (a) combine the schemes for provision of road signs (£5,000) and road improvements (£30,853) to reflect a single scheme for road safety improvements area wide (£35,853); (b) transfer £600 from the sum allocated for amenity enhancement projects in wards 10 and 14 to the allocation for road safety improvements area wide; and (c) note the report by the Area Roads Manager. (Ref: reports dated 7 th and 14 th January 2004 by the Area Roads Manager and Area Corporate Services Manager respectively, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL- PROGRAMME OF CAPITAL EXPENDITURE - 2003-2004 COMPOSITE CAPITAL PROGRAMME - AREA COMMITTEE - LORN & THE ISLES For Year to Date: 14th January 2004
Start date Project Budget /commencement of Estimated Project Description Manager 2003/2004 YTD Actual on site works Completion date Comments £ Taynuilt Sports Club - Grant towards all- K Macdonald 6,000 6,000 Complete weather sports facility (Ward 10) Bonawe Footpath (Ward 15) N Brown 10,000 10,000 Sep-03 Complete Community Councils (Wards 10 & 14) for I Welsh 6,800 Onging Mar-04 Kerrera withdrawn therefore £600 to re-allocate. Work ongoing to be amenity enhancement projects completed this financial year. Awaiting recharges from community councils. Cattle grid replacements (Wards 10 & 14) N Brown 7,000 Recommended that funds be re-allocated.
Dunollie Footpath, Oban (Ward 11) I Welsh 6,100 2,500 Sep-03 Feb-04 Tree work & safety barrier completed. Lighting and landscape improvements to be completed by early February.
Mossfield Stadium - structural works to I Welsh 16,800 12,000 Sep-03 Feb-04 Flooring, benches, ventilation completed. Referee's room in progress. changing area and entrances (Ward 12) Anti-vandal shower units to be installed early February.
Land Acquisition, Soroba (Ward 13) D Kelly 16,800 2,055 Approved by Council 22.10.03
Road Safety Improvements (Ward 14) N Brown 9,500 1,000 Oct-03 Work in progress. Completion date dependent upon Seil Community Council.
Crossapol, Tiree Village enhancement I Welsh 16,800 Oct-03 Mar-04 Community decision expected 13th January. To spend on play area scheme (Ward 17) equipment/relocation this financial year.
Improvements to parking arrangements N Brown 17,700 Feb-03 Consultation being carried out with residents who hold rights in (Ward 11) common over the proposed site.Planning consent applied for..(NID)
Improvements to Lora View playpark, North I Welsh 6,800 2,450 Oct-03 Feb-04 Scrub clearance and fencing complete. New equipment to be installed Connel (Ward 15) February. Project delayed last year whilst community tried to secure additional funding. Upgrading public toilets (Ward 16) I Welsh 16,800 Dec-03 Feb-04 New access for disabled units programmed for January
Feasibility study into a fixed link to provide a P Ward 15,000 Sep-03 Nov-03 Work in progress tidal power scheme - Luing / Seil Provision of footway on Soroba Road, Oban N Brown 15,187 Jan-03 Feb-03 Start 12 January for 5 weeks.
Provision of road signs throughout Oban, N Brown 5,000 Dec-03 Feb-04 Lorn & the Isles Road Improvements - Area Wide N Brown 30,853 22,500 Nov-04 Luing resurfacing - Complete Blaran road end - Complete except remedial works Connel Village footway - Complete
GROSS SPEND PLANNED 203,140 58,505
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.