Report by European Manager in regard to Easdale Harbour Project
AgreedCommittee1 paper
Oban Lorn & The Isles Area Committee agreed this item on Wednesday 14 January 2004. Below is the council's own wording, with the papers it was decided on.
It was agreed to approve a contribution of £8,300 from the existing Development Services Budget, being the shortfall in funding, subject to it being made clear to the Trust that the contribution does not carry with it any liability on behalf of the Council for the integrity of the structure.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The Eilean Eadsale Trust have developed a project which will improve the harbour area, encouraging tourism and safeguarding the livelihood of the island.
The project, with a total cost of £61,600 is being funded by the Community Economic Development Programme (Europe), AIE and the 1.2 Community itself. Argyll and Bute Council has agreed to support an in kind contribution of £3,800 equal to the cost of dredging the harbour. The project still has a shortfall of £8,300, which the Area Committee is being asked to approve from the existing Development Services budget.
Recommendations
2.1It is recommended that the Area Committee approve a contribution of £8,300 from the existing Development Services budget to enable the project to go ahead.
Background
3.1Community Economic Development Programme (CEDP) is a European funded programme, which supports local community projects. The Committee received a presentation on this and LEADER + in January 2003. As with all European funding, it requires to be co-financed by non- European sources of funding.
3.2A small budget was set aside in the former Economic Development, Tourism and Leisure Unit to enable CEDP projects to go ahead, if there was a funding shortfall and if the projects met Council objectives.
3.3Eilean Eisdeal Trust (EET) is a charitable company limited by guarantee, incorporated in 1997 to protect and enhance the islands community, economy and way of life. EET has a 50-year lease of the Harbour and have developed a management and berthing fee structure.
3.4The harbour is in a poor state of repair, but is a vitally important part of the community. Following extensive community consultation, EET have proposed a project which incorporates the following:
Levelling of the “Rush and Gush” area and grading of entrance to permit winter boat storage. Dredging will be carried out in the vicinity of the south- east harbour wall to improve access to the wall Stabilisation of the north west harbour wall to prevent further collapse and removal of fallen stones. Timber fenders are to be strategically fixed the harbour walls to enable safer usage of the walls for berthing and to prevent further decline of the harbour walls. A mooring tot is to be laid to provide safe mooring and more efficient use of available space
An engineering survey will be commissioned to make an accurate appraisal of the harbour’s condition and identify the scope of the repair required.
3.5There will be liaison between the Area Roads Manager and this group in the dredging activities and subject to Eilean Eisdeal Trust complying with the planning permission with conditions that has been approved by the Area Committee.
4. CONCLUSION
4.1The project at Easdale Harbour will enable the Community to take advantage of European funding to develop a long term project, which will have a very positive impact on the local economy.
5. IMPLICATIONS
Policy: The Argyll and Bute Economic Strategy 2000-2003 identifies island communities as being fragile and in need of support to achieve sustainable economic development. It also identifies European funding as a means to support economic activity in these areas.
Financial: The £8,300 will be found from existing budgets. £3,800 is an in-kind contribution.
Personnel: None
Equal The project will improve equality of opportunity to the people Opportunity: on Easdale to access economic development opportunities.
For further information contact: Jane Fowler, European Manager Telephone 01700 501371
5th January 2004
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.