Oban Lorn & The Isles Area Committee agreed this item on Wednesday 4 February 2004. Below is the council's own wording, with the papers it was decided on.
It was agreed:- (a) to reallocate the underspends in Community Council amenity enhancement projects (£845) and Dunollie footpath (£1550) to the sum earmarked for upgrading public toilets (Ward 16), and amend the narrative of this project to read ‘Upgrading public toilets and environs – Mull / Oban’; and (b) that the sum of £16,800 earmarked for the Crossapol, Tiree Village enhancement scheme be carried forward to 2004/05 to enable the community to secure match funding, thereby adding value to the project. (Ref: Report dated 23 rd January 2004 by the Area corporate Services Manager, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL- PROGRAMME OF CAPITAL EXPENDITURE - 2003-2004 COMPOSITE CAPITAL PROGRAMME - AREA COMMITTEE - LORN & THE ISLES For Year to Date: 23rd January 2004
Start date Project Budget /commencement of Estimated Project Description Manager 2003/2004 YTD Actual on site works Completion date Comments £ Taynuilt Sports Club - Grant towards all- K Macdonald 6,000 6,000 Complete weather sports facility (Ward 10) Bonawe Footpath (Ward 15) N Brown 10,000 10,000 Sep-03 Complete Feasibility study into a fixed link to provide a P Ward 15,000 15,000 Sep-03 Complete tidal power scheme - Luing / Seil Community Councils (Wards 10 & 14) for I Welsh 6,200 1,450 Onging Mar-04 Projects nearing completion. Awaiting invoices. £845 amenity enhancement projects available for reallocation
Dunollie Footpath, Oban (Ward 11) I Welsh 6,100 3,750 Sep-03 Feb-04 Work nearing completion. Awaiting invoices. £1550 available for reallocation
Mossfield Stadium - structural works to I Welsh 16,800 14,000 Sep-03 Feb-04 New flooring installed and work on changing area nearing completion. changing area and entrances (Ward 12) Completion of shower area expected February
Land Acquisition, Soroba (Ward 13) D Kelly 16,800 2,055 Draft Order has been referred to the Scottish Executive. Confirmation from Strategic Finance that balance can be carried forward.
Road Safety Improvements (Ward 14) N Brown 9,500 2,000 Oct-03 Mar-04 Work in progress. Council work substantially complete. Contract for remainder about to be awarded.
Crossapol, Tiree Village enhancement I Welsh 16,800 Mar-04 Mar-04 Spend agreed with local community. Option to place equipment scheme (Ward 17) order now or carry allocation through to next year, enabling match funding to be secured and adding value to the project.
Improvements to parking arrangements N Brown 17,700 Feb-04 Mar-04 Consultation being carried out with residents who hold rights in (Ward 11) common over the proposed site. Planning consent applied for. Three week contract.
Improvements to Lora View playpark, North I Welsh 6,800 4,000 Oct-03 Feb-04 Scrub clearance complete. Fencing complete. Installation of new Connel (Ward 15) equipment underway.
Upgrading public toilets (Ward 16) I Welsh 16,800 1,000 Dec-03 Mar-04 Specification agreed. Work now to be undertaken in February.
Provision of footway on Soroba Road, Oban N Brown 15,187 Jan-04 Feb-04 Start 26th January for 5 weeks, dependent upon weather.
Road Improvements - Area Wide N Brown 36,453 35,000 Feb-04 Luing resurfacing - Complete Blaran road end - Complete except for remedial works. Connel Village footway - Complete Road Signage - Substantially complete.
GROSS SPEND PLANNED 196,140 94,255
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.