03/02112/OUT - Mr & Mrs R Barclay - Site for the erection of a dwelling house - Land north of Ardconnel Farm, Connel, Oban
AgreedCommittee2 papers
Oban Lorn & The Isles Area Committee agreed this item on Wednesday 4 February 2004. Below is the council's own wording, with the papers it was decided on.
It was agreed that consideration of this application be continued to the meeting of the Area Committee in April 2004, after the conclusion of the statutory public consultation exercise for the draft local plan, to allow for consideration of any representations made to that plan regarding the settlement boundary of this part of Connel. (Ref: Report dated 5 th January 2004 by the Head of Planning, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
DEVELOPMENT SERVICES Local Member - Councillor E Robertson PLANNING APPLICATION REPORT Date of Validity - 18th November 2003 OBAN, LORN AND THE ISLES Committee Date - 4th February 2004
5th January 2004
Reference Number: 03/02112/OUT Applicants Name: Mr and [name removed]: Outline Application Application Description: Site for the erection of a dwelling house Location: Land north of Ardchonnel Farm, Connel
(A ) THE APPLICATION
Development Requiring Express Planning Permission.
• Site for the erection of a dwelling house (indicative layout submitted). • Formation of an access (indicative position submitted) • Installation of septic tank and soakaway (indicative position submitted)
Other Specified Operations.
• Connection to private water supply.
(B ) RECOMMENDATION
The proposal is recommended for refusal.
(C ) DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
Housing Policy
The site lies within the open countryside on the periphery of Oban. The site is situated in the glen along the back road from Oban to Connel. The site itself is located approximately 500 metres to the north of Ardconnel Farm. Although located on elevated ground the house it to be situated to the east of an existing knoll to help integrate the house into the landscape, together with the retention of the surrounding existing trees.
The site lies within the Oban Catchment Area as defined by Policy HO 25 of the Lorn Local Plan 2nd Alteration. Policy HO 25 states that within the Catchment Area there will be a presumption against housing development except when it is infill, rounding-off or redevelopment related to the existing built form.
This proposal does not represent infill or rounding-off development due to its physical separation from the existing development in the glen and does not represent redevelopment due to the lack of any substantial existing buildings on the site.
The proposal is therefore contrary to Policy HO 25 of the adopted Lorn Local Plan.
Emerging New Local Plan
The emerging Argyll and Bute Local Plan has identified this area as a ‘rural opportunity area’, within which encouragement will be given to small scale development on suitable sites which, in terms of siting and design, will visually integrate with the landscape and settlement pattern. The emerging plan is likely to view this proposal in a favourable light in principle, therefore this proposal is unlikely to prejudice the emerging local plan. F:\MODERNGOV\DATA\PUBLISHED\INTRANET\C00000245\M00001461\AI00013925\2112WR050104SKP0.DOC 1 Whilst it may be the case that this application could be considered to be acceptable in terms of the new local plan, it is considered premature to support this application at this stage in view of the current public consultation which could result in representations being received in relation to the proposed policies applicable to this site.
Justification for a Departure from the Development Plan
The Catchment Area Policy (Policy HO 25) of the existing adopted Local Plan clearly states that there is a presumption against this development as it does not represent infill, rounding-off or redevelopment.
No exceptional circumstances or site specific locational/operational need have been established in support of this application. Accordingly, it is considered there is no justification to depart from the current development plan policy.
Other Material Considerations
• Servicing and Infrastructure
It is proposed to form a new vehicular access and undertake earth works to provide for a minimum of 75 metres visibility in each direction. The Area Roads Engineers comments are awaited.
It is proposed to install a septic tank and soakaway. The Scottish Environmental Protection Agency has advised they have no objections in principle.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.