STRATEGIC AUDIT PLAN 2005-2008

Approved Finance 2 papers

Audit Committee approved this item on Friday 4 March 2005. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision To approve the Strategic Audit Plan 2005-2008 and the Annual Audit Plan for 2005-2006. (Reference: Report by Internal Audit Manger dated 7 February 2005, submitted).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

ARGYLL & BUTE COUNCIL AUDIT COMMITTEE STRATEGIC FINANCE 4 MARCH 2005

STRATEGIC AUDIT PLAN 2005 - 2008

1. SUMMARY This report introduces the Strategic Audit Plan for 2005 – 2008 and Annual Audit Plan for 2005 - 2006. The Strategic Audit Plan has been prepared in consultation with KPMG, our internal audit partners. See Appendix 1.

2. RECOMMENDATIONS 2.1 The Strategic Audit Plan 2005 – 2008 and Annual Audit Plan for 2005 – 2006 are approved. 3. DETAILS

3.1The Strategic Audit Plan 2005 - 2008 as well as including the Annual Audit Plan for 2005 - 2006 covers planned core and non financial audits.

3.2Internal Audit in preparing the strategic audit plan carried out an exercise to determine the core financial audits that will enable Internal Audit over the next 3 years to provide an assurance statement on the Council's overall internal control framework. A section has been included within the strategic audit plan which lays out the broad scope and objectives for each of the core financial audits.

3.3Non financial audits within the strategic audit plan have been derived from a Heads of Service risk evaluation exercise carried out at the end of January 2005. The exercise highlighted a number of key operational risks to be included in the plan. Discussions will take place with the Heads of Service to progress these audits over the next 3 years.

4. CONCLUSION The Strategic Audit Plan and Annual Audit Plan will be progressed by Internal Audit.

5. IMPLICATIONS

5.1Policy: None

5.2Financial: None

5.3Personnel: None

5.4Legal: None

5.5Equal Opportunities: None For further information please contact Ian Nisbet, Internal Audit Manager (01546 604216)

Ian Nisbet Internal Audit Manager 7 February 2005 7Febfinalrep7feb

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STRATEGIC AUDIT PLAN 2005-2008Report 61 KB DownloadRead as text
PDF
Strategic Audit Plan Appendix 1.1Appendix 204 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
JT
Councillor John TacchiMember, expected
BB
Brian BarkerOfficer, expected
JB
Jillian BrownOfficer, expected
DM
Councillor Donald MacMillan BEMMember, expected
JM
Councillor John McAlpineMember, expected
JM
James McLellanOfficer, expected
GM
Councillor Gary MulvaneyChair, expected
IN
Ian NisbetOfficer, expected
CR
Charles ReppkeSecretary, expected
ER
Councillor Elaine RobertsonMember, expected
IM
Ian M M RossMember, expected
NS
Nigel StewartOfficer, expected

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. STRATEGIC AUDIT PLAN 2005-2008This decision
  2. National roads strategic action group response to audit scotlandNoted
  3. Strategic audit plan 2011 - 2014Approved
  4. Strategic audit plan 2008-2011Approved
  5. Audit needs assessment and strategic audit planAgreed

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open