DECISION To note the memo issued to the Strategic Directors emphasising the importance of agreeing realistic implementation dates with auditors which will also provide the Audit Committee with a measured basis against which to monitor implementation progress. To instruct the Head of Roads and Amenity Services to give a verbal report to the next meeting of the Audit Committee explaining the reasons for slippage on the Ferry Services Review. To request that the Chief Executive advise the Audit Committee of the reasons for the delay in the Ferry Services Review and to confirm whether completion of the Review could be brought forward as it had implications for the Capital Budget, meeting on 17 March 2005. (Reference: Report by Internal Audit Manager dated 7 February 2005, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The Internal Audit Annual Plan requires that follow up reviews be conducted for all audits completed during the prior year. Internal Audit also document the progress made by departmental management in implementing the recommendations made by Audit Scotland and Internal Audit. A new reporting system was introduced and approved by the Audit Committee in August 2004. Set out below is the results from a review performed by Internal Audit for recommendations due to be implemented by the 31st December 2004.
Recommendations
2.1The contents of this report are noted and are to be followed up by Internal Audit.
3. DETAILS
3.1Appendix 1 is a statistical summary of the 2003/04 Internal Audit reports issued prior to December 2004. It details the number of recommendations contained in each report, number of recommendations to be implemented by the follow up date, the number implemented and those past their implementation date. The implementation date used for reporting to this Audit Committee is the 31st December 2004. A reference column has been added to provide a link to Appendix 2, where reasons are given by local management as to why recommendations have not been implemented by the agreed date. The same layout has been used for the follow up of Audit Scotland report recommendations.
3.2Appendix 1 is split into 2 documents 1a & 1b. The first document refers to all reports with recommendations due November to December 2004. The second document lists action points outstanding from the previous Audit Committee. These are points that should have been implemented by the 31st of October 2004 for the last Audit Committee. The same layout has been used for the reporting of Audit Scotland report recommendations in Appendices 3 & 4.
3.2Appendix 2, details under each report’s title the recommendation that is still to be implemented the department and Head of Service responsible and an explanation for the delay, the level of risk, original and a revised implementation date.
3.3All new external audit reports issued by Audit Scotland to the Council are reported initially separately to the Audit Committee with their executive summary and action plan. Thereafter they will be included in the summary list in Appendices 3 & 4 of this report.
3.4At the last Audit Committee the members wanted to ensure that all departments were aware of the necessity to adhere to the negotiated deadlines and should take into account any staffing/budgetary constraints when initially setting these. As a d result of this request Internal Audit sent out a memo on the 23rd December 2004 to all Strategic Departmental Directors emphasising the importance of agreeing realistic implementation dates with auditors, which will also provide the Audit Committee with a measured basis against which to monitor implementation progress. (See Appendix 5).
REQUESTED SERVICE REPORTS
3.7A report entitled Regularity & Governance 3 was issued by Audit Scotland in September 2004. At the last Audit Committee members requested that a report be presented by the Finance Manager – Community Services explaining why the DMR procedure manual review had been the subject of a further delay, as the Committee considered its implementation a fundamental piece of work. A report has been prepared by the Finance Manager and is attached in Appendix 6.
4. CONCLUSIONS
Implementation of recommendations will continue to be monitored by Internal Audit.
5. IMPLICATIONS 5.1 Policy: None
5.2Financial: None
5.3Personnel: None
5.4Legal: None
5.5Equal Opportunities: None
For further information please contact Ian Nisbet, Internal Audit Manager (01546 604216) Ian Nisbet Internal Audit Manager 7 February 2005. 7Febfinalreport7feb
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.