Decision 1. To note the contents of the Contract Review process as detailed in Appendix 2 of the report; 2. Agreed the actions shown in the table of Appendix 2; 3. To note the information contained in Section 4 of the report; and 4. To instruct the Director of Operational Services, in consultation with the Head of Strategic Finance, to provide further detail on the financial implications as soon as available information is to hand. (Reference: Report by Director of Operational Services, submitted) *
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report is to update members on the Contract Review process which has taken place with Shanks during the last 18 months and to note action required as a result of that review.
Recommendations
2.1Members note the outcome of the contract review process as detailed in Appendix 2 of this report and agree the actions shown in the table of that appendix.
2.2Members note the information contained in Section 4 of this report and require the Director of Operational Services, in consultation with the Head of Strategic Finance, to provide further detail on the financial implications as soon as available information is to hand.
3. DETAIL
3.1The Council’s Strategic Policy Committee of 13th April 2005 considered a report on contractor performance in respect of the Waste Management PPP and instructed the Director of Operational Services to conduct a review of the contract in line with provisions for this to happen after the first 5 years of operation.
3.2This review has taken place with a number of meetings between relevant staff of both parties and external support by the Caledonian Environment Centre (CEC), which operates as part of Glasgow Caledonian University. The executive summary of their input is attached as Appendix 1 to this report.
3.3As outlined in the original report to members the main issue which required review were: 1. Composting standards and the ability to continue with mixed waste composting;
2. Future operation of end of life vehicle collection and disposal;
3. Consideration of ongoing remedial works at Gartbreck and Glengorm landfill sites (subject to report to the SPC last month)
4. Possible need to rerun the financial model;
5. Re-examination of the funding model of the contract;
6. How to deal with new legislative burdens – e.g. waste electrical and electronic equipment legislation.
Appendix 2 of this report identifies these issues and other relevant items identified during the review process and suggests a way forward for future operations, which is reflected in recommendation 2.1
3.4For 2005/06 the delivery by Shanks of a recycling rate of (excluding composting) 10.53% of Council waste delivered to them was achieved in partnership with the Council’s kerbside collection services in the areas covered by their sites. This figure rises to 16.15% of Council waste in the areas concerned once the addition of community groups’ waste collection is taken into account.
3.5The main contractual target for Shanks to meet in 2005/06 was for diversion of waste from landfill of just under 15,300 tonnes, equivalent to 40% of the waste delivered to them. In the event, they under-achieved this target, reporting a diversion figure of 12,500 tonnes of waste or 33%. This figure requires to be finalised and approved by SEPA, bearing in mind the comments made in paragraphs 3 and 4 of the CEC Executive Summary, shown as Appendix 1.
3.6For members’ information the current position with regard to Shanks corporate structure has changed quite substantially since the original signature of the PPP contract in 2001. At that time the company engaged in the full range of waste management services across the UK and had similar interests in Belgium and the Netherlands.
Since then there has been a conscious decision by Shanks to focus its UK operations “On the new Waste Management markets generated by changes in European Waste Management regulation and UK landfill tax”. This is evidenced by the company selling the majority of its landfill assets in the United Kingdom and seeking to concentrate on collection and recycling of material in the commercial market and on securing contracts for long term municipal waste in the UK. This has resulted in them having PPP/ PFI type contracts with Argyll & Bute, Dumfries & Galloway and the East London Waste Authority.
Concurrently with this they have increased their investment in Belgium and the Netherlands.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.