CAPITAL PLAN MONITORING REPORT 30 JUNE 2006

Approved Committee 1 paper

Strategic Policy Committee approved this item on Thursday 24 August 2006. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision 1. To approve the re-profiled Capital Plan as detailed in Appendix 1 of the report; and 2. To note the level of actual expenditure as at June 2006. (Reference: Report by Head of Strategic Finance dated 9 August 2006, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Strategic Policy Committee

Recommendations

2.1That the reprofiled capital plan at Appendix 1 be approved.

2.2Members note the level of actual expenditure as at June 2006.

3 DETAIL

3.1Appendix 1 contains the detailed reprofiled Capital Plan submissions from the various departments. Departments have reprofiled where possible in line with the proposed expenditure profile detailed in paragraph 3.4.7 of the Head of Strategic Finance’s report submitted to the Council on 28 June 2006. The report to the Council on 28 June 2006 set a target of approximately £19.5m per annum for net capital expenditure for each of the years 2006-07, 2007-08 and 2008-09. The reprofiled plan now being submitted has net capital expenditure of £23.3m in 2006-07 and £17.7m in each 2007-08 and 2008-09. Whilst this still has a slight element of front loading in 2006-07 it is considered to be acceptable and within reasonable boundaries in terms of trying to achieve a more evenly profiled capital plan.

3.2The increases and decreases in project costs reported at Appendix 5 of the report have been contained, where possible, by adjusting the budgetary provision in respect of other projects in the Capital Plan. In overall terms the capital plan is £884,000 higher than that reported on 28 June 2006. £832,000 of this relates to the increased costs of improvements to island landfill sites and financed by unsupported borrowing to be funded from Roads and Amenity Services revenue budget as a result of a review of the Waste PPP contract. This proposal was submitted to the SPC on 20 July 2006. The balance of £52,000 relates to movements on other projects that will be monitored during the course of 2006-07.

3.3In relation to Campbeltown Community Facility members should note whilst the project cost has been returned in line with previously approved budget negotiations are ongoing with the contractor regarding the final account. 3.4 Appendix 2 shows the variances between the provisional programme included as Appendix 1 of the Capital Plan Overview Report submitted to Strategic Policy Committee on 15 June 2006 and the reprofiled programme included as Appendix 1 of this report. Explanations have been provided for variances greater than +/- £50,000.

3.5The provision for the Feolin Ferry structure has been deleted from the revised Capital Plan in line with the decision taken by the Council on 28 June 2006.

3.6The £549,000 allocated for roads and infrastructure projects has been added to the Reconstruction line of the Head of Roads & Amenities section of the Capital Plan.

3.7Appendix 3 compares actual expenditure as at 30 June 2006 with the reprofiled budget for 2006-07 by head of service. In overall terms the net capital expenditure amounts to £3.009m against a full year budget of £23.324m. Actual expenditure is 12.9% of full year budget. This is higher than the levels of actual expenditure at the end of June in previous years however it should be noted the overall plan is at a higher level. The level of actual net capital expenditure at 30 June for 2004-05 and 2005-06 was £2.5m and £1.8m equating to 8.5% and 14.7% of the final outturn respectively.

For further information please contact Bruce West, Head of Strategic Finance 01546- 604220

Bruce West Head of Strategic Finance 9 August 2006 Appendix 1

ARGYLL AND BUTE COUNCIL- 5 YEAR ROLLING PLAN OF CAPITAL EXPENDITURE COMPOSITE CAPITAL PROGRAMME - SUMMARY SHEET

To Future Departments 2006/07 2007/08 2008/09 2009/10 2010/11 Total Project Cost 31/3/2006 Years

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PLAN MONITORING REPORT 30 JUNE 2006Report 129 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
AM
Councillor Alastair McKinlayMember, expected
AM
Councillor Allan MacaskillChair, expected
IG
Councillor Ian GilliesMember, expected
RB
Councillor Robin BanksVice-Chair, expected
GF
Councillor George FreemanMember, expected
GH
George HarperOfficer, expected
AH
Councillor Alison HayMember, expected
DH
Douglas HendryOfficer, expected
DK
Councillor Daniel KellyMember, expected
DM
Councillor Duncan MacIntyreMember, expected
RM
Councillor Robert MacintyreMember, expected
SM
Susan MairOfficer, expected

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. CAPITAL PLAN MONITORING REPORT 30 JUNE 2006This decision
  2. Capital Plan Monitoring Report - for the year ending 31 March 2025Noted
  3. Capital planning updateNoted
  4. Capital Plan 2016 - 2020Agreed
  5. Capital planning pack 2015-16 to 2019-20Approved
  6. Capital plan monitoring 31 december 2012Noted

More from Argyll and Bute Strategic Policy Committee

All decisions
MeetingDecisionOutcome
19 Apr 2007 Leader's reportDecision To note the contents of the report for the period 14 March to 10 April 2007. (Reference: Report by Leader of... Noted Open
19 Apr 2007 North of scotland local authorities - revenues and benefits projectDecision Agreed that delegated authority be given to the Head of ICT and Financial Services to sign a Memorandum of U... Agreed Open
19 Apr 2007 Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue... Noted Open
19 Apr 2007 Argyll and bute design awards scheme and sustainable design forumAgreed to have a single Council wide Planning Award Scheme to be administered centrally by the Design Forum and; 3. T... Agreed Open
19 Apr 2007 Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies