Decision To note the Revenue Budget Monitoring position as at 30 June 2006. (Reference: Report by Head of Strategic Finance dated 2 August 2006, Joint Report by Director of Community Services and Head of Strategic Finance, dated 1 August 2006, Joint Report by Director of Operational Services and Head of Strategic Finance dated 31 July 2006, Joint Report by Director of Development Services and Head of Strategic Finance dated 27 July 2006, Joint Report by Director of Corporate Services and Head of Strategic Finance dated 28 July 2006 and Joint Report by Chief Executive and Head of Strategic Finance dated 2 August 2006, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members note the revenue budget monitoring position, as at 30 June 2006.
3. DETAIL
3.1The year to date approved expenditure is under budget by £1,784,000. The main factors contributing to this are:
Community Services: x Underspend on staff costs, including the effect of the 584,000 pay award still to be processed and vacancies within both the Primary and Secondary sector. x Delay in charging from Scottish Water and Scottish 199,000 Power for a number of properties. x Invoices not being received when expected and the 341,000 effect of the moratorium. x Profiling errors and delays in receiving income. -111,000 x Other variances. -54,000
Operational Services x Provision for Single Status being paid later than 117,000 originally anticipated and staff vacancies in Design Services. x Accrual for staff costs at Rothesay Pier. 36,000 x Accruals for central repairs completed in previous year 123,000 being paid later than anticipated. x Fleet leasing payments paid earlier than expected. -244,000 x Prepaid Strategic Waste Fund grant. 270,000 x Income recovered from fleet fuel purchases and the 265,000 waste management trading account earlier than anticipated.
Development Services: x Variance due to staff vacancies and the effect of the 57,000 pay award still to be processed. x Expenditure on grant funded projects which were not -84,000 budgeted for. A budget is being prepared for this. x Variance due to carry forward balances on self funding -268,000 projects which were outwith the revenue budget when it was prepared. Profiled budgets will be prepared for these. x Building standards income ahead of profile and grants 238,000 received for unbudgeted projects.
Corporate Services: x Amount to be remitted to Crown Agents and 107,000 Strathclyde Safety Camera Partnership. x Income from Civic Government licence renewal due at 120,000 the start of a three year cycle. x Increased income within Registrars services, 72,000 particularly from marriage notices. x Unbudgeted grant income and licence application 96,000 income for Private Landlord Registration. x Other variances. 15,000
Chief Executives: x Expenditure incurred as a result of equal pay -101,000 settlement, the provision for this has been released and this will be corrected for the July period. x Incorrect coding of an invoice, this has been corrected -28,000 for the July period. x Other variances 30,000
Treasury Management x Coding corrections and profiling required. 4,000
1,784,000
3.2Refer to Community Services report point 3.3, that notes a number of areas of projected overspend.
3.3Refer to Operational Services report point 3.3 for further detail on the favourable year to date variance.
4. MANAGING VACANCIES
4.1As part of the 2006-07 budget exercise departments identified savings that were to be made through managing vacancies. The following table provides an analysis of year to date actual direct employee costs by department (excluding teachers) with a comparison against the year to date profiled budget. Actual Budget Variance Budget YTD YTD* Saving Required Department £’000 £’000 £’000 £’000 Chief Executive’s Unit 753 760 7 57 Community Services 8,183 8,556 373 150 Operational Services 4,136 4,201 65 32 Development Services 905 948 43 77 Corporate Services 1,569 1,543 -26 108 Total 15,546 16,008 462 424
* The Budget YTD has been adjusted to remove the pay award profiled to occur in the April to June period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Development and environment issuesDecision To note the contents of the report. (Reference: Report by Spokesperson for Development and Environment Issue...
Refuse collections on private roadsDecision The Motion was carried by 5 votes to 3 and the Committee resolved accordingly. (Reference: Extract of Minute...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.