INTERNAL AUDIT PROGRESS REPORT 2006-2007

Approved Finance 2 papers

Audit Committee approved this item on Friday 30 March 2007. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Decision 1. To approve the progress made with Annual Audit Plan for 2006-7. 2. To clarify to the Members of the Committee what the issues are with the new e-procurement system. (Ref: Report by Internal Audit Manager dated 14 March 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Audit Committee

Summary

An interim progress report has been prepared covering the audit work performed by Internal Audit up to the 2nd of March 2007. The objective of the report is to advise members of the progress of the Annual Audit Plan. (See Appendix 1).

Recommendation

2.1The Audit Committee is asked to approve the progress made with the Annual Audit Plan for 2006 - 2007.

Background

3.1The progress report contained in Appendix 1 lists the audits scheduled for the financial year 2006 –2007, and are ordered by section and level of completion.

3.2As at the 2nd of March 2007, of 17 core financial systems audits set out in the audit plan, 12 have been completed. Of the remaining 5 audits, 4 have been started and one audit has been deferred. One of these audits will be carried out by our partners KPMG.

3.3It is proposed to defer one audit namely Payments to Voluntary Bodies (Following the Public Pound) and this has been agreed with our external auditors RSM. In 2005 – 2006, Internal Audit assisted Audit Scotland with this audit area. What resulted was an agreement with them that Internal Audit would continue to monitor progress made by the Council over a 3 year period. However, in 2006 – 2007 due to operational reasons little progress has been made by the Council which has delayed this audit. Audit Scotland was kept informed and the conclusion reached was that the audit may have to be deferred to 2007 – 2008. In agreement with the Council’s new external auditors, RSM this audit has been deferred.

3.4In the last report to the Audit Committee the e-Procurement/Creditor audit was combined resulting in 50 audit days of which 25 days had been expended with a draft report issued. The remaining audit days were to be allocated to testing a new e-Procurement system. However, management have reported problems with the development of the system to be audited and may not have resolved the issues by the end of March 2007. Less audit days were expended than had been planned for Unified Benefits System joint audit work with Audit Scotland. Audit Scotland fully resourced the audit and carried the work out sooner than was planned and conflicted with staff training and joint audit work with KPMG. In discussion with RSM Robson Rhodes (RSM), joint working for this audit is currently being planned.

3.5Of the remaining 15 Non-Financial audits from this years audit plan, as at the 2nd of March 2007, 10 audits have been completed. Of the remaining 5 audits all have been started with one of them to be carried out by KPMG. 3.6 In order to meet the Audit Scotland requirement, for a review of Payments to Voluntary Organisations, it was agreed with them that the Non Financial Audit - Partnership Project Funding would focus on payments by the Council to the Tourist Board, as this is the largest amount paid to a voluntary body by the Council. This audit has now commenced.

3.7As set out in the Annual Audit Plan a total of 80 days were set aside for Other Areas – Follow Up Work etc. As at the 2nd of March 2007, a total of 38 days have been expended on this task.

3.8A total of 80 days were set aside within the audit plan for Special Investigations / Contingency audit work. As at the 2nd of March 2007, a total of 27 days have been expended.

4. SUMMARY OF AUDIT ACTIVITIES FOR 2006 - 2007

4.1It can be reported that Internal Audit continues to make reasonable progress with the Annual Audit Plan. Joint working has been ongoing with KPMG on computer audit and other joint work. As the section approaches the end of the financial year the final audits from both the Core and Non Financial audit sections of the plan are in most cases well established.

CONCLUSION Continued progress is being made on audits planned for 2006 – 2007.

6. IMPLICATIONS

5.1Policy: Update on audit plan for 2006 – 07.

5.2Financial: The audit plan is based on budgeted provision.

5.3Personnel: None

5.4Legal: None

5.5Equal Opportunities: None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT PROGRESS REPORT 2006-2007Report 57 KB DownloadRead as text
PDF
Progress Report 06_07 8Report 27 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
JT
Councillor John TacchiMember, present
DF
Deirdre ForsythSecretary, present
DM
Councillor Donald MacMillan BEMMember, present
JM
Councillor John McAlpineMember, absent
GM
Councillor Gary MulvaneyChair, present
ER
Councillor Elaine RobertsonMember, present
IM
Ian M M RossMember, present
CV
Christopher ValentineMember, present
BW
Bruce WestOfficer, present

On this subject at Argyll and Bute

Search all
  1. INTERNAL AUDIT PROGRESS REPORT 2006-2007This decision
  2. Internal audit updateNoted
  3. Internal audit report stakeholder engagementDecided
  4. Internal audit report risk managementDecided
  5. Internal audit contractNoted
  6. Internal audit report direct paymentsDecided

More from Argyll and Bute Audit Committee

All decisions
MeetingDecisionOutcome
24 Mar 2017 Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... Noted Open
24 Mar 2017 External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... Noted Open
24 Mar 2017 Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... Agreed Open
24 Mar 2017 External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies