Decision 1. To note the contents of the report and the advice given regarding the EGF funding by the Operations Manager. 2. To note that the words “other Councils and” at paragraph 3.3 of the report should be deleted. 3. To instruct that the actions detailed within the report be followed up by Internal Audit. (Ref: Report by Internal Audit Manager dated 28 February 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Audit Scotland issued a national report towards the end of November 2004 entitled, “Maintaining Scotland’s Roads”. The national report did not have any implementation dates assigned to its 9 recommendations. The Head of Roads & Amenity Services prepared an action plan incorporating the report’s recommendations and added a further 3 to reflect dependent issues. The Head of Service commenced reporting to the Audit Committee and Strategic Policy Committee (SPC) in December 2004. Set out below is the current implementation position in respect of planned actions.
Recommendation
2.1The contents of this report are noted and are to be followed up by Internal Audit.
3. DETAILS
3.1Appendix 1 sets out the current position as at the 28th of February 2007. With regard to recommendation 1, information was collated for the annual report on the condition of roads and maintenance backlog for the SPC on the 14th of December 2006.
3.2In respect of recommendation 3, Roads & Amenity Services received notice from the Scottish Executive that the 32 Council Society of Chief Officers of Transportation in Scotland (SCOTS) EGF funding bid had been unsuccessful. The section is awaiting a further proposal regarding future funding options.
3.3With regard to recommendations 7 and 8, management have reported continued progress with the Roads Maintenance Management System (RMMS) roll out. It was intended that after RMMS was established it would be linked to other Councils and the Councils own financial system. Implementation was to be complete by February 2007. However, with the loss of the SCOTS EGF funding the link to the financial system and other Councils will not be made at this time.
3.4Management was asked to conduct an option appraisal for procuring and financing road maintenance services for March 2007. Management have reported that the options appraisal has been incorporated into the Operational Services Options Appraisal which is looking at the whole of Operational Services and is due to report in May/June 2007. Once this review is complete the Audit Committee will receive a copy of the report for its review.
3.5Recommendation 4 remains an ongoing task for Operational Services.
4. CONCLUSION
4.1Progress with the implementation of recommendations will continue to be reported on by Internal Audit. 5. IMPLICATIONS 5.1 Policy: None
5.2Financial: None
5.3Personnel: None
5.4Legal: None
5.5Equal Opportunities: None
For further information please contact Ian Nisbet, Internal Audit Manager (01546 604216).
Ian Nisbet Internal Audit Manager 28th February 2007. 28Marfinalreport28Mar
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.