Decision To note the contents of the report and that a presentation on the Strategic and Operational Risk Registers would be brought to a future meeting of the Audit Committee. (Reference: Report by Governance and Risk Manager dated 12 June 2007, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
The Risk Management Group (RMG) has to report on a quarterly basis to the Audit Committee on the progress being made with the implementation of the risk management framework and business continuity planning process. Set out below is a report on the progress since the last report on 30 March 2007.
2. DETAIL
2.1The Strategic Risk Register has been approved by the SMT. The RMG in conjunction with the services Loss Control Groups will require to review and update this over the next six months. Consideration is being given to proposed amendments in the format of the register to make it similar to the Corporate Health and Safety Plan and a meeting to progress this has been arranged for the end of June.
2.2Each Service now has a Loss Control Group in place and will meet on an agreed basis. Each Loss Control Group has strong representation from all the departments within the service and has had at least one meeting. They are aware of their remit and are functioning effectively in line with the previously approved risk management framework. Each Loss Control Group reports to their DMT on an agreed basis.
2.3To ensure continuity of attendance at the Risk Management Group, each service has nominated representatives from their respective Loss Control Group. These are as follows:
1. CE Unit – Logie Collins, Carol Keeley, Alex Colligan 2. Community Services – Ernie Brown 3. Operational Services – Terry Markwick 4. Development Services – Dave Tomlinson 5. Corporate Services – Iain Jackson, Douglas Bailey
Reports 2007 – 0190DF It has been agreed that Alex Marr, Risk Management Partners should be a member of the Risk Management Group. Each Loss Control Group will send other members to the Risk Management Group when a subject requiring input from that person is to be discussed.
2.4Business Continuity Plans based on a template approved by the Risk Management Group are being prepared by each service for the loss due to flood or fire of their area of Kilmory. A full plan for the loss of Kilmory will be prepared by the end of January 2008.
2.5Business Continuity Plans have already been prepared for the loss of other buildings, eg, the Clydesdale Bank Buildings, Lochgilphead and the Loss Control Groups have responsibility for rolling out this process to departments within each Service in order that they can prepare Business Continuity Plans for each building occupied by the Council. It is intended that this process will be completed by January 2008.
2.6The recently installed performance management system has a risk management package and its use will be developed by the Governance and Risk Manager and Policy and Strategy over the next year.
Iain Jackson Governance and Risk Manager 12 June 2007
Reports 2007 – 0190DF
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.