BRIDGE ASSET MANAGEMENT PLAN

Approved Committee 1 paper

Argyll and Bute Council approved this item on Wednesday 26 September 2007. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Decision To adopt the Policy outlined in the submitted report (Ref: Report by Head of Roads and Amenity Services dated August 2007, submitted and Recommendation from the Executive dated 20 September 2007, tabled).
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Council

Summary

1.1The purpose of this paper is to outline the policy for the management of the Council’s bridges and retaining walls, note the current backlog in repairs and identify potential ways forward in order to keep the structures fit for purpose within an acceptable cost. The policy will be incorporated into the Roads Maintenance and Asset Management Plan as the Bridge Asset Management Plan.

Recommendation

That the Council adopts the policy outlined in this paper such that:-

2.1Public road structures as defined in 4.1 (bridges greater than 1.5m span and retaining walls generally supporting more than 1.0m of fill) are managed, inspected and maintained from within the Bridge Maintenance budget. Other smaller structures are maintained from within the Roads Maintenance budget;

2.2Non Public Road structures within Roads and Amenity Services’ remit (e.g. cemeteries, parks) are formally managed, inspected and maintained to the level permitted by the available budget set for this task;

2.3Other Council Services are advised of the need to manage their structural assets and the availability of the in-house expertise within the Roads Design Unit that could assist in this task.

Background

3.1The Bridge Maintenance budget provides for the management, inspection and repair of road structures such as bridges, culverts and retaining walls.

3.2In September 2005 a Code of Practice was introduced for the Management of Highway Structures. Although not mandatory it is seen as a Best Practice document and the Council could be at risk from legal action by an injured party if an incident were to take place at a structure and the guidance had not been followed. This Code of Practice is part of the suite of documents published by the Institution of Highways and Transportation, which includes the Roads Asset Management Plan.

3.3The Code of Practice defines various structure types as follows:-

Bridge – span 1.5m or more Culvert – span 1.5m or more but there is fill between the top of the culvert and the road pavement layers Retaining Wall – wall where the dominant function is to act as a retaining structure. 4 PROPOSALS

4.1Taking cognisance of the Code of Practice, it is proposed that the infrastructure supported by the Bridge Maintenance budget shall cover the following structures on public roads as listed in the List of Public Roads:-

 Bridges (which will include both bridges and culverts) of 1.5m or more clear square span measured between abutment faces (including multi cell culverts where the cumulative individual clear square span is 1.5m or greater);

 Retaining walls of over 1.0 metre retained height or where they are structurally significant as far as the public road is concerned ie partial collapse would affect traffic flows.

 Bridges and retaining walls (as above) on by-passed sections of road where the road is still the responsibility of the Council.

4.2The existing bridge register will be reviewed for compliance with the above and adjusted accordingly. The current ongoing programme of locating and inspecting the retaining walls will be altered to comply with these requirements.

4.3The estimated number of structures included in 4.1is:-

Area No. of bridges Estimated no. of Retaining Walls B&C 186 700 H&L 154 300 MAKI 311 400 OL&TI 307 600 Total 958 2000

The approximate reconstruction value of the above is £435m. At present a programme of locating and assessing the retaining walls is underway and the estimated numbers are based on the results found to date for approximately 70% of the road mileage increased pro rata to the total of 1436 miles.

4.4There are a significant number of structures on the public road network that are smaller than the criteria listed in 4.1 and these will be maintained from the Roads Road Maintenance budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BRIDGE ASSET MANAGEMENT PLANAgenda 152 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

30 of 35 attended
GC
Councillor Gordon ChalmersMember, present
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
VD
Councillor Vivien DanceMember, present
MD
Councillor Mary-Jean DevonMember, present
GF
Councillor George FreemanMember, apologies
AH
Councillor Alison HayMember, apologies
AH
Councillor Anne HornMember, present
DK
Councillor Daniel KellyMember, apologies
DK
Councillor Donald KellyMember, present
DK
Councillor David KinniburghMember, present
DM
Councillor Donald MacdonaldMember, present

All 35 on the meeting page

On this subject at Argyll and Bute

Search all
  1. BRIDGE ASSET MANAGEMENT PLANThis decision
  2. Bridge asset management planAgreed

More from Argyll and Bute Argyll and Bute Council

All decisions
MeetingDecisionOutcome
23 Sep 2026 Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro... Decided Open
23 Sep 2026 Nhs highland director of public health annual report 2025Decision The Council – 1. noted the Director of Public Health Annual Report 2025; and 2. supported the recommendation... Noted Open
23 Sep 2026 Leader's reportDecision The Council – 1. noted the contents of the submitted report; and 2. noted that any reports, briefings or cop... Noted Open
23 Sep 2026 Policy leads reportDecision The Council noted the content of the submitted report. (Reference: Report by Policy Lead Councillors dated 1... Noted Open
23 Sep 2026 Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex... Decided Open