Decision The Council – 1. Approved the new Corporate Plan 2007-2011 and beyond, noting that the Plan will require further revision in the light of the development of Outline Business Cases for town centre/waterfront developments as noted at 5 below. 2. Adopted the Statement of Intent describing key service delivery promises over the next four years. 3. Noted the baseline projections for the financial strategy and agrees the development of it on the basis of the conclusions and recommendations set out in the IPF report. 4. Agreed the monitoring and annual review arrangements outlined in paragraph 6 of the Chief Executive’s report. 5. ( i ) Recognises the role it has to play in place making within its communities; and accordingly (ii) progresses the process of developing from Initial Business Case to Outline Business Case for all the town centre and waterfront development projects, noting that at the stage of prioritisation of the Outline Business Cases, the OBCs will be subject to a process of independent scrutiny based on the weighing criteria approved by the Council in February 2007. (Ref: Report by Chief Executive dated 4 September 2007, Report by Head of Strategic Finance dated 17 September 2007, Amended Recommendation from Mid Argyll, Kintyre and Islands Area Committee of 5 September 2007, Recommendation of the Helensburgh and Lomond Area Committee of 4 September 2007, Recommendation of the Oban, Lorn and the Isles Area Committee of 5 September 2007 and Recommendation of the Bute and Cowal Area Committee of 4 September, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1The Council approve the recommended priority order for town centre and waterfront regeneration projects as follows: First - Dunoon Second - Helensburgh Third - Campbeltown Fourth - Oban Fifth - Rothesay
2.2Proper governance arrangements should be established as outlined in paragraph 3.8
3 DETAIL
3.1The Council has identified town centre and waterfront regeneration as a priority. Town centre and waterfront projects were previously identified in the 2006-2008 Corporate Plan and are identified as a priority in the draft of the Corporate Plan being submitted to the Council on 26 September for approval. These projects have featured throughout the development phase of the revised Corporate Plan. The Council has previously allocated revenue budget to support the commissioning of studies for such projects and also to fund initial development/planning stages. Limited provision has also been made within the Capital Plan for town centre and waterfront regeneration.
3.2Progressing town centre and waterfront projects is likely to place a significant demand on resources both in terms of officer time and budget. The Council has limited resources and it is inevitable that there will be a scarcity of resources to allow all of the projects to progress simultaneously. It is therefore essential that the Council establish a priority order for the town centre and waterfront regeneration projects.
3.3Establishing a priority order is not a rejection of any project but a guide to the projects that should be given priority when it comes to allocating scarce resources. Each project has a different package of measures that will have different demands in terms of officer support and budgetary requirement. Although a project may not be the number one priority there may still be certain aspects of that project that can be progressed providing higher priority projects are not utilising all of the resources available for town centre and waterfront projects. As an example project A may have a demand for significant capital expenditure on council assets which requires a high level of input from Property Services and which uses all of the available Capital Plan allowance whereas project B requires officer support from Development Services and Estates to market and dispose of certain packages of land or buildings.
3.4The Council agreed on 13 February 2007 an approach to weighting and scoring capital projects and this has been used to assess the initial business cases for town centre and waterfront regeneration projects. A copy of the agreed weighting and scoring criteria is attached.
3.5An initial business case following the guidance for capital projects has been prepared for each of the 5 town centre and waterfront regeneration projects. The IBCs were submitted to the September meetings of the area committees. The agreed weighting and scoring criteria have been applied to the IBCs along with any comments from the area committees.
3.6The outcome of the assessment process is the following priority order: First - Dunoon Second - Helensburgh Third - Campbeltown Fourth - Oban Fifth – Rothesay
3.7The assessment was carried out by the Capital Planning Group comprising Sandy Mactaggart (Head of Facility Services), Malcolm MacFadyen (Head of Community Regeneration), Brian Barker (Policy and Strategy Manager) and Bruce West (Head of Strategic Finance).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.