Decision 1. To agree in principle to the development of the in house option as detailed in the report; 2. To note the current position relating to Helensburgh and Lomond within Scottish Enterprise Dunbartonshire; 3. To note the concerns about the lack of co-terminosity and to keep under review the discussions at Scottish Enterprise Dunbartonshire and seek a consistent position across the whole Argyll and Bute area. (Reference: Report by Director of Development Services, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates members of the Executive on progress regarding changes to the delivery of Business Gateway as announced by the Scottish Government in autumn 2007. This report covers both the Highlands and Islands and Scottish Enterprise areas, reflecting the Council’s geographic coverage.
Recommendations
2.11. That the Executive considers the in-house option as a preferred way forward for Business Gateway delivery in Argyll and Bute, Highlands and Islands area at present.
2. That members note the current position in Dunbartonshire relating to Helensburgh and Lomond.
3. DETAIL
3.1Members will be aware that in autumn 2007, the Scottish Government announced its intention to transfer the Business Gateway function from the Enterprise Network to local authorities by April 2008. Business Gateway is the mechanism by which public sector advice and support is given to new and expanding businesses. In some areas business start-up grants are also offered. Business Gateway is currently operated by Scottish Enterprise but not by Highlands and Islands Enterprise. 3.2 The Government wishes to see a uniform approach to Business Gateway across Scotland as part of its Economic Strategy. HIE are therefore undertaking an exercise to identify which of their existing business support activities fit the Business Gateway model and what resources are currently used to deliver these. HIE considers that, given the scale of the exercise, transfer of activity is unlikely to take place before the end of 2008. 3.3 A steering group of officers from HIE and the Highlands and Islands local authorities has met on 2 occasions to map out a route forward. The next meeting will be held on 24th January in Inverness, preceded by a local authorities only meeting. An initial officer meeting has taken place with Scottish Enterprise Dunbartonshire and East and West Dunbartonshire Councils. COSLA Leaders, SOLACE and SLAED (Scottish Local Authorities Economic Development) are also involved in strategic discussions. 3.4 It has become apparent that the Enterprise Networks will be transferring a minimal resource to local authorities as the Business Gateway function. This will relate primarily to existing contracts with business advisors and the transfer of one administrative/clerical officer post. In the HIE area, the value of business gateway services will transfer to the local authority. This will be an as yet unspecified share of £2m. There are no identified one-off transition costs and no identified overheads for management, development, publicity or administration of the staff, contract or function that will transfer. As the Council does not have a Business Development Unit, the additional function of Business Gateway delivery will have to be considered in terms of work plans and programmes. There will need to be a capacity building process to deal with the management, development and operation of the Business Gateway function. HIE Argyll an Islands have offered support and expertise over the transfer period. 3.5 The transfer of Business Gateway to the Council offers an opportunity to create a one door approach for businesses to receive services from the Council. This would require close cross departmental working and quality control and would comply with the Council’s continuous improvement agenda. Options can be explored relating to the contact centre. 3.6 Highlands and Islands area
In the HIE area, one contractor currently delivers business advice across the whole area. This contract will have to be terminated as a result of the creation of Business Gateway because of fundamental changes to delivery. HIE are seeking agreement on the method of procurement for the new service, and have proposed 3 options for Councils to consider. These are:
Option 1 – Extend the existing advice services contract with a single contractor
This has been ruled out as it contravenes procurement rules.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.