Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 21 January 2009. Below is the council's own wording, with the papers it was decided on.
Decision The Committee agreed that planning permission be granted for the reason stated in the report. (Reference: Report by Head of Planning dated 9 January 2009, submitted, Supplementary Report by Head of Planning dated 19 January 2009, tabled ).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
DEVELOPMENT SERVICES Ward Number - 3 Mid Argyll PLANNING APPLICATION REPORT Date of Validity - 22.10.08 MID ARGYLL, KINTYRE & THE ISLANDS Committee Date - 21.01.09 __________________________________________________________________________
Reference Number: 08/01892/DET Applicants Name: Ford Community Project Ltd Application Type: Detailed Application Description:Erection of Community Centre and formation of associated facilities and car park Location: Land south of Torbreck, Ford __________________________________________________________________________
(A) THE APPLICATION
(i) Development Requiring Express Planning Permission
• Erection of Community Centre; • New access • Formation of car park • Formation of play area
(ii) Other specified operations.
• Connection to public water main • Connection to public sewer
It is recommended that planning permission be granted subject to the conditions attached. __________________________________________________________________________
(C) SUMMARY OF DETERMINING ISSUES AND MATERIAL CONSIDERATIONS
(i) Development Plan Context:
The development lies within the PDA (Potential Development Area) 12/70 within the settlement of Ford in the Draft ‘Argyll and Bute Local Plan’ Post Inquiry Modifications (November 2008). Ford is classified as a ‘Small Town & Village’ within that Plan which enables appropriate infill/rounding-off development within the settlement, up to ‘medium’ scale.
Whilst the application is for development only within the northern section of the PDA, it has been submitted along with indicative proposals for the remainder. Within the Local Plan this PDA is identified for mixed uses of medium density, with 25% of any housing to be affordable. The indicative proposal beyond the boundaries of the application retains much of the remaining land in open use. There is a scheduled monument (cairn) within the PDA the site and setting of which requires protection form built development. Indicative proposals include an all-weather sports pitch, the formation of a mountain bike trail within a former gravel pit, and 4 houses to rent or for sheltered housing. The present application does not have adverse consequences for the prospective development of the remainder of the PDA for mixed community/residential uses.
There is no conflict between the proposal and the adopted but outgoing ‘Mid Argyll Local Plan’. All other material considerations including access, parking, amenity, privacy, setting of the nearby monument and design are all considered acceptable.
(ii) Representations:
There have been two objections lodged by two households. There have also been two letters of support, one of which points to the size of a community ballot which found substantial favour within the community for this development.
(iii) Consideration of the Need for Non-Statutory or PAN 41 Hearing:
Not applicable.
(iv) Reasoned Justification for a Departure to the Provisions of the Development Plan.
Not applicable.
(v) Is the Proposal a Schedule 1 or 2 EIA development:
No.
(vi) Does the Council have an interest in the site:
No.
(vii) Need and Reason for Notification to Scottish Ministers.
Not applicable
(viii) Has a sustainability Checklist Been Submitted:
Not required.
Angus J Gilmour Head of Planning 9th January 2009
Author: Derek Hay 01546 604083 Reviewing Officer: Richard Kerr 01546 604080 NOTE: Committee Members, the applicant, agent and any other interested party should note that the consultation responses and letters of representation referred to in Appendix A, have been summarised and that the full consultation response or letter of representations are available on request. It should also be noted that the associated drawings, application forms, consultations, other correspondence and all letters of representations are available for viewing on the Council web site at www.argyll- bute.gov.uk CONDITIONS AND REASONS RELATIVE TO APPLICATION: 08/01892/DET
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.