MR J HERROD: ERECTION OF DWELLINGHOUSE AND DETACHED GARAGE, UPGRADE OF EXISTING ACCESS AND INSTALLATION OF SEPTIC TANK WITH ASSOCIATED INFILTRATION SYSTEM: LEANANMOR, MUASDALE (REF: 23/01358/PP)

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 19 June 2024. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard Time Limit Condition (as defined by Regulation) Standard Condition on Soil Management During Construction Additional Conditions PP - Approved Details & Standard Notes – Non EIA Development 1. The development shall be implemented in accordance with the details specified on the application form dated 12.07.2023, supporting information and, the approved drawings listed in the table below unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Plan Title. Plan Ref. No. Version Date Received Location Plan Herrod 23/100-01 Rev A. 13.07.2023 Site Plan Herrod 23/100-02 Rev B. 07.02.2024 Floor Plans and Elevations of Dwellinghouse Herrod 23/100-03 Rev A. 13.07.2023 Floor Plans and Elevations of Detached Garage Herrod 23/100-04 Rev A. 13.07.2024 Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 2. PP – Timescale to be Agreed for Completion No development shall commence until details of the proposed timescale for completion of the approved development have been submitted to and approved by the Planning Authority. Thereafter, the development shall be implemented in accordance with the duly approved timescale for completion unless an alternative timescale for completion is otherwise agreed in writing with the Planning Authority. Reason: In order to comply with the requirements of NPF4 Policy 16F. 3. PP – Access, Parking and Turning As Shown The parking and turning area shall be laid out and surfaced in accordance with the details shown on the approved plans prior to the development first being occupied and shall thereafter be maintained clear of obstruction for the parking and manoeuvring of vehicles. Notwithstanding the details on the approved plans, the access arrangements shall be implemented to accord with the following requirements with the submission of further information for approval as specified: a. Prior to the occupation of the development, the existing access on the A83 Trunk Road shall be upgraded, generally in accordance with Herrod drawing No. 23/100-02 Revision B dated 30.09.2023, to the satisfaction of the planning authority, after consultation with Transport Scotland. b. The first 5 metres from the edge of the A83 trunk road shall be surfaced in a bituminous surface and measures shall be adopted to ensure that all drainage from the site does not discharge onto the trunk road. c. Prior to the commencement of development, details of the fencing / barrier proposals along the trunk road boundary shall be submitted to, and approved by, the planning authority, after consultation with Transport Scotland and thereafter implemented prior to commencement of operation. The fencing / barrier proposals shall be located such that they can be erected and maintained from within the development without requiring access to the trunk road. Reasons: In the interest of road safety; to ensure that the standard of access layout complies with the current standards and that the safety of traffic on the trunk road is not diminished; to ensure that drivers of vehicles leaving the site are enabled to see and be seen by vehicles on the trunk road carriageway and join the traffic stream safely; to ensure that material from the site is not deposited on the trunk road to the detriment of road safety; to ensure that the efficiency of the existing drainage network is not affected; to minimise the risk to pedestrians and animals gaining uncontrolled access to the trunk road with consequential risk of accidents. 4. No built development should take place below existing ground level of 3.76mAOD. Reason: In order to prevent unacceptable flood risk to people and property. To ensure a precautionary approach to flood risk and to ensure the longevity and future resilience of the development of the site to climate change and sea level rise by promoting flood risk avoidance as set out in Policy 22 of NPF4. 5. PP – Submission of Details of Materials Notwithstanding the effect of Condition 1, no development shall commence until written details of the type and colour of materials to be used in the construction of external walls, roofs, windows and doors have been submitted to and approved in writing by the Planning Authority. The development shall thereafter be completed using the approved materials or such alternatives as may be agreed in writing with the Planning Authority. Reason: In order to integrate the development into its surroundings. 6. PP – Full Landscaping Scheme No development shall commence until a scheme of boundary treatment, surface treatment and landscaping has been submitted to and approved in writing by the Planning Authority. The scheme shall comprise a planting plan and schedule which shall include details of: i) Existing and proposed ground levels in relation to an identified fixed datum; ii) Existing landscaping features and vegetation to be retained; iii) Location design and materials of proposed walls, fences and gates; iv) Proposed soft and hard landscaping works including the location, species and size of every tree/shrub to be planted; v) ... view the full minutes text for item 5.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development & Economic Growth

Planning Application Report and Report of Handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 relative to applications for Planning Permission or Planning Permission in Principle

Reference No: 23/01358/PP Planning Hierarchy: Local Application Applicant: [name removed]: Erection of dwellinghouse and detached garage, upgrade of existing access and installation of septic tank with associated infiltration system Site Address: Leananmor Muasdale Argyll And Bute

DECISION ROUTE

Committee Decision under Local Government Scotland Act 1973

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission • Erection of dwellinghouse and detached garage; • Improvement of existing vehicular access onto A83(T); • Installation of septic tank and soakaway.

(ii) Other specified operations • Connection to public water supply.

(B) RECOMMENDATION:

Recommend that planning permission be approved subject to the conditions and reasons attached.

(C) CONSULTATIONS:

Transport Scotland – 15.09.23, 20.09.23, 07.03.24 – No objection subject to conditions relating to the provision of improvements to the existing access onto the A83(T) to a standards suitable to serve the development proposed.

Area Roads Mid Argyll Kintyre And Islay - 07.08.2023 – No objection subject to conditions prescribing requirements for onsite parking and turning.

Scottish Water - 26.07.2023 – No objections subject to advice to applicant.

Scottish Environmental Protection Agency - 03.08.2023 – No objection subject to condition prescribing a minimum finished floor level to protect the development against risk of flooding. (D) HISTORY:

04/01130/OUT - Erection of a dwellinghouse – Approved 21.09.2004

14/00424/PPP - Site for the erection of dwellinghouse and garage. (As amended by email correspondence received 26.06.14) – Withdrawn 23.07.2015

15/02370/PPP - Site for the erection of dwellinghouse – Approved 27.10.2015

16/02681/PPP - Site for the erection of dwellinghouse (amended access relative to planning permission in principle reference 15/02370/PPP). – Approved 24.11.2016

18/02627/PP - Erection of dwellinghouse with garage, installation of treatment plant, air source heat pump and formation of new access off the A83(T) – Withdrawn 28.02.2019

(E) PUBLICITY:

Advert Type: Regulation 20 Advert Local Application Expiry Date: 25.08.2023

(F) REPRESENTATIONS:

(i) Representations received from:

Objection

1. Jessie Macdougall Isleview Muasdale Tarbert Argyll And Bute 25.07.2023 2. John Macdougall Isleview Muasdale Tarbert Argyll And Bute 25.07.2023 3. [name removed] Mara Muasdale Tarbert Argyll And Bute 07.08.2023 4. Archie Graham Parklea Muasdale Tarbert Argyll And Bute 01.08.2023 5. [name removed] Old Post Office Muasdale Tarbert Argyll And Bute 08.08.2023 6. Margaret Graham Parklea Muasdale Tarbert Argyll And Bute 01.08.2023 7. Anne Maccallum Sunset Cottage Muasdale PA29 6XD 04.08.2023 8. Sharon Maccallum Sea Renity House Muasdale PA29 6XD 04.08.2023 9. Gary Breeden Sea Renity House Muasdale PA29 6XD 04.08.2023 10. Joseph Loganbill Taigh A' Pheantair Muasdale PA29 6XD 09.08.2023

Support

n/a

Representation

Jeanne Loganbill Taigh A' Pheantair Muasdale Tarbert Argyll And Bute 08.08.2023

Representations are published in full on the planning application file and are available to view via the Public Access section of the Council’s website.

(ii) Summary of issues raised:

• Concern is raised in relation to road safety and the use of the proposed means of vehicular access. In particular it is noted that visibility to the south is limited by a hedge which would appear to be outwith the ownership and control of the applicant.

• Concern is raised that the existing road layout/40mph speed limit of the A83(T) is unsuitable to accommodate the new access.

Comment: It is noted that Transport Scotland have not raised objection to the proposal on road safety grounds. See assessment below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23_01358_PP, 10/06/2024 Pre-Agenda Briefing of the Planning, Protective Services and Licensing CommitteeAgenda 481 KB Download
PDF
MR J HERROD: ERECTION OF DWELLINGHOUSE AND DETACHED GARAGE, UPGRADE OF EXISTING ACCESS AND INSTALLATION OF SEPTIC TANK WITH ASSOCIATED INFILTRATION SYSTEM: LEANANMOR, MUASDALE (REF: 23/01358/PP)Report 327 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 15 attended
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairVice-Chair, present
JB
Councillor Jan BrownMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, apologies
DH
Councillor Daniel HampseyMember, present
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
MI
Councillor Mark IrvineMember, present
AK
Councillor Andrew KainMember, present
PD
Councillor Paul Donald KennedyMember, present

All 15 on the meeting page

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies