Mid Argyll, Kintyre & the Islands Area Committee approved this item on Wednesday 4 February 2009. Below is the council's own wording, with the papers it was decided on.
Decision The Area Committee approved the following allocations of Capital Receipt funds with Tarbert Scottish Series grant being approved subject to the receipt and successful assessment of the 2007/08 accounts. It was further noted that the remaining funding requirement for Lochgilphead Dropped Kerbs would be prioritised , if required, within the next financial year. Project Criteria Total Project Cost % of cost Sum allocated %age of cost Port Mor Centre Met Forward Looking > Developing the third sector (page 21) ; Campaigning > Service Delivery Challenges> People on the Fringe > Access to Key Services (Page 24) £12,700 50% £6000 47% Tarbert Scottish Series Met Area Plan under Outstanding Environment > Events and Festivals. £ 30,000 25% £7500 45% Front Green Improvements, Lochgilphead (drainage and top dressing) Partially met Campaigning > Economy > Developing Argyll and Bute as a quality destination… extending the tourism season £7,500 100% £3220 43% Lochgilphead Dropped Kerbs Met Corporate Plan theme of Vibrant Communities through improving access to services (ABC07a) £20,000 72% £8730 44% Campbeltown Street Signage Fingerpost Scheme Met Area Strategy>Vibrant Communities>Town Centre Animation £8770 66% £5770 66% Total £31,220 (Reference: Report by Area Corporate Services Manager dated 21 January 2009, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1Members are invited to consider applications for the use of capital receipt funds in accordance with the criteria set out for use of this fund by the Executive Committee in March 2008 and the application procedure agreed by the MAKI Committee on 6 August 2008.
Recommendation
2.1That members consider the recommendations for funding detailed in Appendix 1.
Background
3.1The Executive Committee in March 2008 agreed the following criteria for spend of capital receipt money:
1) In respect of area committees this means the funding that becomes available can be used for revenue and capital expenditure
2) Area Committees must use funds in a way that contributes to the Corporate Plan (including area plans) and Statement of Intent. Funding can be used as a contribution to projects in either the revenue or capital budget
3) Where funding is being used for a capital project then the criteria for capital expenditure are as follows: - The expenditure must result in the creation of an asset owned by the Council - The expenditure must be in respect of an asset already owned by the council and must significantly increase the value of the asset, extend the life of the asset or enhance the operating capability of the asset
4) Where funding is being used for revenue expenditure then the expenditure, in addition to contributing to the Area Plan, Corporate Plan or Statement of Intent must relate to: - Repair and maintenance of public sector infrastructure - A one off contribution to an external body towards the capital cost of a community asset or a contribution to an event - A one off contribution towards the cost of an event that has a significant impact on the corporate objectives of the Council. 5) Payments must not be made to support ongoing revenue costs and must not create an ongoing commitment on the Council’s revenue budget.
3.2Current Applications Further to the process agreed at the August Committee two external applications have been received for the Port Mor Centre in Port Charlotte and Tarbert Scottish Series. Relevant Council officials were also contacted to see if there were any internal schemes requiring funding and a number of these were brought forward for members’ consideration. Para 3.3 and Appendix 1 detail the projects, requested funding and recommendations in terms of funding.
3.2Budget Available Appendix 2 details the sums previously committed for expenditure. The Committee previously allocated £5000 to the Kilarrow / Bowmore footpath. This project has been delayed due to planning permissions objections and at this stage will not be progressing any further. The £5000 allocated has been added back into the available budget.
The budget remaining for 2008/09 is £31,220
3.3Assessment The assessment process considers whether the application meets, partially meets, or does not meet the criteria as agreed by the Executive committee (see para 3.1 above)
Port Mor Centre: The grant requested is to do further work on the access road to the facility and pay for some furnishings, equipment and room dividers. The application states that this will allow the centre to host conferences, support interaction between young people and improve access to the facilities.
The application assessed by the Area Community Learning and Regeneration Manager and is found to meet the criteria as a contribution to an external body towards the capital cost of a community asset. The project contributes to the delivery of the corporate plan under Forward Looking > Developing the third sector (page 21); Campaigning > Service Delivery Challenges> People on the Fringe > Access to Key Services (Page 24). In addition the funding will also add value to the investment already made by the Council and other funders to the facility.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.