Mid Argyll, Kintyre & the Islands Area Committee noted this item on Wednesday 4 February 2009. Below is the council's own wording, with the papers it was decided on.
Decision The Committee noted the contents of the report and requested a future report from the European Manager as to whether there were any EU funding streams available for strategic roads projects. (Reference: Report by Head of Roads and Amenity Services dated 13 January 2009, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Recommendations
It is recommended that the Committee note the contents of the report.
3. DETAILS
3.1Preliminary design work has been completed for localised widening of the road to minimum design standards and minimum cost. Detailed design is now in progress. The design work should be complete by May 2009. Project cost is estimated at £600,000
3.2Planning Services have intimated that the works are permitted development and that no formal planning application is required.
3.2Preliminary discussions with the landowner have been favourable and there is an expectation that land can be acquired on a voluntary basis. Land plans have been sent to Legal to formally acquire the land.
3.3Tenders have been issued for the archaeological investigations and work should start in late January 2009.
3.3The current programme for the works is for construction in the summer of 2010. This was to allow time to deal with the archaeological issues, possible planning and land acquisition. If the archaeological investigation reveal no issues and the land can be acquired then we will seek to accelerate the construction work with a possible start in the summer of 2009.
1 4. IMPLICATIONS
4.1Policy – None. 4.2 Financial – Capital funding is required from annual block allocation 4.3 Personnel – None 4.4 Equalities Impact Assessment - None 4.5 Legal – None.
For further information, please contact Peter Ward (Tel: 01546 604651).
Stewart Turner Head of Roads and Amenity Services 13 January 2009
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.