Decision The committee agreed that the Head of Legal & Protective Services be instructed to conclude a Deed of Variation to the S75 Agreement as detailed in the report by the Head of Planning Services. (Reference: Report by the Head of Planning Services dated 30 th March 2009 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
DEVELOPMENT SERVICES Ward Number - 6 Cowal BUTE & COWAL AREA COMMITTEE Committee date - 7 April 2009
Reference Number: 01/01553/DET Applicants Name: CRE Energy Limited (agent Scottish Power) Application Description: Erection of 35 wind turbines and associated infrastructure; de-forestation works; and improvements of access tracks(As Amended) Location: Land at Cruach Mhor, Glendaruel
PRIVATE WATER SUPPLY, GLENDARUEL
A Background
1. In association with the grant of planning permission 01/01553/DET for a wind farm at Cruach Mhor, Glendaruel, a Section 75 Agreement was concluded which, inter alia, required the developer to provide and maintain an alternative private water supply to households in the Duiletter area of Glendaruel. th 2. Reports were considered at the Area Committee meeting on 7 September 2004 and 5 April 2005 relative to breakages in the private water supply and whether or not the Section 75 Agreement had been breached. It was latterly resolved to continue the matter.
3. The Department became aware during June/July 2007 that residents were still experiencing problems with their water supply. These concerns were raised with Scottish Power Renewables who advised that recent problems with the water treatment plant had been unpredictable and extensive.
4. Scottish Power Renewables have now written to the Council (copy attached) advising that they consider that it may be in the best interests of all parties to contract Scottish Water to extend the public water supply beyond Kilmodan Primary School to service the 17 properties affected. If such a scheme were to be installed, they would seek a Deed of Variation to the S75 Agreement which provides that, on the satisfactory completion of the necessary works and the adoption of the Glendaruel water supply by Scottish Water, conditions NINTH to THIRTEENTH of the S75 Agreement shall no longer be in force.
5. Following consultations with the residents affected, Scottish Power Renewables report that there appears to be widespread support for this proposal although 2 households have rejected the offer.
B Recommendation
1. The proposed public water supply would appear to provide a more secure long-term solution to the water supply difficulties experienced. It is therefore recommended that the Head of Legal & Protective Services be instructed to conclude a Deed of Variation to the S75 Agreement which provides that, on the satisfactory completion of the necessary works and the adoption of the Glendaruel water supply by Scottish Water, conditions NINTH to THIRTEENTH of the S75 Agreement shall no longer be in force.
Angus J Gilmour Head of Planning Services 30 March 2009
Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version APPENDIX
16.03.2009 Argyll & Bute Council Our Ref: A&BC letter 1 Development Management Your Ref: xxx Hill Street Dunoon PA23 7AP
For the Attention of David Eaglesham
Dear Sir
(B ) PROPOSED PERMANENT WATER SUPPLY TO CLACHAN OF GLENDARUEL
Thank you for taking time to meet my colleague Iain Cassidy and myself on 5th February 2009.
As you will be aware, in 2003 Scottish Power Renewables (SPR) developed Cruach Mhor Windfarm near Glendaruel. As part of the Planning Agreement, SPR agreed to install the associated water supply for the 17 properties in the Clachan of Glendaruel in order to ensure that the windfarm development had no adverse impact on the private water supplies. The current water supply is intended to last for the operational period of the windfarm (25 years) and thereafter the responsibility for the operation and maintenance of the existing water plant shall revert to the 17 affected properties.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.