Decision The Committee: i. Noted the Programme Governance and Management arrangements which will be used during the CHORD programme. ii. Asked that the last line of paragraph 3.1 of the report be amended to read “which would have a personal financial interest in any project”. iii. Noted that the Bute & Cowal Area Committee wish to retain the status quo in relation to membership of Project Boards. (Reference: Report by the Director of Corporate Services dated 24 th March 2009 – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1When the Council decided on 27 November 2008 to allocate, but not yet commit, £30+m of capital funding to projects across Argyll and Bute which followed its consideration of the CHORD OBCs, it remitted to the Executive to establish programme governance arrangements to ensure the CHORD Programme was taken forward in a planned, transparent and accountable way. This involved setting up a Programme Management Board (PMB) to manage the programme and Project Boards to develop and manage the individual projects, following Prince2 and Managing Successful Programmes (MSP) principles.
1.2The attached minute extract is from the PMB meeting on 20 March 2007(Appendix 1). The PMB has agreed Programme Governance and Management arrangements (Appendix 2) and a template for a Project Initiation document (PID) (Appendix 3). The PID is the preliminary deliverable towards the first main deliverable of a Full Business Case (FBC) for each project.
Recommendations
2.1Area Committees and Project Boards are asked to note the Programme Governance and Management arrangements which will be used during the CHORD programme.
2.2Area Committees are invited to appoint relevant local Councillors to be core members of the relevant Project Board
2.3Project Boards are requested to put in place arrangements that will enable them to sign off the completed PID as the first preliminary deliverable of the project.
2.4Project Boards are requested to consider whether they wish to include other people to become non- core consultative members on the Project Board.
3 Detail
3.1The Governance arrangements provide for a Project Board to cover all the projects in each town. This is to comprise the relevant local councillors and the link Director, as core members. It will be those core members of the Board who sign off the important documents and stages of the project, such as the PID and FBC. Area Committees are asked to appoint the Councillor Members of the Board. The PMB has suggested this should be a small number of local Councillors, appropriate and necessary to the projects being taken forward. Other councillors could be appointed as non–core members where there is a relevant interest. The Board may also include other people from the community eg local community council or others. It should not include any person who may have or represent an organisation which would have a financial interest in any project.
3.2The Programme and Project Management arrangements provide for a Programme Senior Responsible Officer (SRO). This will be the Head of Economic Development and Strategic Transportation who will have ultimate accountability for the delivery of the programme. There will be a Programme Manager, yet to be appointed, by way of secondment for 6 months in the first instance. The recruitment of this person is underway. Each Project will have a Project Manager who will be appointed from within Development Services to lead a Project Team for each project and work with the Project Board. The respective roles associated with all these arrangements are set out in the Programme Governance and Management Arrangements. Area Corporate Services Managers will administer the Project Boards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.