09/01628/PP: APPLICATION FOR INSTALLATION OF BIOMASS BOILER AND FORMATION OF TIMBER BOARDED ENCLOSURE: STRACHUR MEMORIAL HALL, FREE CHURCH ROAD, STRACHUR: STRACHUR MEMORIAL HALL COMMITTEE
AgreedPlanning2 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 20 January 2010. Below is the council's own wording, with the papers it was decided on.
Decision Agreed to grant planning permission subject to the following conditions and reasons:- 1. That the development to which this permission relates must be begun within three years from the date of this permission. Reason: In accordance with Section 58 of the Town and Country Planning (Scotland) Act 1997. 2. The development shall be implemented in accordance with the approved drawings – Drawing No.1 Plan Showing Position of Proposed Unit, Drawing No.2 Plans and Elevations as Proposed and Drawing No.3 Site and Location Plans unless the prior written approval of the Planning Authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Reason : For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 3. Vehicle movements, collections and deliveries associated with the operation of the Biomass boiler and fuel storage shall not take place outwith the hours of 7.00 am to 18.00 pm weekdays excluding Scottish Public Holidays without the prior written approval of the Planning Authority in consultation with the Council’s Head of Legal and Protective Services. (Ref: Report by Head of Planning dated 29 December 2009, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Development Services
Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________
Reference No: 09/01628/PP
Planning Hierarchy: Local
Applicant: Strachur Memorial Hall Committee
Proposal: Installation of Biomass Boiler and Formation of Timber Boarded Enclosure
Site Address: Strachur Memorial Hall, Free Church Road, Strachur ____________________________________________________________________________
DECISION ROUTE
(i) Local Government (Scotland) Act 1973 ____________________________________________________________________________
(A) THE APPLICATION
(i) Development Requiring Express Planning Permission
• Installation of biomass boiler • Formation of timber boarded enclosure surrounding biomass boiler Other specified operations
• Not applicable. ____________________________________________________________________________
(B) RECOMMENDATION:
It is recommended that planning permission be granted subject to the attached conditions and reasons. ____________________________________________________________________________
(C) HISTORY:
None relevant to this proposal. ____________________________________________________________________________
(D) CONSULTATIONS:
Area Roads Manager 30.11.09 - No objections
Environmental Services Manager - No comments to date (E) PUBLICITY:
Article 9 neighbour notification (closing date 14th December 2009) and Regulation 20 Advert Local Application (closing date 1st January 2010). ____________________________________________________________________________
(F) REPRESENTATIONS:
One letter of representation has been received at the time of writing from Lorna Whyte, Aotearoa, Free Church Road, Strachur (e-mail dated 26th November 2009)
Summary of issues raised: 1. There seem to be two types of biomass boilers presented in the specifications accompanying the application and they are seeking clarification as to which one is planned for the site. Comment: The agent (letter dated 16th December 2009) has confirmed that the boiler to be used is the KSM-Multistoker Type F 375-35F with a rating of 35 kW. 2. Further information is required on the level of noise expected from the running of the biomass boiler together with the frequency of use and at what times of the day it will operate. Comment: The agent (letter dated 16th December 2009) has stated that noise emissions have been investigated with the manufacturer in Denmark who has advised that the noise level will not exceed 60 decibels inside the sealed container and that, externally, the noise level would be similar to a domestic washing machine. The reference to frequency of use is not possible to quantify and will be related to user demand and prevailing weather conditions.
(G) SUPPORTING INFORMATION
Has the application been the subject of:
(i) Environmental Statement: No (ii) An appropriate assessment under the Conservation (Natural Habitats) Regulations 1994: No (iii) A design or design/access statement: No (iv) A report on the impact of the proposed development eg. Retail impact, transport impact, noise impact, flood risk, drainage impact etc: No ____________________________________________________________________________
(H) PLANNING OBLIGATIONS
(i) Is a Section 75 agreement required: No ____________________________________________________________________________
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30, 31 or 32: No ____________________________________________________________________________ (J) Section 25 of the Act; Development Plan and any other material considerations over and above those listed above which have been taken into account in the assessment of the application
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
09/01628/PP: APPLICATION FOR INSTALLATION OF BIOMASS BOILER AND FORMATION OF TIMBER BOARDED ENCLOSURE: STRACHUR MEMORIAL HALL, FREE CHURCH ROAD, STRACHUR: STRACHUR MEMORIAL HALL COMMITTEEReport
1309/01628/PP: APPLICATION FOR INSTALLATION OF BIOMASS BOILER AND FORMATION OF TIMBER BOARDED ENCLOSURE: STRACHUR MEMORIAL HALL, FREE CHURCH ROAD, STRACHUR: STRACHUR MEMORIAL HALL COMMITTEEThis decision
09/01628/PP: APPLICATION FOR INSTALLATION OF BIOMASS BOILER AND FORMATION OF TIMBER BOARDED ENCLOSURE: STRACHUR MEMORIAL HALL, FREE CHURCH ROAD, STRACHUR: STRACHUR MEMORIAL HALL COMMITTEEThis decision
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.