09/01535/PP: APPLICATION FOR ERECTION OF TEMPORARY CONSTRUCTION COMPOUND FOR USE AS OFFICES AND WELFARE FACILITIES (FOR A MAXIMUM PERIOD OF 18 MONTHS): GLENMORAG CAR PARK, KILBRIDE ROAD, DUNOON: SCOTTISH WATER

Agreed Planning 2 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 20 January 2010. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Decision Agreed to grant planning permission subject to the undernoted conditions and reasons:- 1. That the development to which this permission relates must be begun within three years from the date of this permission. Reason: In accordance with Section 58 of the Town and Country Planning (Scotland) Act 1997. 2. The development shall be implemented in accordance with the details specified on the application form dated 26 th October 2009 and the approved drawing reference numbers: 5000004826-WW-DRA-04009010, 5000004826-WW-DRA-04009011, unless the prior written approval of the planning authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 3. The temporary use of the land/construction site shall only be used by Scottish Water and/ or their contractors in direct association with the construction of a Wastewater Treatment Works at Bullwood Quarry and/or any associated pipe laying/maintenance and repair or other works within the environs of Dunoon (West Bay) which constitute ‘ permitted development’ under the Town and Country Planning (General Permitted Development) (Scotland) Order 1992. This temporary permission shall cease on or before 31 July 2011 and thereafter the land shall be restored to its original condition no later than 31 August 2011, unless any extended period is agreed in advance in writing by the Planning Authority. Reason : This permission is sought for temporary use only and to ensure appropriate reinstatement following the cessation of the temporary use . 4. Notwithstanding the submitted information, no vehicle movements (and starting of engines), no use of any plant and no cleaning or maintenance of plant, vehicles or machinery shall take place outwith the hours of 0730 to 1800 Monday to Friday and 0730 to 1300 on Saturdays or at any time on Sundays or Bank Holidays, except as otherwise agreed in writing with the Planning Authority in conjunction with Public Protection. Reason: To protect the amenity of local residents from undue noise and disturbance from vehicles leaving the site. 5. The visibility splays (42.0 metres in each direction from a 2.4 metre setback) onto Kilbride Road from the car park shall be maintained clear of any obstruction in excess of 1.0m in height for the duration of the occupation of the compound. Reason : In the interests of highway safety. 6. A temporary security boundary fence (‘ heras ’ or equivalent) shall be retained around the perimeter of the compound for the duration of the temporary use. No temporary fencing or other materials shall be placed on the grassed area surrounding the site. Reason : In the interests of public safety and visual amenity. 7. Any lighting units shall be operated, positioned and angled to prevent any glare or light spillage outwith the boundary of the site, having regard to the Institute of Lighting Engineers Guidance. Reason : In the interest of residential amenity. 8. No vehicles, plant, equipment or construction materials used by Scottish Water and/or their contractors shall at any time be positioned or parked outwith the site edged red. Reason : To ensure that adequate car parking is available for visiting members of the public and in the interest of highway/parking safety and to prevent a conflict between the competing uses.
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development Services

Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________

Reference No: 09/01535/PP

Planning Hierarchy: Local application.

Applicant: Scottish Water

Proposal: Erection of temporary construction compound for use as offices and welfare facilities (for a maximum period of 18 months).

Site Address: Glenmorag Car Park, Kilbride Road, Dunoon ____________________________________________________________________________

DECISION ROUTE

(i) Local Government (Scotland) Act 1973

____________________________________________________________________________

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission

Formation of temporary site compound (five single-storey portacabins and five two- storey portacabins to provide office, canteen, stores, toilets and generator); Erection of temporary security fencing.

(ii) Other specified operations

Connection to public water main; Connection to public sewer. ____________________________________________________________________________

(B) RECOMMENDATION:

It is recommended that Planning Permission be granted subject to the conditions reasons and advisory notes set out below. ___________________________________________________________________________

(C) HISTORY:

A planning application (ref. 04/01679/COU) for the formation of a temporary construction site compound and siting of 10 portacabins at two-storey level was placed before the Area Committee on 5th October 2004, but withdrawn prior to determination.

A planning application (ref. 04/01121/COU) for the formation of a temporary construction site compound and siting of 10 portacabins at two-storey level was withdrawn on 19th August 2004. Planning permission (ref. 04/02020/COU) was granted on 25th November 2004 for the formation of temporary construction site compound (2nd Amended Site) and the siting of portacabins at two-storey level. A non-material amendment application (ref. 05/01792/NMA) was granted on 4th October 2005 for the siting of additional portacabins. Both 04/02020/COU and 05/01792/NMA were implemented with all works ceasing during summer 2006.

Planning permission (ref. 06/02357/COU) for the formation of temporary site compound and the siting of 4 two-storey portacabins was granted on 11th January 2007. This temporary permission expired on 30th June 2007.

A related application for the erection of a Waste Water Treatment Works within Bullwood Quarry (ref. 05/02439/DET) was refused by the Area Committee on 11th October 2006 but allowed on appeal and permission granted on 15 April 2008. A revised application (08/02245/DET) was approved on 7 April 2009.

____________________________________________________________________________

(D) CONSULTATIONS:

Area Roads Manager (response dated 3rd December 2009): No objections subject to conditions regarding sightlines, access, wheelwashing facilities, surface water drainage and advisory note regarding Road Opening Permit. Scottish Water (expiry date 22nd December 2009): Views awaited. Public Protection: No response to date ____________________________________________________________________________

(E) PUBLICITY:

Regulation 20(1) Advert published 11 December 2009 (expiry date 1 January 2010). ____________________________________________________________________________

(F) REPRESENTATIONS:

No letters of representation have been received. ____________________________________________________________________________

(G) SUPPORTING INFORMATION

Has the application been the subject of:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
01535 location planPlan 434 KB Download
PDF
09/01535/PP: APPLICATION FOR ERECTION OF TEMPORARY CONSTRUCTION COMPOUND FOR USE AS OFFICES AND WELFARE FACILITIES (FOR A MAXIMUM PERIOD OF 18 MONTHS): GLENMORAG CAR PARK, KILBRIDE ROAD, DUNOON: SCOTTISH WATERReport 130 KB DownloadRead as text

At this meeting

Whole meeting
2MINUTESOn the agenda 3TAXI FARE SCALE REVIEW: CIVIC GOVERNMENT (SCOTLAND) ACT 1982Agreed 409/01372/PP: APPLICATION FOR ALTERATIONS AND EXTENSION TO DWELLINGHOUSE: ARISAIG, CRANNAIG A'MHINISTEIR, OBAN: MR & MRS DJ MACDONALDAgreed 509/01443/PP: APPLICATION FOR ERECTION OF 5 DWELLINGHOUSES, STABLES AND INSTALLATION OF PRIVATE SEWAGE SYSTEM: LAND AT JUNCTION OF B833 PORTKIL ROAD, PORTKIL, BY KILCREGGAN: MRS A J MACCONOCHIEAgreed 609/01497/PP: APPLICATION FOR CHANGE OF USE OF LAND TO OUTDOOR LEARNING AREA FOR USE BY PUPILS OF HERMITAGE PRIMARY SCHOOL AND PARKLANDS SPECIAL SCHOOL AND ERECTION OF PERIMETER FENCING: LAND TO THE REAR OF HERMITAGE PRIMARY, 11 EAST ARGYLE STREET, HELENSBURGH: ARGYLL AND BUTE COUNCILAgreed 709/01515/PP: APPLICATION FOR REMOVAL OF REMOTE CLASSROOM, DEMOLITION OF REAR EXTERNAL ACCESS STAIR AND ERECTION OF SINGLE STOREY FRONT EXTENSION AND REPLACEMENT REAR ACCESS STAIR: NORTH BUTE PRIMARY SCHOOL, PORT BANNATYNE, ISLE OF BUTE: ARGYLL AND BUTE COUNCILAgreed
809/01535/PP: APPLICATION FOR ERECTION OF TEMPORARY CONSTRUCTION COMPOUND FOR USE AS OFFICES AND WELFARE FACILITIES (FOR A MAXIMUM PERIOD OF 18 MONTHS): GLENMORAG CAR PARK, KILBRIDE ROAD, DUNOON: SCOTTISH WATERThis decision
909/01568/PP: APPLICATION FOR SINGLE STOREY EXTENSION TO SCHOOL: BOWMORE PRIMARY SCHOOL, FLORA STREET, BOWMORE, ISLAY OF ISLAY: ARGYLL AND BUTE COUNCILAgreed 1009/01576/PP: APPLICATION FOR ERECTION OF 500 TONNE SALT BARN: UNIT 2, CNOC NA SGILLEN, TOBERMORY, ISLE OF MULL: ARGYLL AND BUTE COUNCILAgreed 1109/01581/PP: APPLICATION FOR ERECTION OF 1000 TONNE SALT BARN: LAND OPPOSITE PENNYGOWN QUARRY, GLENFORSA, AROS, ISLE OF MULL: ARGYLL AND BUTE COUNCILAgreed 1209/01626/PP: APPLICATION FOR ERECTION OF A BIRD VIEWING HIDE AND FORMATION OF ACCESS PATH: BIRD VIEWING HIDE, BROXWOOD, SANDBANK, ARGYLL: SANDBANK COMMUNITY DEVELOPMENT TRUSTAgreed 1309/01628/PP: APPLICATION FOR INSTALLATION OF BIOMASS BOILER AND FORMATION OF TIMBER BOARDED ENCLOSURE: STRACHUR MEMORIAL HALL, FREE CHURCH ROAD, STRACHUR: STRACHUR MEMORIAL HALL COMMITTEEAgreed 1409/01702/PP: APPLICATION FOR FORMATION OF NEW CAR PARK: LAND TO THE NORTH OF UNITED CHURCH OF BUTE, HIGH STREET, ROTHESAY, ISLE OF BUTE: UNITED CHURCH OF BUTEAgreed 1509/01723/PP: APPLICATION FOR RENEWAL OF PLANNING PERMISSION (O5/00580/NID) FOR THE RETENTION OF EXTERNAL STORAGE CONTAINER: KIRKMICHAEL COMMUNITY CENTRE, TOWNHEAD ROAD, HELENSBURGH:ARGYLL AND BUTE COUNCILAgreed 1609/01807/PP: APPLICATION FOR INFILLING OF FORMER PADDLING POOL TO FORM RECREATIONAL GROUND: FORMER PADDLING POOL, BULLWOOD ROAD, DUNOON: SCOTTISH WATERAgreed

Who was there

12 of 15 attended
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
VD
Councillor Vivien DanceMember, apologies
MD
Councillor Mary-Jean DevonMember, present
DK
Councillor Daniel KellyMember, present
DK
Councillor Donald KellyMember, apologies
DK
Councillor David KinniburghMember, apologies
NM
Councillor Neil MackayMember, present
DM
Councillor Donald MacMillan BEMMember, present
BM
Councillor Bruce MarshallMember, present
AM
Councillor Alister McAlisterMember, present
RM
Councillor Roderick McCuishMember, present

All 15 on the meeting page

On this subject at Argyll and Bute

Search all
  1. 09/01535/PP: APPLICATION FOR ERECTION OF TEMPORARY CONSTRUCTION COMPOUND FOR USE AS OFFICES AND WELFARE FACILITIES (FOR A MAXIMUM PERIOD OF 18 MONTHS): GLENMORAG CAR PARK, KILBRIDE ROAD, DUNOON: SCOTTISH WATERThis decision
  2. Ministry of defence c/o defence infrastructure organisation (dio): proposal of application notice for the erection of 639 single accommodation units (slu) for military personnel with associated service access road and engineering/infrastrucNoted
  3. Tsl contractors ltd: detailed planning application for the erection of residential development comprising 97 residential units and a commercial unit (class 1) with all associated external works and landscaping: land north west of isle of mull hotel, craignure, isle of mull (ref: 22/01418/pp)Agreed
  4. Auch estate: proposal of application notice for demolition of existing lodge and farm buildings, erection of new replacement guest lodge and new guest steading accommodation, walled garden, ancillary buildings, landscape, access (main roadNoted
  5. Scottish hydro electric transmission plc: proposal of application notice for the erection of electricity substation comprising platform area, control building, associated plant and infrastructure, ancillary facilities, access track(s), laydNoted
  6. Taylor wimpey uk ltd and helensburgh golf club: proposal of application notice for residential development, including affordable housing, demolition of existing clubhouse and erection of new clubhouse, revision of new and retained golf holeNoted

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies