ROAD ISSUES AND A83 - KENNACRAIG TO CAMPBELTOWN - ROAD CONDITION
AgreedCommittee2 papers
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 7 April 2010. Below is the council's own wording, with the papers it was decided on.
Agreed to request the Executive to examine the road assessment procedure undertaken by the Executive Director of Development and Infrastructure as the current assessment does not reflect the Mid Argyll, Kintyre and the Islands Area Plan priorities for the A83. Agreed to continue consideration of this report to the Special Meeting Area on the 5 th May 2010 in light of the Executive decision on the roads assessment procedure. Noted that a representative from Scottish Water would be attending the next Business Day on 5 th May. Agreed that the Contracts Manager provide the Committee and update on the existing funding rationale. (Ref: Reports by Stewart Clark, Contracts Manager dated 7 April 2010, submitted). Councillor Colville having declared an interest in the following item, left the room and took no part in the decision.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1This report provides an update on outstanding roads-related issues in Mid Argyll, Kintyre & Islay.
Recommendations
2.1It is recommended that Members note this report.
3. DETAIL
3.1Along with many other roads across Argyll & Bute, the A83 has suffered considerable damage as a result of the severe frosts experienced this winter.
3.2The attached report, in Appendix A, identifies 5 locations on the A83, between Kennacraig and Campbeltown, which are considered to be showing the worst signs of deterioration.
3.3Significant expenditure is required in at least three of the locations identified in the report. Once works have been carried out under the auspices of the ‘frost damage budget’ and next year’s capital budget, it is likely that several hundred thousand pounds of funding will still be required to fully reinstate the carriageway at the locations highlighted.
3.4The report is not exhaustive; there are numerous areas requiring remedial works, however, as mentioned previously, the report concentrates solely on the worst sections. Where funding is not forthcoming, the road will continue to be maintained in a safe condition using the roads maintenance revenue budget.
4. Policy: The road network will be maintained in line with the ‘Road Maintenance & Asset Management Plan’ as closely as the available roads maintenance budget will allow.
5. Financial: Expenditure of revenue and capital budget to maintain the network.
6. Personnel: Nil
1 For further information, please contact:
Stewart Clark, Contracts Manager - West Argyll (Tel: 01546 604893)
Graham Brown Operations Manager 7th April 2010
2 APPENDIX A
3 A83 Campbeltown Road – Kennacraig to Campbeltown 5 March 2010 Report on Sites Requiring Treatment
Introduction This report has been produced at the behest of Councillor John Semple. Those sections of the A83 Campbeltown Road showing major signs of deterioration have been assessed and the likely cost for suitable treatment has been identified for each site. The sections considered are as follows:- • North of Clachan • North of Tayinloan • Glenbarr • Bellochantuy • North of Campbeltown
It should be noted that there are numerous sections of the A83 requiring remedial works, however, the five sections identified are considered to be those showing the worst signs of deterioration.
A83 North of Clachan This section lies mainly to the north of Clachan.
A83 North of Clachan
• The existing carriageway surface at this location comprises of old surface dressing over an oxidised bituminous surface. This surface is both potholing & wearing through to the lower layer. This deterioration will continue if left untreated.
• A 280m long critical section will be resurfaced from the ‘frost-heave budget’ this financial year – highlighted in red on the attached plan in Appendix A. This is approximately 10% of the overall area requiring treatment; the budget for this work is £25,000. The most critical section to be treated lies on the hill north of Clachan. Gradients and bends on this section increases stress on the surface and this has
4 accelerated surface deterioration. The area of proposed overlay cannot be patched as a permanent solution as the surface is too weak to tie into.
• The remaining 2,900m long section which requires treatment is highlighted in yellow on the plan in Appendix A.
• The remainder of the hill will be reassessed for inclusion in the 2010/11 capital programme. Approximate costs are expected to be in the region of £80,000
• The level sections to the north & south of Clachan hill are unlikely to be included in the 2010/11capital programme without excluding a large proportion of the proposals for the remaining network. Approximate costs are expected to be in the region of £180,000
A83 North of Tayinloan This section has several drainage issues in addition to the poor surface condition.
A83 North of Tayinloan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.