Decision Members agreed:- 1. To note the report. 2. That the Roads Performance Manager would review the road issues which had been raised by Members and provide timely updates. (Reference: Report by Executive Director – Development and Infrastructure Services, dated 29 April 2016, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to advise Members of the roads revenue budget position at the end of the 3rd Quarter of financial year 2015/16.
1.22015/16 Budget - The overall roads maintenance budget for the 2015/16 year (excluding winter maintenance and coastal protection) is £3,912,226. The roads maintenance budget for the 2015/16 year (excluding winter maintenance, coastal protection and centrally allocated budgets) for the Helensburgh and Lomond area, is £617,904, of which, £293,303 has been spent at the end of the 3rd Quarter – or 47%.
1 ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 29 APRIL 2016
2.1This report follows-on from the report presented earlier in the year at the December Area Committee, which provided information on road maintenance revenue activities being delivered in Q2 2015/16
Recommendations
3.1That the Committee notes this report.
4.0DETAILS
4.1The Roads Operations Budget is proposed in line with the Roads Maintenance and Management Strategy and the Roads Maintenance and Asset Management Plan (RAMP). The available revenue budget is currently insufficient to allow all of the required works to be fully undertaken.
4.2Roads revenue expenditure is closely monitored by separating types of work into different ‘activities’. This report is based solely upon financial information which has been collated through the ‘Total’ costing system. Budgetary figures provided in the Appendices to this report represent spends to the end of Q3 for the present financial year. Winter maintenance and coastal protection costs have been excluded from this report.
4.3There is still some external funding to spent in Helensburgh and Lomond – the SPT Clycle Way £200,000 Value – Current update: Works are nearing completion on Station Road- Ferry Road section. A bridge supplier has now been appointed for new footbridge and this will be constructed in-situ. Ferry Road is to be resurfaced as accommodation works. The temporary access road will be removed from Burns Parks on completion of the works. Street furniture will be installed following discussions with Elected Members, CC and Police Scotland.
4.5Carriageway reconstruction works have been taking place with Resurfacing works now complete on Glen Luss Road and the Glen Douglas Road. Selective patching works have been carried out on A814 Cats Castle (Dumbarton Boundary section).
4.6Footway Reconstruction works have also been carried out and we are currently completing resurfacing works on Kilmahew Avenue, Cardross.
2 4.7 We have outstanding footway works at various locations which will now be completed early in the new financial year: East Clyde Street at Farmfoods (currently delayed because of dangerous building at this locus). East Princes Street at Helensburgh Station and at Sinclair Street from Victoria Road to Pump House.
4.8Further quarterly reports will continue to be presented to Members at future Area Committees.
4.9Appendix 1 shows the overall roads revenue maintenance budget for 2015 to 2016 for each area. The overall roads maintenance budget for the 2015/16 year (excluding winter maintenance and coastal protection) was £3,912,226 as indicated in the table.
5.0Appendix 2 provides information on percentage spend at the end of Q3 for 2015/16 for each area
5.1Appendix 3 shows spend at the end of Q3 for all activities in the Helensburgh and Lomond area this financial year 2015/16.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.