REVIEW OF CONTRACT MANAGEMENT

Noted Executive 3 papers

Executive noted this item on Thursday 15 April 2010. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Decision Noted the contents of the Executive Director’s report and agreed to advise the Audit Committee of the action being taken to address the requirements of the Action Plan. (Reference: Extract from Minutes of Audit Committee 5 March 2010, Report by Internal Audit Manager dated February 2010 and Report by Executive Director – Customer Services dated 7 April 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Executive

Summary

1.1This paper outlines the steps that are being taken to address the requirements of the Action Plan outlined within Appendix 2 of the Internal Audit Report on the Review of Contract Management.

Recommendation

2.1Members are asked to note the action that is being taken.

3. DETAIL

3.1Background: The February 2010 Internal Audit Report on the Review of Contract Management outlines 4 key actions for improvement. This paper briefly confirms the steps that are being taken to address these.

3.2Actions required: Firstly, with respect to Initial Business Cases, I can confirm that the template will be amended to incorporate a benchmarking sheet. Also, when seeking permission to move forward from an Initial Business Case to undertake an Outline Business Case, a clear indication of the costs involved will be provided for Members’ consideration. Steps will also be taken over the next few months to ensure that Members receive appropriate training on their role in approving business cases at each gateway within the Capital Planning Process. Members are also asked to note that Internal Audit have taken steps to include a review of capital projects within this year’s Audit Plan.

4. CONCLUSION

4.1The Internal Audit Report on the Review of Contract Management is due to be considered in detail at the next meeting of the Asset Management Board which is scheduled to take place on 4 May 2010. This will enable further consideration of the arrangements that are being put in place to ensure full compliance with the Action Plan. 5. IMPLICATIONS

Policy: The actions that are being addressed will ensure compliance with the Council’s Best Value obligations as they relate to Asset Management.

Finance: The full financial implications will be outlined when seeking permission to move forward with the development of Outline Business Cases.

Personnel: Nil.

Legal: Nil.

Equal Opportunities: Nil.

Director of Customer Services

7 April 2010

For further information please contact:

Malcolm MacFadyen Head of Facility Services

Tel: 01546 604412 E-mail: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive 15 4 10 Review of Contract ManagementReport 65 KB DownloadRead as text
PDF
REVIEW OF CONTRACT MANAGEMENTReport 39 KB Download
PDF
Review of Contract Management, 05/03/2010 Audit Committee, 06/04/2010 Pre-Agenda Briefing of the ExecutiveAgenda 108 KB Download

At this meeting

Whole meeting

Who was there

15 of 21 attended
MA
Maureen ArthurMember, absent
JB
Jane BrownMember, apologies
RC
Councillor Robin CurrieMember, present
WD
William DalbyMember, present
VD
Councillor Vivien DanceMember, present
GF
Councillor George FreemanMember, present
AH
Councillor Alison HayMember, present
DM
Councillor Donald MacdonaldMember, present
DM
Councillor Duncan MacIntyreMember, present
RM
Councillor Robert MacintyreMember, present
DM
Councillor Donald MacMillan BEMMember, present
DM
David McEwanMember, apologies

All 21 on the meeting page

On this subject at Argyll and Bute

Search all
  1. REVIEW OF CONTRACT MANAGEMENTThis decision
  2. Waste management ppp - contract reviewNoted

More from Argyll and Bute Executive

All decisions
MeetingDecisionOutcome
19 Apr 2012 Leader's reportDecision Noted the report. (Reference: Report by Leader of the Council dated April 2012, submitted) Noted Open
19 Apr 2012 EnvironmentDecision Noted the report. (Reference: Report by Spokesperson for Environment dated April 2012, submitted) Noted Open
19 Apr 2012 European affairsDecision Noted the report. (Reference: Report by Spokesperson for European Issues dated April 2012, submitted) Noted Open
19 Apr 2012 Social affairsDecision 1. Noted the report; and 2. Agreed that adoption of the Learning Disability Service Users Conference should ... Noted Open
19 Apr 2012 Education capital programme 2012/13 to 2014/15Decision Approved the proposed projects to invest the additional capital allocation of £2.126m in asset sustainabilit... Approved Open