CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Feb9Thursday

Helensburgh CHORD Project Board

Argyll and ButeHeldPapers from www.argyll-bute.gov.uk
Thursday 9 February 2012, 4.00pmHeld 5399 days ago.
Ceremonies RoomHelensburgh. Open to the public.
6 items, 5 papersAbout 2.4 MB, led by Highlight/Progress Report.
No exempt items listedEvery item is due to be heard in public.
This meeting was held9 February 2012
6items
5papers
3decisions
–exempt
Running order, sized by papersItem 1 to 6
ReportsProcedureExempt parts

The agenda, item by item

What the committee will consider, in order, with every paper attached to its item. Highlight/Progress Report is the main business.

1
Procedure

Apologies

2
Procedure

Declarations of Interest

4
ReportMain business

Highlight/Progress Report

Decision: Decision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, dated 1 February 2012, submitted) Decision page

2 papers, 1.5 MBSearch inside with Pro
AppendixAppendix A: A242S-097-101-Phasing 1110251.4 MBDownload
ReportHighlight/Progress Report80 KBDownload
5
Report

Helensburgh Chord Risk Register

Decision: Decision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Febrary 2012, submitted) Decision page

1 paper, 771 KBSearch inside with Pro
ReportHelensburgh Chord Risk Register771 KBDownload
6
Report

Project Plan

Decision: Decision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at the completion of each phase of works. Agreed that regular updates on progress will continue to be provided by the CHORD Project Manager, to the Helensburgh and Lomond Area Committee. The Local Area Community Planning Group will also be updated at regular intervals. Decision page

ReportProject Plan21 KBDownload
Read inside all 5 papersPro opens every page, searches every appendix, and keeps the papers if the council removes them.

The main business: Highlight/Progress Report

Item 4 is where most of this meeting's papers sit: 2 papers, about 1.5 MB.

Item 4

Highlight/Progress Report

What is in the pack2 papers, about 1.5 MB
Appendix A
A242S-097-101-Phasing 111025Supporting paper
1.4 MB
Report
Highlight/Progress ReportThe report to the committee
80 KB
Read and search every page of this itemPro opens all 2 papers, and keeps them if the council removes them.

How this item got here

This committee has dealt with the subject before.

23 March 2010Highlight/Progress Report HH02- Rejuvenating the West Bay Esplanade
23 March 2010Highlight/Progress Report HH01 - Town Centre Management and Streetscape Improvements
5 April 2011HIGHLIGHT PROGRESS REPORT
9 February 2012Highlight/Progress ReportThis meeting.

Every paper for this meeting

All 5 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.

PaperSizeOur copy
Minute of Meeting 27 July 2011Item 3, Minute of Meeting 27 July 2011
52 KB
Kept 5 Oct
A242S-097-101-Phasing 111025Appendix A, item 4, Highlight/Progress Report
1.4 MB
Kept 5 Oct
Highlight/Progress ReportItem 4, Highlight/Progress Report
80 KB
Kept 5 Oct
Helensburgh Chord Risk RegisterItem 5, Helensburgh Chord Risk Register
771 KB
Kept 5 Oct
Project PlanItem 6, Project Plan
21 KB
Kept 5 Oct

Last time, and what carried over

The committee last met on 5 April 2011. 4 of its items lead into this meeting. Point at any item to follow a thread. Procedural items are left out.

Apr5
5 April 201111 items, 6 papers
Held
carried over
Feb9
9 February 20126 items, 5 papers
Held
3
MINUTE OF MEETING 11 NOVEMBER 2010
4
HIGHLIGHT PROGRESS REPORT
5
HELENSBURGH CHORD RISK REGISTER
6
PROJECT PLAN
7
COMMUNICATION PLAN POST DETAILED DESIGN STAGE D - JANUARY 2011 - Dec 11
8
HELENSBURGH EIA EXECUTIVE SUMMARY
3
Minute of Meeting 27 July 2011
4
Highlight/Progress Report
5
Helensburgh Chord Risk Register
6
Project Plan

The threads

  • MINUTE OF MEETING 11 NOVEMBER 2010 leads to item 3, Minute of Meeting 27 July 2011
  • HIGHLIGHT PROGRESS REPORT leads to item 4, Highlight/Progress Report
  • HELENSBURGH CHORD RISK REGISTER leads to item 5, Helensburgh Chord Risk Register
  • PROJECT PLAN leads to item 6, Project Plan

Not carried over

COMMUNICATION PLAN POST DETAILED DESIGN STAGE D - JANUARY 2011 - Dec 11, HELENSBURGH EIA EXECUTIVE SUMMARY do not return this time.

See the 5 April meeting

This committee over time

Every Helensburgh CHORD Project Board meeting we have read, the dates it has set for the future, and each time those dates have changed.

4 meetings, 2010 to 2012Dot size shows the number of papers
201020112012
HeldThis meeting
MeetingItemsPapers
25 Apr 2012Wednesday
8items
0papers
HeldOpen
9 Feb 2012Thursday, this meeting
6items
5papers
5 Apr 2011Tuesday
11items
6papers
HeldOpen
23 Mar 2010Tuesday
8items
10papers
HeldOpen

Follow the Helensburgh CHORD Project Board

Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.

What should we tell you?

Argyll and Bute, Helensburgh CHORD Project Board

Helensburgh CHORD Project Board: 3 kinds of updateArgyll and Bute, sent the same day
PDF
5 papers published for 9 FebruaryHighlight/Progress Report and 4 more papers
DAT
Meeting dates updatedAny date added, moved or dropped
DEC
Decisions from 9 FebruaryThe committee's resolutions, the day they are recorded
ABC
"highlight" found in 1 paperHighlight/Progress Report
Each update links to the paper and the council's own copy
Free: one weekly alert. Pro: every option, the same day. Pro Plus: straight into your own systems.

Free

One alert, sent weekly, on titles and decisions.

£0for good
  • 1 alert, weekly summary
  • Titles and decisions
  • Link to every official paper
Save this alert free
Most chosen

Pro

Unlimited alerts the same day, searching every page.

£99per user a month
  • Unlimited alerts, same day
  • Matches inside every page and appendix
  • Every council, not just this one

Pro Plus

Your team, with every match pushed into your own tools.

£449a month, 3 users included
  • Everything in Pro, for 3 users
  • Alerts as webhooks into Slack or a CRM
  • API key and bulk export of this council

Data licence

Every council's records in your own products and research.

£12,000a year, from
  • Unlimited API and full archive delivery
  • Rights to use the data in your products
  • Back to 2000, every council
Talk to us

Never miss what this committee decides

Papers, decisions and date changes for the Helensburgh CHORD Project Board, and every other committee you follow, the day they appear.

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies