Helensburgh CHORD Project Board noted this item on Thursday 9 February 2012. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Febrary 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh CHORD Project Board
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Helensburgh Chord Risk RegisterReport 771 KB Download

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. Helensburgh Chord Risk RegisterThis decision
  2. Chord-helensburgh: surplus funds, comet plinthNoted
  3. Helensburgh chord - artwork progress reportAgreed
  4. Helensburgh CHORD Public Realm Improvements - Progress UpdateNoted
  5. Helensburgh CHORD Risk RegisterAgreed
  6. Helensburgh CHORD - Update on flooding at Wee Kelpie, West Clyde StreetAgreed

More from Argyll and Bute Helensburgh CHORD Project Board

All decisions
MeetingDecisionOutcome
9 Feb 2012 Highlight/Progress ReportDecision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, da... Noted Open
9 Feb 2012 Project PlanDecision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at th... Agreed Open
5 Apr 2011 Highlight progress reportDecision To note the update on the progress of the Highlight/Progress Report. Noted Open
5 Apr 2011 Helensburgh chord risk registerDecision To note the update on the progress of the Risk Register. Noted Open
5 Apr 2011 Project planDecision Noted the update on the progress of the Project Plan. Agreed to ascertain procedure to be followed in the ev... Noted Open