CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Helensburgh CHORD Project Board, Thursday 9 February 2012 at 4.00pm

Highlight/Progress Report

Noted Committee 2 papers

Helensburgh CHORD Project Board noted this item on Thursday 9 February 2012. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

Decision Noted the update on the progress of the Highlight/Progress Report. (Ref: Report by CHORD Project Manager, dated 1 February 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh CHORD Project Board

HIGHLIGHT / PROGRESS REPORT Transforming the Town Centre – Traffic Management & Streetscape PROJECT Project Improvements and Improvements & Redevelopment of the West Bay Helen Ford NAME: Manager: Esplanade Reporting Period: 28/7/2011 – 9/2/2012 Date report prepared: 1 February 2012 Appointment of Contractor/ Project stage: Project stage completion date: 3/5/2013 Implementation of works

Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater

Progress – Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery (including those completed ahead of schedule) (including brief explanation of why product delivery period date outstanding) date Programme Board and Executive sign Submission of HLF Stage 2 3/2/12 Contract Award 17/2/12 off FBC, August and September 2011 application, delay mainly due to respectively obtaining required letters of support from community. Application will be submitted by the 3 February 2012 Phasing Programme – See Appendix A

Issue of PQQ and Tender Documents Mobilisation 13/2/12 – 9/3/12 9/3/12

Implementation of TRO process for Construction - 12/3/12 – 3/5/13 TBC signalised pedestrian crossing at West Progress report King St Implementation of Temporary TRO for CHORD works

Transport Scotland approval of Tourist signage (brown sign)

Risk Ref. Risk Current status Previous Revised RAG status RAG status See Appendix B. Register will be updated in discussion with appointed contractor.

Budget Management – Total budget available to complete this stage:£6,660,000 Forecast expenditure to conclusion of FBC Actual Expenditure (as reported at end of Variance if Required December 2011) HH01 £297379 HH02 £298,253 Total £595,632 £409,096 See note 1 below

Any further information 1. Projected forecast expenditure to project completion. Forecast based on current project plan. The Helensburgh CHORD project has been allocated £6,660,000. To date, £409,096 has been spent. The balance remaining is £6,250,904. The current forecast is that the monies will be drawn down as follows:

July 2011 – March 2012 £95,293 April 2012 – March 2013 £5,366,289 April 2012 – May 2013 £700,875 May 2014 release of retention £ 88,447 Total £6,250,904 2. Overall Budget Position On finalisation of the tender report for the contract works, the overall budget position will be reviewed and reported to the Project Board along with recommendations (in line with section 4.6 of the FBC) on where any cost savings should be allocated.

3. Community Engagement

The following meetings/events have taken place since the last reporting period:

6/9/11 – Chamber of Commerce – Phasing meeting 1/12/11 - Q/A with Contractors, presentation by Employability Team 14/12/11 – Meeting with community representatives re HLF application

Since the last Project Board meeting several press releases were issued in response to negative coverage of CHORD project, presentation boards erected in the Square and the Esplanade and the web page updated bi-monthly.

Communication Plan – Implementation stage Following appointment of preferred contractor, project communication plan will be updated to reflect contractor’s community engagement plans and circulated to Board.

A press release will be issued on appointment of the preferred contractor, along with an update on the HLF Stage 2 application, approval of Tourist signage and on how the community will be kept informed during the implementation of the works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A242S-097-101-Phasing 111025Appendix A 1.4 MB Download
PDF
Highlight/Progress ReportReport 80 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Argyll and Bute

Search all
  1. Highlight/Progress ReportThis decision
  2. Highlight/progress reportNoted
  3. Rothesay Pavilion - Highlight/Progress ReportNoted
  4. Rothesay THI - Highlight/Progress ReportNoted
  5. Campbeltown berthing facility - highlight / progress report (agenda item 6)Agreed
  6. Chord programme update - highlight / progress reportNoted

More from Argyll and Bute Helensburgh CHORD Project Board

All decisions
MeetingDecisionOutcome
9 Feb 2012 Helensburgh Chord Risk RegisterDecision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Fe... Noted Open
9 Feb 2012 Project PlanDecision Agreed to note the update by the CHORD Design Team. Agreed that updates will be provided, to the Board at th... Agreed Open
5 Apr 2011 Highlight progress reportDecision To note the update on the progress of the Highlight/Progress Report. Noted Open
5 Apr 2011 Helensburgh chord risk registerDecision To note the update on the progress of the Risk Register. Noted Open
5 Apr 2011 Project planDecision Noted the update on the progress of the Project Plan. Agreed to ascertain procedure to be followed in the ev... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies