MR JOSEPH READE: REMOVAL OF SECTION 75 RELATIVE TO PLANNING PERMISSION 98/01377/REM AND 99/00886/VARCON: LEPHAIN, TOBERMORY, ISLE OF MULL (REF: 12/00053/PP)
AgreedPlanning2 papers
Planning, Protective Services and Licensing Committee agreed this item on Wednesday 21 March 2012. Below is the council's own wording, with the papers it was decided on.
Decision Agreed that the Section 75 Agreement be amended to provide:- “The occupation of the dwellinghouse to which planning permission relates, shall be limited to a person(s) employed, or last employed in the management and/or operation of the Island Bakery, Lephain, Tobermory, Isle of Mull. In the event that any person, company or organisation; in whose favour the owner of the land on which the dwellinghouse is built grants a Standard Security over that said land; exercises a power of sale in terms of the said Standard Security by reason of the granters [applicants] being in default, then this Section 75 Legal Agreement shall cease to apply”. (Reference: Report by Head of Planning and Regulatory Services dated 6 March 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Development and Infrastructure
Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________
Reference No: 12/00053/PP
Planning Hierarchy: Local Development
Applicant: [name removed]: Removal of Section 75 Agreement Relative to Planning Permission 98/01377/REM & 99/00886/VARCON
Site Address: Ceilte, Dervaig Road, Tobermory, Isle of Mull ____________________________________________________________________________
DECISION ROUTE
(i) Local Government Scotland Act 1973 ____________________________________________________________________________
(A) DETAILS OF APPLICATION:
This application seeks permission to amend a Section 75 Agreement, (reference ED/CN/9949 S75) linked to planning permission 98/01377/REM & 99/00886/VARCON which restricts the occupation of the dwellinghouse to a person(s) employed or last employed in the management and/or operation of the Island Bakery, Lephain, Tobermory, Isle of Mull and their dependent(s) or the widow(er) of such a person in all time coming and in accordance with the conditions laid down in Planning Permission 98/01377/REM. ____________________________________________________________________________
(B) BACKGROUND
Outline planning permission and reserved matters (reference 97/01758/OUT and 98/01377/REM) were approved by Members on 9 July 1998 and 9 November 1998 for erection of a dwellinghouse at the site.
The applicant owns and manages the Island Bakery which has its premises at Lephain, Tobermory, Isle of Mull. Members of the Committee considered that it was essential that the applicant be able to live in close proximity to the bakery, but due to the site being in an area where a new dwellinghouse would not normally be supported on policy grounds, imposed the following condition on the planning permission.
“The occupation of the proposed dwellinghouse shall be restricted to a person(s) employed, or last employed in the management and/or operation of the Island Bakery, Lephain, Tobermory, Isle of Mull and their dependant(s) or the widow(er) or such a person.” A subsequent application reference 99/00886/VARCON was submitted which sought to have the above condition transferred to a Section 75 Agreement which would similarly restrict the occupation of the dwellinghouse to a person employed in the bakery. The reason for the request being that the applicant’s bank was unwilling to lend money for the house owing to the fact that, unlike a Section 75 Agreement, there is no possibility of the bank repossessing the house without restriction.
The principle of transferring the occupancy restriction from condition to a Section 75 Agreement was considered acceptable and was approved by Members on 14 July 1999 with the Section 75 Agreement being concluded on 29 July 1999. ______________________________________________________________________
(C) REQUEST FOR REMOVAL OF AGREEMENT:
The applicant has stated that during the process of re-mortgaging the dwellinghouse with a new lender, the legal agreement was noted which prevented him from moving his mortgage. Accordingly, this application seeks to have the Section 75 Agreement amended to allow any mortgage lender to sell the property on the open market in the event of re-possession.
Such an amendment to the Section 75 Agreement would allow the owner of the land to exercise a power of sale in terms of the standard security by reason of the granters being in default but would still ensure that the occupancy of the dwellinghouse be limited as previously intended, in all other circumstances.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
MR JOSEPH READE: REMOVAL OF SECTION 75 RELATIVE TO PLANNING PERMISSION 98/01377/REM AND 99/00886/VARCON: LEPHAIN, TOBERMORY, ISLE OF MULL (REF: 12/00053/PP)Report
13MR JOSEPH READE: REMOVAL OF SECTION 75 RELATIVE TO PLANNING PERMISSION 98/01377/REM AND 99/00886/VARCON: LEPHAIN, TOBERMORY, ISLE OF MULL (REF: 12/00053/PP)This decision
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.