SIR ROBERT MCALPINE: ERECTION OF MIXED USED DEVELOPMENT: ARDYNE POINT, TOWARD (REF: 07/00952/OUT)
DecidedPlanning6 papers
Planning, Protective Services and Licensing Committee decided this item on Wednesday 21 March 2012. Below is the council's own wording, with the papers it was decided on.
Decision On there being an equality of votes the Chair gave his casting vote for the Motion and the Committee resolved accordingly. (Reference: Report by Head of Planning and Regulatory Services dated 31 August 2009, supplementary report no 1, supplementary report no 2 dated 7 March 2012, submitted and supplementary report no 3 dated 19 March 2012, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Planning, Protective Services and Licensing Committee
Argyll and Bute Council Development and Infrastructure Services
Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________
Reference No: 07/00952/OUT
Planning Hierarchy: Major Application
Applicant: Sir Robert McAlpine
Proposal: Erection of mixed use development comprising: Partial infill of existing southern basin, improvements to retaining walls and coastal protection measures and associated ground clearance/engineering infrastructure works. Erection of a 220 berth marina (Class 11) with associated land based facilities; hotel (Class 7)(up to 120 beds) with ancillary restaurant/public house; retail units (Class 1 store and craft shop); Class 4 office units (5,500 square metre); improvements to existing fish farm and complementary Class 5 industrial premises; ferry terminal comprising link span crossing and associated car parking/waiting areas; residential development (flats and houses up to 220 units); waste water treatment plant comprising septic tanks and outfall; improvements to existing vehicular access and new vehicular/pedestrian accesses, landscaping, SuDS scheme and car parking.
Site Address: Ardyne Point , Toward ____________________________________________________________________________
SUPPLEMENTARY REPORT 2
1. SUMMMARY
The purpose of this report is to advise Members of a proposed change to the terms of the section 75 agreement associated with the above proposal and to further clarify the proposed Heads of Terms of the section 75 agreement.
2. ASSESSMENT
Members will recall that it was agreed to approve this application on 21st October 2009 subject to a section 75 agreement requiring the following:
1. Improvements to the C10 Glen Striven Road between the limit of the A815 at Toward and the entrance to the site at the Memorial Hall, in order to secure, as far as topography allows, a minimum overall carriageway width of 6.0 metres. These works to be completed to adoption standard before construction works commence on the application site; 2. The formation of a footway to an adoptable standard between Toward Primary School and the entrance to the site at the Memorial Hall. These works are required to be completed before construction works commence on the application site; 3. Extension of the 40 mph speed restriction to a point beyond the entrance to the development. To be completed before the 50th house is occupied and / or the ferry terminal is operational.
The applicant has requested that the phasing of points 1 and 2 of the section 75 agreement noted above be amended to allow commencement following the development of 20 residential units on the site, or the completion of the ferry terminal whichever is sooner.
The applicant contends that this would be reasonable as these road improvements are only required for the residential / ferry element of the proposal. In addition, the Road Network Manager (email dated 8/7/11) has confirmed that there would be no objections to the adjusted timings for the legal agreement, however, it should be noted that a Roads Construction Consent and Road Bond would be required for the road serving the residential development where it departs from C10 Glenstriven Road toward Ardyne Harbour, this is on the line of the existing concrete access road. Any residential development of more than 5 units requires an access to adoptable standards as per policy LP TRAN 4.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Protective Services and Licensing Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.