SCOTTISH POWER PLC: FORMATION OF A TEMPORARY CONTRACTOR'S SITE COMPOUND: LAND TO NORTH OF CRUACHAN POWER STATION, TAYNUILT (REF: 12/00213/PP)

Agreed Planning 3 papers

Planning, Protective Services and Licensing Committee agreed this item on Wednesday 30 May 2012. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision Agreed to grant planning permission subject to the following conditions and reasons:- 1. The development shall be implemented in accordance with the details specified on the application form dated 25 th January 2012 and the approved drawing reference numbers: · Plan 1 of 1 (OB.02.01/01) unless the prior written approval of the Planning Authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Reason: For the purpose of clarity and to ensure that the development is implemented in accordance with the approved details. 2. In the event that the site has not been occupied for its intended purpose during the course of a continuous period of 18 months, the permitted use shall be deemed to have ceased and all structures, containers and materials shall be removed from the site, unless otherwise agreed in writing by the Planning Authority, and immediately thereafter the land shall be reinstated in accordance with details which shall be submitted to agreed in writing in advance by the Planning Authority. Reason: In the interests of amenity and to ensure that the site is reinstated to an appropriate and satisfactory standard. 3. This permission relates only to the use of the compound by contractors working within Cruachan Power Station and associated areas. Any structures, containers or materials shall only be sited on the land whilst maintenance or other contracted works are ongoing within Cruachan Power Station and shall be removed within 2 months from the completion of works on site. Reason: In accordance with the use applied for. 4. Any structures shall be used only for site offices and storage accommodation and shall at no time be used for residential purposes. Reason: In accordance with the use applied for. 5. No trees or shrubs within the application site as identified by the red line on Drawing No. (OB.02.01/01), shall be lopped, topped, felled or uprooted without the prior written approval of the Planning Authority. Reason: The landscape features hereby protected, are important to the appearance and character of the development site and their retention ensures that the development is screened from existing properties in the immediately surrounding area. 6. Within 3 months from the date of this permission, the portable building providing toilet facilities hereby approved shall be painted in a recessive colour and thereafter shall be maintained as such. The proposed recessive colour to be used shall be agreed in writing by the Planning Authority prior to the portakabin being painted. Any replacement portable building shall be painted in the same colour as the original structure was required to be painted, unless any variation thereof has been agreed in writing in advance by the Planning Authority. Reason: In the interests of visual amenity and in order to integrate the structure with its surroundings. 7. Permission is granted for the portable building providing toilet facilities and occupying the application site at the time of this permission for a period up to 30 th May 2022, following which it shall be removed from the site, unless on application permission has been granted for its retention for a further period by the Planning Authority. Reason This temporary structure is one of limited life expectancy, the future of which should be reviewed in the future in the interests of visual amenity. (Reference: Report by Head of Planning and Regulatory Services dated 3 May 2012 and supplementary planning report number 1 dated 28 May 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development Services

Delegated or Committee Planning Application Report and Report of Handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle ____________________________________________________________________________

Reference No: 12/00213/PP

Planning Hierarchy: Local

Applicant: Scottish Power Plc

Proposal: Formation of a temporary contractor’s site compound

Site Address: Land to north of Cruachan Power Station, Taynuilt, Argyll and Bute, PA33 1AN ____________________________________________________________________________

DECISION ROUTE

(i) Local Government Scotland Act 1973 ____________________________________________________________________________

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission

• Formation of a temporary contractors site compound for a period of 3 years; • Utilisation of an existing private vehicular access; • Utilisation of 10 existing on-site vehicle parking spaces and associated turning areas; • Utilisation of an existing private water supply; • Utilisation of an existing septic tank and partial soakaway.

(ii) Other specified operations

• None ____________________________________________________________________________

(B) RECOMMENDATION:

Having due regard to the development plan and all other material planning considerations, it is recommended that planning permission be granted subject to the conditions and reasons appended to this report. ____________________________________________________________________________

(C) HISTORY:

96/00776/COU - Change of use of rough ground to form a contractor’s compound and siting of portakabins – application approved 1st October 1996

02/01205/DET - Renewal of temporary consent 96/00776/COU – formation of a contractor’s compound – application approved 9th August 2002

02/01941/NMA - Non-material amendment to 02/01205/DET – amendment to number, size and position of portakabins – application approved 18th November 2002 05/00494/DET - Renewal of previous temporary consent 02/01205/DET – formation of a contractor’s temporary site compound – application approved 8th April 2005

08/00425/DET - Erection of a contractor’s temporary site compound – application approved 10th April 2008 ____________________________________________________________________________

(D) CONSULTATIONS:

Area Roads Manager - Response received 23rd February 2012 – Transport Scotland to advise

Transport Scotland - Response received 8th February 2012 – no objection

Public Protection - Response received 6th February 2012 – no objection ____________________________________________________________________________

(E) PUBLICITY:

‘Regulation 20 – Advert Local Application’ from the 9th February 2012 to the 1st March 2012. ____________________________________________________________________________

(F) REPRESENTATIONS:

Two representations have been received from;

• [name removed], 1 Railway Cottage, Falls of Cruachan, Lochawe (e-mail dated 12.02.2012) • [name removed], 1 Railway Cottage, Falls of Cruachan, Lochawe (e-mail dated 18.02.2012)

The concerns raised are summarised as follows:

• Part of the application site outlined by the red line belongs to us as the owners of 1 and 2 Railway Cottages.

Comment: Officers have liaised with the applicant’s agent in relation to the issue of land ownership who confirmed on the 23rd March 2012 that all of the land forming the application site identified by the red line is within the ownership of Argyll and Bute Council. Certification to that effect has been supplied and notice served on the Council’s, Estates Department dated the 25th January 2012.

• The proposed units to be erected within Area 2 will clearly be in view from my property so diminishing the quality of the immediate environment and my enjoyment of it.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12 00213 PP ROHReport 115 KB DownloadRead as text
PDF
1200213PP planReport 229 KB Download
PDF
SCOTTISH POWER PLC: FORMATION OF A TEMPORARY CONTRACTOR'S SITE COMPOUND: LAND TO NORTH OF CRUACHAN POWER STATION, TAYNUILT (REF: 12/00213/PP)Report 69 KB Download

At this meeting

Whole meeting
3MINUTESOn the agenda 4CIVIC GOVERNMENT (SCOTLAND) ACT 1982: PUBLIC ENTERTAINMENT LICENCEAgreed 5M AND K MCLEOD LTD: TEMPORARY USE OF FORMER AMBULANCE DEPOT FOR CLASS 6 (STORAGE OR DISTRIBUTION): FORMER AMBULANCE STATION, MANSE BRAE, LOCHGILPHEAD (REF: 11/02280/PP)Noted
6SCOTTISH POWER PLC: FORMATION OF A TEMPORARY CONTRACTOR'S SITE COMPOUND: LAND TO NORTH OF CRUACHAN POWER STATION, TAYNUILT (REF: 12/00213/PP)This decision
7ARGYLL AND BUTE COUNCIL: ERECTION OF NEW VEHICLE WORKSHOP, WELFARE BUILDING, GLASSHOUSE AND BIKE SHELTER INCLUDING NEW VEHICLE ENTRANCE AND ADDITIONAL PARKING: COUNCIL MAINTENANCE DEPOT, LUSS ROAD, HELENSBURGH (REF: 12/00219/PP)Agreed 8ARGYLL AND BUTE COUNCIL: INSTALLATION OF A BIOMASS BOILER INCLUDING PLANT ROOM AND WOODCHIP STORE: ISLAY HIGH SCHOOL AND BOWMORE PRIMARY SCHOOL, FLORA STREET, BOWMORE, ISLAY (REF: 12/00564/PP)Agreed 9TOWARD SAILING CLUB: ERECTION OF 5 KILOWATT WIND TURBINE (15 METRES HIGH TO BLADE TIP): TOWARD SAILING CLUB, TOWARD, DUNOON (REF: 12/00663/PP)Agreed 10MR AND MRS JOHN SMITH: ERECTION OF DWELLINGHOUSE, INSTALLATION OF PRIVATE SEWAGE TREATMENT FACILITY AND FORMATION OF NEW ACCESS: LAND NORTH WEST OF FINNART FARMHOUSE, FEUINS ROAD, PORTINCAPLE (REF: 12/00818/PP)Agreed 11NORTHERN ENERGY DEVELOPMENTS LIMITED: DEVELOPMENT OF LAND WITHOUT COMPLIANCE WITH CONDITION 1 OF PLANNING PERMISSION REFERENCE 08/00309/DET - ERECTION OF A WOOD FIRED COMBINED HEAT AND POWER PLANT AND FORMATION OF VEHICULAR ACCESS: LAND TOAgreed 14The Committee resolved in terms ofOn the agenda 12ENFORCEMENT UPDATE: 10/00319/ENAMENPrivate

Who was there

9 of 13 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleMember, apologies
RC
Councillor Robin CurrieMember, apologies
MD
Councillor Mary-Jean DevonMember, present
GF
Councillor George FreemanMember, present
FH
Councillor Fred HallMember, present
DK
Councillor David KinniburghMember, present
AM
Councillor Alistair MacDougallMember, apologies
RG
Councillor Robert Graham MacIntyreMember, present
DM
Councillor Donald MacMillan BEMMember, apologies
AM
Councillor Alex McNaughtonMember, present
ST
Councillor Sandy TaylorMember, present

All 13 on the meeting page

On this subject at Argyll and Bute

Search all
  1. SCOTTISH POWER PLC: FORMATION OF A TEMPORARY CONTRACTOR'S SITE COMPOUND: LAND TO NORTH OF CRUACHAN POWER STATION, TAYNUILT (REF: 12/00213/PP)This decision
  2. Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Agreed
  3. The scottish government on behalf of scottish power renewables (uk) limited: electricity act section 36 consultation for earraghail renewable energy development, comprising thirteen onshore wind turbines around 78mw, solar photovoltaic arraAgreed
  4. The scottish government on behalf of scottish hydro electric transmission plc: construction of approximately 13.3 km of 275 kv overhead line (ohl) from between a proposed substation at creag dhubh to the existing scottish power energy netwoAgreed
  5. Scottish hydro electric transmission plc: construction of approximately 13.3 km of 275kv over head line (ohl) from between a proposed substation at creag dhubh to the existing scottish power energy networks (spen) 275 kv ohl that runs fromAgreed
  6. The scottish government on behalf of drax cruachan expansion limited: electricity act section 36 consultation relevant to construction and operation of new underground power station and associated infrastructure adjacent to cruachan 1 to prAgreed

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies