Resolved

Decision Agreed to grant planning permission subject to the following conditions and reasons:- 1. The development shall be implemented in accordance with the details specified on the application form dated 21 March 2012 and the approved drawing reference numbers: 1:10,000 Location Plan, 1:500 Block Plan, 0130-AD-00174 D, unless the prior written approval of the Planning Authority is obtained for an amendment to the approved details under Section 64 of the Town and Country Planning (Scotland) Act 1997. Reason: For the purpose of clarity, to ensure that the development is implemented in accordance with the approved details. 2. For the avoidance of any doubt, the monopole and turbine blades shall be painted in RAL 7000 Dark Squirrel Grey, unless otherwise agreed in writing by the Planning Authority. Reason: In terms of visual impact and to integrate the wind turbine in its surroundings. 3. This permission shall be for a period of 20 years from the date of this permission. Within 6 months of the end of that period, or following the earlier cessation of use of the wind turbine for a continuous period in excess of 12 month, whichever is the earlier, the wind turbine and ancillary equipment shall be dismantled and removed from the site and the land reinstated in accordance with details to be submitted to and approved by the Planning Authority, unless a further planning application for the retention of the turbine is has been approved by the Planning Authority. Reason : In order that the Planning Authority has the opportunity to review the circumstances pertaining to the consent, which is considered to be of a temporary nature and in the interests of the visual amenity of the area. (Reference: Report by Head of Planning and Regulatory Services dated 4 May 2012, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Planning, Protective Services and Licensing Committee

Argyll and Bute Council Development and Infrastructure Services

Delegated or Committee Planning Application Report and Report of handling as required by Schedule 2 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2008 relative to applications for Planning Permission or Planning Permission in Principle _________________________________________________________________________

Reference No: 12/00663/PP

Planning Hierarchy: Local application.

Applicant: Toward Sailing Club

Proposal: Erection of 5 kilowatt wind turbine (15 metres high to blade tip).

Site Address: Toward Sailing Club, Toward, Dunoon _________________________________________________________________________

DECISION ROUTE

(i) Local Government Scotland Act 1973 _________________________________________________________________________

(A) THE APPLICATION

(i) Development Requiring Express Planning Permission

• Erection of wind turbine (Evance R9000 5kw); mounted on a 12.3 metre high monopole, three blades 2.75metres in length, 15 metres to blade tip height;

• Associated concrete foundation.

(ii) Other specified operations

• Installation of underground cabling. _________________________________________________________________________

(B) RECOMMENDATION:

It is recommended that planning permission be granted subject to the conditions, reasons and advisory notes set out below. _________________________________________________________________________

(C) HISTORY:

Planning permission (06/01155/DET) for the formation of a concrete slipway was granted on 14 August 2006 and implemented. _________________________________________________________________________

(D) CONSULTATIONS:

Public Protection (response date 12 April 2012): No objections in respect of noise and shadow flicker. NATS NERL Safeguarding (response dated 5 April 2012): No safeguarding objections. Advisory note recommended.

Ministry of Defence (expiry date 23 April 2012): No response.

Estates Department (expiry date 15 May 2012): No response.

Historic Scotland (response dated 2 May 2012): No objections in principle. Given small scale of turbine, no adverse impacts on setting of the Castle Toward designed landscape or Toward Castle. _________________________________________________________________________

(E) PUBLICITY:

Regulation 20(1) Advert (publication date 13 April 2012, expiry 4 May 2012).

(F) REPRESENTATIONS:

No letters of representation have been received.

(G) SUPPORTING INFORMATION

Has the application been the subject of:

(i) Environmental Statement: No (ii) An appropriate assessment under the Conservation (Natural Habitats) Regulations 1994: No (iii) A design or design/access statement: Yes

A Design and Access Statement has been submitted together with calculations and other manufacturer’s specifications.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
00663 location planPlan 477 KB Download
PDF
TOWARD SAILING CLUB: ERECTION OF 5 KILOWATT WIND TURBINE (15 METRES HIGH TO BLADE TIP): TOWARD SAILING CLUB, TOWARD, DUNOON (REF: 12/00663/PP)Report 121 KB DownloadRead as text

At this meeting

Whole meeting
3MINUTESOn the agenda 4CIVIC GOVERNMENT (SCOTLAND) ACT 1982: PUBLIC ENTERTAINMENT LICENCEAgreed 5M AND K MCLEOD LTD: TEMPORARY USE OF FORMER AMBULANCE DEPOT FOR CLASS 6 (STORAGE OR DISTRIBUTION): FORMER AMBULANCE STATION, MANSE BRAE, LOCHGILPHEAD (REF: 11/02280/PP)Noted 6SCOTTISH POWER PLC: FORMATION OF A TEMPORARY CONTRACTOR'S SITE COMPOUND: LAND TO NORTH OF CRUACHAN POWER STATION, TAYNUILT (REF: 12/00213/PP)Agreed 7ARGYLL AND BUTE COUNCIL: ERECTION OF NEW VEHICLE WORKSHOP, WELFARE BUILDING, GLASSHOUSE AND BIKE SHELTER INCLUDING NEW VEHICLE ENTRANCE AND ADDITIONAL PARKING: COUNCIL MAINTENANCE DEPOT, LUSS ROAD, HELENSBURGH (REF: 12/00219/PP)Agreed 8ARGYLL AND BUTE COUNCIL: INSTALLATION OF A BIOMASS BOILER INCLUDING PLANT ROOM AND WOODCHIP STORE: ISLAY HIGH SCHOOL AND BOWMORE PRIMARY SCHOOL, FLORA STREET, BOWMORE, ISLAY (REF: 12/00564/PP)Agreed
9TOWARD SAILING CLUB: ERECTION OF 5 KILOWATT WIND TURBINE (15 METRES HIGH TO BLADE TIP): TOWARD SAILING CLUB, TOWARD, DUNOON (REF: 12/00663/PP)This decision
10MR AND MRS JOHN SMITH: ERECTION OF DWELLINGHOUSE, INSTALLATION OF PRIVATE SEWAGE TREATMENT FACILITY AND FORMATION OF NEW ACCESS: LAND NORTH WEST OF FINNART FARMHOUSE, FEUINS ROAD, PORTINCAPLE (REF: 12/00818/PP)Agreed 11NORTHERN ENERGY DEVELOPMENTS LIMITED: DEVELOPMENT OF LAND WITHOUT COMPLIANCE WITH CONDITION 1 OF PLANNING PERMISSION REFERENCE 08/00309/DET - ERECTION OF A WOOD FIRED COMBINED HEAT AND POWER PLANT AND FORMATION OF VEHICULAR ACCESS: LAND TOAgreed 14The Committee resolved in terms ofOn the agenda 12ENFORCEMENT UPDATE: 10/00319/ENAMENPrivate

Who was there

9 of 13 attended
GB
Councillor Gordon BlairMember, present
RC
Councillor Rory ColvilleMember, apologies
RC
Councillor Robin CurrieMember, apologies
MD
Councillor Mary-Jean DevonMember, present
GF
Councillor George FreemanMember, present
FH
Councillor Fred HallMember, present
DK
Councillor David KinniburghMember, present
AM
Councillor Alistair MacDougallMember, apologies
RG
Councillor Robert Graham MacIntyreMember, present
DM
Councillor Donald MacMillan BEMMember, apologies
AM
Councillor Alex McNaughtonMember, present
ST
Councillor Sandy TaylorMember, present

All 13 on the meeting page

More from Argyll and Bute Planning, Protective Services and Licensing Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Beaufort wind limited: erection of 7 turbines (up to 149.9m to tip) and ancillary development and decommissioning of existing beinn ghlas wind farm: existing beinn ghlas wind farm, taynuilt (ref: 25/01240/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: 1. PP - A... Agreed Open
15 Sep 2026 Mr tony coogan: alterations to guesthouse to facilitate lawful use of existing roof space as ancillary guest house owner's accommodation: greencourt, benvoullin road, oban (26/00434/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Mrs faulkes: proposed alterations and erection of extension: 30 the green, craobh haven (ref: 26/01009/pp)Decision The Committee agreed to grant planning permission subject to the following conditions and reasons: Standard ... Agreed Open
15 Sep 2026 Scottish power renewables/machair wind limited: scottish government's marine directorate section 36 consultation on proposed machair offshore wind farm: site 15 km north west of isle of islay and 12.4 km west of isle of colonsay (ref: 26/01100/s36)Decision The Committee agreed that the Scottish Government’s Marine Directorate should be notified that Argyll and Bu... Agreed Open
15 Sep 2026 Development management performance update - fq1 2026/27Decision The Committee reviewed and agreed the content of the report. (Reference: Report by Executive Director with r... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies