Decision Noted the contents of the report and agreed to use on an ongoing basis the accompanying schedule of risk themes to provide an overview of progress in the continued development of an effective system of risk management. (Reference: Report by Head of Strategic Finance dated 8 March 2013, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides information on future development of the strategic risk register (SRR) and use of the SRR as a tool to support the work of the Audit Committee. It also updates the Audit Committee on ongoing developments in relation to risk management over the last few months.
Recommendation
2.1This is a progress report for noting.
3 DETAIL
Use of Strategic Risk Register
3.1There was significant discussion at the Audit Committee Away Day around risk management. This covered the role of the Audit Committee in relation to risk management, how the Audit Committee can use risk as a tool to target audit resource and as a focus for gaining assurance.
3.2The role of the Audit Committee is to be satisfied there is an effective system of risk management in place. It is not to take the role of actually managing risk.
3.3Audit activity should be risk based. Audit resources are limited and the Audit Committee wants to gain assurance in the most effective way possible. This means targeting scare audit resources at the areas of most significant risk.
3.4In targeting audit resources the Audit Committee will want to understand the risks facing the Council and the effectiveness of the controls related to these risks. This will provide the Audit Committee with information to reach a view on whether it has sufficient assurance that risk management is effective and also the overall effectiveness of the Council’s management control system. The mantra is “Risk, Controls, Assurance”.
3.5The SRR is a key tool in identifying the risks facing the Council. This should inform audit activity and should be kept under review. It was suggested that the SRR should be an item for consideration at each meeting of the Audit Committee not from the point of view of trying to manage the risks on the SRR but to consider how it gets assurance on the adequacy of controls and overall control framework.
3.6The SRR is in need of review and it is planned to carry this out and update the SRR over the next few months. Much of the work over the last year or so has been putting in place arrangements for regular review of operational risk registers (ORRs). The existing SRR is reviewed quarterly based on the review of ORRs but needs a more comprehensive review and update. It is proposed that in moving to a more risk focussed approach to the work of the Audit Committee that the following is adopted: • For June Audit Committee – Complete review of SRR and agree overall approach to utilising the SRR to support the work of the Audit Committee. • For September Audit Committee – Develop and agree more detail of how this will work and the specific areas of audit interest. • For December Audit Committee – Use the SRR and understanding developed at June and September meetings to set framework/guidance for 2014-15 internal audit plan. • For March 2014 Audit Committee – Consider draft 2013-14 internal audit plan against SRR and whether it provides the Audit Committee with assurance that audit activity is targeted on the controls for key risks.
3.7A copy of the current SRR is attached for information.
Ongoing Developments in Risk Management
3.8A quarterly update is provided to the Audit Committee on developments/progress in relation to risk management. These reports are not about making the Audit Committee responsible for managing risks but to provide assurance around the process and systems the Council has in place in relation to risk management.
3.9A report was presented to the Audit Committee on 7 December advising the Audit Committee on the progress against the risk management action plan for 2012-13. A copy of the risk management action plan for 2012-13 is attached to this report.
3.10Whilst work is progressing against the actions shown in the risk management action plan 2012-13, there are two items currently classified as being off track These are:
• Deliver and Develop Training Programme to ensure People are equipped to Manage Risk, and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ...
Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna...
External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.