Decision The Board:- i. Endorsed the next steps as outlined within the submitted report and appended ‘Oban Marine Tourism Study’ and agreed these are taken forward in a phased and programmed manner. ii. Recommended to the Council that it progresses the business case process and undertakes a proportionate technical assessment of the proposal, noting that this process will be taken forward in partnership with HIE and will have input from the relevant stakeholders. iii. Agreed that the proposal for redevelopment of the White Building, an integral part of the study’s proposals, is progressed in a manner that allows its redevelopment to be progressed towards completion as early as possible.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Oban Marine Tourism Study Report on Consultations IronsideFarrar 111 McDonald Road Edinburgh, EH7 4NW Tel: 0131 550 6500 www.ironsidefarrar.com
7960 / March 2013 Executive Summary
Executive Summary In developing proposals for marine tourism in Oban Bay the key messages are:
significant and sustainable growth opportunities exist for marine tourism for Oban across all areas including cruise, charter, sailing, excursion trips , activity and participatory sports
a breadth of interests should be encouraged to contribute and secure economic /tourism benefits by capturing growth across the market and building the profile of Oban as a destination and hub for marine tourism
Argyll and Bute Council and Highlands and Islands Enterprise (HIE) will give consideration to investment in the essential public infrastructure under CHORD / HIE, funding programmes to secure economic benefits
public investment is required to create the appropriate infrastructure and this should if possible address all users/ sectors and be based on the North Pier (South)
a momentum is required to advance the project with a clear focus on delivery
2.0MARINE TOURISM OBAN Marine Tourism West Scotland Opportunity Oban Agreement on Markets & Breadths of User Needs/ Sectors Agreement or need for Infrastructure - North Pier
3.0DEVELOPING PROPOSALS THROUGH CONSULTATION Introduction Review of Proposals Oban Marine North Pier Addressing Barriers to Delivery Issues Identified through Consultation
4.0DEVELOPING A RECOMMENDATION Objective Next Steps
APPENDICES Appendix 1: Workshop 3 Slides. Developing a Strategy through Facilitated Stakeholder Planning
7960 Oban Marine Tourism Study - Report on Consultations. March 2013 i ii IronsideFarrar Introduction 01 1.0 MARINE TOURISM FACILITIES – OBAN BAY
1.1Introduction Argyll and Bute Council and Highland and Islands Enterprise (HIE) are keen to support opportunities to develop Marine Tourism in Oban Bay.
Argyll and Bute Council and Highlands and Islands Enterprise appointed Ironside Farrar to assist the key stakeholders identify a viable and deliverable scheme supporting marine tourism opportunities.
1.2Aims and Objectives Working through a Core Group including (A&BC / HIE/ Oban Bay Marine Ltd / Oban Marina / RYA / The Crown Estate / Visit Scotland) the commission involved a series of facilitated workshops and one-to-one consultations with the aim of: Review proposals identified to support Marine Tourism Identify the optimal configuration of marine tourism facilities in Oban Bay Seek to match demand to potential market needs that minimise displacement Promote opportunity for existing berthing / mooring, visitor pontoons/ transit marina, step ashore facility, connectivity with Oban Marina/Kerrera Identifying the appropriate scale, configuration and function of transit marina/visitor pontoons in Oban Bay Identify a Way Forward
1.3Approach & Methodology Ironside Farrar role has been to assist and facilitate all parties address barriers to successful implementation and to assist in identifying a platform for the project to be advanced.
The study has relied heavily on studies prepared by Oban Bay Marine; assessments by Argyll and Bute Council and wider contextual reports addressing Sailing Tourism in Scotland. The primary source of information was consultation through the Core Group and one-to-one consultation with stakeholders. The consultants record their thanks to the assistance provided by all parties and the willingness of all parties to share information. The consultants appreciate the time and willingness of all parties to engage and share information and commit to a successful scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Alignment with transport scotlandDecision The Board:- i. Noted the paper and endorsed the partnership approach proposed to coordinate the future plann...
Oban bay/harbour interim business caseTo endorse the Interim Business Case and to recommend to the Programme Management Board that £1,840,000.00 be drawn d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.