Decision The Board:- i. Approved the proposed utilisation of the remaining £4.865 million; ii. Instructed Officers to progress discrete business cases in order that the drawdown if the remaining monies can be approved by the CHORD Programme Board and the Council; iii. Instructed Officers to advise the CHORD Programme Board of the intended utilisation of the remaining £4.865 million; and iv. Agreed that the CHORD Project Manager would come back to the CHORD Project Board with an updated communication plan and update on timescales. Councillor MacIntyre , being unable to find a seconder to his intended amendment, requested, under the terms of Standing Order 10.5, that his dissent from the decision taken be recorded in the Minutes. (Ref: Report by CHORD Programme Manager dated 20 th March 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
DEVELOPMENT AND INFRASTRUCTURE SERVICES 27 MARCH 2013
OBAN CHORD - PROPOSED PROJECT PACKAGE FOR DELIVERY
1.0SUMMARY 1.1 In early 2012, the Oban CHORD Project Board and the CHORD Programme Board approved an Interim Business Case (IBC) for Oban CHORD. The IBC was prepared to allow the Project Board to make decisions on the way to proceed, accepting that the Case would evolve as the various elements were progressed and issues regarding, deliverability, affordability and risk became clearer. At that stage a project package of £1.84 million was approved.
1.2Given the current position with the £1.84m package of works –see Table 1 at 3.1 below coupled with a clear desire to focus on “delivery” of the Oban CHORD project within the next three years from both the local members and the community, an Oban CHORD & Lorn Arc TIF workshop was held on the 28th February 2013 for Oban, Lorn and the Isles (OLI) members. The aim of the workshop was to outline and discuss how best to “deliver” the Oban CHORD project within the next three years. The workshop was well received by Members.
1.3Subsequently, the Chair of the Oban CHORD Board asked the CHORD Project Team to bring forward a paper based on the presentation given at the workshop to the Oban CHORD Board for approval, outlining:
• the current position with the £1.84 million IBC approved projects; • the intended utilisation of the remaining £4.865 million; • how the utilisation of the remaining monies complements the £1.84 million already approved; • the proposed timescales for the FBCs; and • timescales for the delivery of the complete package of CHORD projects
2.0RECOMMENDATIONS 2.1 It is recommended that the Oban CHORD Project Board:
• approves the proposed utilisation of the remaining £4.865 million • instructs officers to progress discrete business cases in order that the drawdown of the remaining monies can be approved by the CHORD Programme Board and Council • instructs officers to advise the CHORD Programme Board of the intended utilisation of the remaining £4.865 million
3.0DETAIL 3.1 Oban CHORD has a funding allocation of £6.9 million. An Interim Business Case was endorsed by the Board on 6th January 2012 which recommended the release of £1.84 million of funding to progress 3 key elements – Traffic Management; Transport Interchange; and Reconfiguration of the Bay – Table 1 below outlines how funds are currently attributed. Table 1 Breakdown of the £1.84m
Soroba Soroba Argyll Transport George North pier Rd Rd/Miller Square Interchange St/Stafford Pontoons /Oban Road St High School £370k £30k £100k £340k £700k £300k On Hold. Now To be Now part of Now part On hold awaiting Now funded delivered proposed of outcome of outwith from by public proposed Marine Tourism CHORD Roads Roads realm public Review/Business delivery budget works realm Case timescale works
3.2Given the above position with the current £1.84m package of works coupled with both the CHORD Board’s and OLI Members’ clear desire to focus on “delivery” of the Oban CHORD project within the next three years, the CHORD Project Team reviewed the current approach and came forward to the Workshop on the 28th February with the proposals outlined in Appendix A - Oban CHORD and Lorn Arc TIF Members Workshop.
3.3The proposed way forward outlined in detail in Appendix A is to have four distinct project areas:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Alignment with transport scotlandDecision The Board:- i. Noted the paper and endorsed the partnership approach proposed to coordinate the future plann...
Oban marine tourism facilities reviewDecision The Board:- i. Endorsed the next steps as outlined within the submitted report and appended ‘Oban Marine Tou...
Oban bay/harbour interim business caseTo endorse the Interim Business Case and to recommend to the Programme Management Board that £1,840,000.00 be drawn d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.