Resolved
To note the terms of the update and to agree that the Chair write to Oban Bay Marine, given the information provided to the Board by one of the non-core members.
Oban CHORD Project Board noted this item on Friday 6 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the terms of the update and to agree that the Chair write to Oban Bay Marine, given the information provided to the Board by one of the non-core members.
HIGHLIGHT / PROGRESS REPORT PROJECT NAME: Oban CHORD Project Manager: Joanne Casey Reporting Period: 21/11/11 – 06/01/12 Date report prepared: 13 December 2011 Development of the Full Business Project stage: Project stage completion date: 06 January 2011 Case
Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater
Progress – please refer to Project Plan Key products completed this period Key products outstanding this Revised Key products for next reporting Delivery date (including those completed ahead of schedule) period delivery date period (including brief explanation of why product outstanding) Preparation of Interim Business Case to allow Progress to Programme Board 31/01/2012 first application for capital drawdown and Executive for approval of capital drawdown Preparation of updated OAP Refresh document following comments from Project Board which is now available online as a ‘Consultation Draft’ Public Consultation held 22nd November
o:\c_oban\ob01_bay_harbour\board_papers\d_06_01_12\ob_highlight_prog_rep_jan 2012final.doc Risk Management – please refer to Risk Register (updates risks below in bold italic text) No risk updates
Budget Management – please refer to Resource Allocation Schedule Total budget available to complete FBC stage: £175,000 Forecast expenditure for current financial year Actual expenditure to date Variance explanation if required:
£175,000 £127,334.75
Any further information
PID documents: including appendices – i.e. risk register, project plan, resource allocation schedule and communications plan have all been updated to reflect current position – (version 1.2).
Interim Business Case provided for comment and approval to proceed with the drawdown of capital monies requested
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIGHLIGHT/PROGRESS REPORT: OBAN BAY/HARBOURReport | 67 KB | DownloadRead as text |
Follow Oban CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Mar 2013 | Highlight/progress reportDecision The Board:- i. Noted the information provided; ii. Agreed that a consultation report on traffic management w... | Noted | Open |
| 27 Mar 2013 | Oban chord - proposed project package for deliveryDecision The Board:- i. Approved the proposed utilisation of the remaining £4.865 million; ii. Instructed Officers to... | Approved | Open |
| 27 Mar 2013 | Alignment with transport scotlandDecision The Board:- i. Noted the paper and endorsed the partnership approach proposed to coordinate the future plann... | Noted | Open |
| 27 Mar 2013 | Oban marine tourism facilities reviewDecision The Board:- i. Endorsed the next steps as outlined within the submitted report and appended ‘Oban Marine Tou... | Agreed | Open |
| 6 Jan 2012 | Oban bay/harbour interim business caseTo endorse the Interim Business Case and to recommend to the Programme Management Board that £1,840,000.00 be drawn d... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.